140P1321Q0044_Statement_of_Work___San_Antonio_Missions__Replace_Fire_and_Security_Systems_-_SOW_7-12-21_(1)_-_Copy.docx
DOCX document 658 KB Posted
- Attached to
- SAAN REPLACE VC INTRUSION ALARM AND CCTV Federal contract opportunity
- Solicitation number
- 140P1321Q0044
About this file
This statement of work outlines requirements for a construction project to replace fire and security systems and add closed circuit security cameras at the San Antonio Missions National Historical Park visitor center. The scope of work includes removing existing systems over 15 years old and installing new addressable fire alarm and intrusion detection systems, along with interior and exterior security cameras, to be integrated into an existing video management system. Key requirements include installing dual technology motion detectors, duress alarms, exterior notification devices in multiple colors, and redundant intrusion detection. The contractor must design and install the systems in compliance with applicable codes and standards, and provide as-built drawings, warranties, training and maintenance manuals upon completion. The solicitation number is 140P1321Q0044 and was issued by the Department of the Interior National Park Service Intermountain Region for this construction project at the San Antonio Missions National Historical Park.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 140P1321Q0044__Request_for_Quote__Fire_and_Security_Systems__San_Antonio_Missions.pdf | ||
| 140P1321Q0044_Construction_Wage_Determination_TX_20210231___gov_-_Copy.pdf | ||
| Sol_140P1321Q0044.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
San Antonio Missions NHP San Jose Visitor Center San Antonio, TX
SCOPE OF WORK
REPLACE FIRE AND SECURITY SYSTEMS
ADD CLOSED CIRCUIT SECURITY CAMERAS
SAAN
PMIS 229657
July 12, 2021
NATIONAL PARK SERVICE
INTERIOR REGIONS 6 | 7 | 8
Table of Contents
| 1 | Project Overview | 4 |
| 1.1 | Location and Facilities | 4 |
| 1.2 | Project Description | 4 |
| 2 | Bid Add Option | 4 |
| 3 | Codes and Standards | 5 |
| 4 | Project Requirements | 5 |
| 4.1 | General | 5 |
| 4.2 | Performance Scope | 6 |
| 4.3 | Secruity System Requirements | 8 |
| 4.4 | Cable and conduit | 9 |
| 4.5 | Existing Fire and Security Alarm Equipment | 9 |
| 4.6 | Pre-testing and Final Testing | 9 |
| 4.7 | Training | 10 |
| 4.8 | Inspection and Tests | 10 |
| 4.9 | Warranty | 10 |
| 4.10 | Design Submittals and Shop Drawings | 10 |
| 4.11 | As-built Drawings | 10 |
| 4.12 | Operation and Maintenance Manual | 10 |
| 5 | Additional Requirements | 11 |
| 5.1 | Project Schedule | 11 |
| 5.2 | Safety | 11 |
| 5.3 | Security | 12 |
| 5.4 | Quality Assurance | 12 |
| 5.5 | Travel | 13 |
| 5.6 | Progress Payments | 13 |
| 5.7 | Project Meetings | 13 |
| 6 | Site Coordination | 14 |
| 6.1 | Existing Conditions and Coordination | 14 |
| 6.2 | Special Construction Conditions | 14 |
| 6.3 | Staging Areas | 14 |
| 6.4 | Work Zones | 14 |
| 6.5 | Protection of Public | 15 |
| 6.6 | Parking of Work Vehicles | 15 |
| 6.7 | Temporary Materials, Equipment and Services | 15 |
| 6.8 | Hot Work Permit | 15 |
| 6.9 | Smoking | 15 |
| 6.10 | Electricity | 15 |
| 6.11 | Telephone | 15 |
| 6.12 | Water | 15 |
| 6.13 | Sanitary Facilities | 15 |
| 6.14 | Hauling Restrictions | 15 |
| 6.15 | Waste Management | 15 |
| 7 | Submittals | 16 |
| 8 | Final deliverables | 16 |
9 Attachments………………………………………………………….……..………………17
Project Overview Location and Facilities The project involves the facility at the San Antonio Missions National Historical Park (SAAN), San Jose Visitor Center, located at 6701 San Jose Drive, San Antonio, TX 78214. The scope of work for this project includes replacement of an existing fire and security system with the design and installation of a fire and security intrusion detection system, installation, and integration of several CCTV cameras on the interior and exterior of the San Jose Visitor Center.
Project Description Existing systems generally comprise commercial fire and security systems over 15 years of age. Many of these systems have exceeded their design life and/or lack coverage or features required by SAAN. This Scope of Work (SOW) is for the of replacement fire and security detection systems and additional security cameras in San Jose VC at SAAN. This project is intended to replace an aged fire and intrusion detection system as well as expand the facility security capabilities of the park by adding CCTVs to an existing system.
The project requires design and installation of fire and security systems. The fire alarm system must provide complete coverage, as defined by NFPA 72, and the intrusion system must provide redundant over lapping coverage using a minimum of dual technology devices offering pet friendly sensitivity. The fire alarm and security systems may be combined, or separated, and may use wireless technology where additional devices are required, however must meet all applicable codes and manufacture requirements. If combined system is used, it must be listed for commercial fire application. The scope allows flexibility for the most efficient methods of integration of additional CCTV however must meet and be approved by park Chief Law Enforcement Officer. At the completion of the new installation, complete demolition and appropriate disposal of existing systems and equipment is required and patching and painting of existing surfaces as required.
One goal of the project is to reuse existing infrastructure and equipment where possible which includes primarily cable, conduit and junction boxes. Visual inspection and continuity tests shall be performed on cable that the contractor deems ready to reuse. If the existing cable is used, it must meet the NEC requirements and covered under the warranty period.
The Contractor shall be responsible for all necessary work to achieve required project outcomes, including labor, equipment, tools, personal protective equipment (PPE), coordination with Authorities Having Jurisdiction (AHJ), internal construction permits, incidental design, travel, and other related expenses.
The site visit will occur on August 13, 2021 at 9:00 a.m. Please RSVP to the CO by August 10, 2021.
Options
A: One (1) year monitoring of the new fire and security system for the Visitor Center and six (6) other buildings currently being monitored by others.
B: New data storage server for the camera monitoring portion of the security system, to be specified by the contractor to accommodate to larger quantity of cameras.
Codes and Standards The Contractor is responsible for securing all needed permits and for ensuring compliance with all federal, state, and local codes and design standards, latest editions, including the following. If discrepancies are found between the SOW and codes or standards as referenced in this SOW, the codes or standards shall govern, unless noted otherwise.
A. International Building Code (IBC, International Code Council) (Most current edition) B. National Electrical Code (NFPA 70) (Most current edition) C. International Fire Code (IFC, International Code Council) (Most current edition) D. National Fire Protection Association Codes (NFPA) E. Occupational Safety and Health Administration (OSHA)
Project Requirements General The Scope of Work (SOW) requires the Contractor to provide a complete code compliant combination fire alarm/security system for the San Jose Visitor Center
San Jose Visitor Center
a. General: Main visitor center for San Antonio Missions NHP. Contains museum area with interpretive displays, retail, office, meeting spaces, storage, kitchen/break rooms, outdoor break areas, restrooms, lockers, shower and theater spaces.
b. Approximate building area: 13, 312 square feet (sf)
c. Existing systems: 2 separate security systems, one in the old Los Compadres (Mission Heritage Partners) area. Commercial automatic sprinkler system with light hazard coverage. Johnson Control/Simplex Grinell monitored fire alarm system with detectors and manual pull stations. Tyco intrusion detection system with door contact alarms, wireless motion detectors. The "call out" to monitor station is through a dry contact signal to the Tyco intrusion system through a telephone line.
A. Replace the existing fire and security systems with new systems and related field components. The systems shall meet both fire protection and site security requirements and shall transmit associated point of address signals to local monitoring station (Park designated) B. In accordance with this SOW, the Contractor shall determine all required site-specific information required for the execution of this project.
C. National Park Service Regional Structural Fire Management Officer is the Authority Having Jurisdiction (AHJ) for the fire protection features of this project.
D. The systems shall be designed and installed to meet NFPA 72 (most recent edition) and associated current codes.
E. Existing design and building plans are Attachment A.
Performance Scope A. Provide a complete coverage new addressable fire alarm/security system as required by the SOW, applicable codes, and other project requirements.
B. Fire alarm design documents shall be developed in accordance with referenced codes, standards, by persons who are qualified and experienced in the design of fire alarm systems in accordance with NFPA 72, National Fire Alarm Code equipment and personnel definitions. Minimum acceptable qualifications is a NICET III in the design of fire alarm systems or a Fire Protection Engineer.
C. The fire alarm system installation supervisor shall be qualified and experienced in the design of fire alarm systems in accordance with NFPA 72, National Fire Alarm Code equipment and personnel definitions. This supervisor shall be trained and certified by the manufacturer of the equipment being installed, and there shall be minimum of one Fire Alarm NICET level II on-site throughout the installation.
D. The security design and installation must be developed and installed by security professionals with a minimum of ten years designing and installing commercial security systems in the state of Texas.
San Jose Visitor Center
a. Removal of existing fire and intrusion panel and alarm devices
b. Inspection of existing cable, raceways, and junction boxes
c. Removal of unsatisfactory cable, raceways, and junction boxes for re-use in new system.
d. Removal of unused cable inside abandoned raceways.
e. Repair and replacement of cable, raceways, and junction boxes
f. Installation of new fire and intrusion alarm system devices. Includes but is not limited to: smoke alarms, heat detectors, glass break sensors, strobes, horns, keypads, door contacts, panic buttons, relays, and annunciators.
g. Panic (duress) device must be placed at areas of cash exchange locations – shall be programmed to be silent alarm.
h. Intrusion access panel must be programmed with a common silent duress access code: Using the code will disarm all devices and allow access to the building, however, will provide a silent duress alarm to the Chief Law Enforcement Ranger designated monitor station.
i. Installation of new fire and intrusion alarm panel. Fire and intrusion alarm will be disabled during this time and will require an estimated downtime of 5 days, during which the Government will provide a Fire Watch.
j. Provide a complete set of shop drawings of the automatic fire alarm system consistent with NFPA 72.
k. Commissioning of new fire and intrusion alarm system.
l. Provide for approval by Chief Law Enforcement Ranger a sketch or drawing of proposed camera locations with an estimated coverage area. Combined fire/security system and add security cameras
m. Fire detection device coverage shall be expanded to provide “complete detection” throughout the building. Additional devices shall be installed as required to comply with referenced standards.
n. Exterior notification devices for both fire and security
o. Security system shall incorporate duress, personal panic/duress and active shooter alarms complete with corresponding exterior notification devices (sirens, strobes of different colors)
p. Include redundant security detection coverage with combination door contact, break glass, and motion detection throughout. At a minimum, two devices shall be installed in each room with a window or door in the exterior wall.
q. All motion detectors shall be dual technology type (pet friendly)
r. Provide cellular call out for fire/security systems to park designated monitoring station in accordance with referenced standards
s. All devices (fire and security) shall be wireless type in accordance with referenced standards
t. Installation of 11 interior dome cameras, with final locations to be determined by the contractor and confirmed with Park Law Enforcement. The cameras should primarily observe entry and egress points as well as places where financial transactions take place.
u. Installation of 6 exterior dome cameras. These cameras shall be installed to observe intrusion activity in the four courtyards, the utility enclosure, and the outdoor hallway leading to the entry door of the Los Compadres office.
v. Installation of 6 high resolution fixed cameras. These cameras shall be installed to observe activity on the grounds of the park not covered by the dome cameras. Special areas of interest are the area along the south of the visitor center, near Napier Ave; the western portion of the grounds facing Roosevelt Ave; the grounds north of the visitor center leading up to the mission walls, and the grounds near the east of the visitor center, ideally covering the blind spots that currently exist in the parking lot CCTV coverage area.
w. Commissioning of new cameras and integration into existing data storage server. Firmware upgrades shall be completed by the contractor prior to integration of new system.
1) Existing server uses a Milestone XProtect Smart Client 2018 R3 Ver 12.3a (64-bit) Build 12100 or approved equal
x. All cameras shall be connected to the software system to be accessed remotely / off-site by the Chief Law Enforcement Ranger or their designated person.
y. Replacing the monitor of the CCTV system with a 32” LCD Monitor with a minimum 1080P, with two (2) HDMI inputs, and one (1) USB.
z. Upgrading the CCTV server storage capabilities and operating system (option bid B).
aa. Contractor shall exercise “good engineering judgment” to design a User-friendly systems and minimize the use of multiple power supplies and control units, and not compromise recognized codes (NFPA) or manufacture requirements.
ab. The systems shall report all related security and fire alerts to the Park designated monitor station. The fire alarm system ‘alarm event’ shall always maintain the highest priority in signal transmission. The Contractor is responsible for making the necessary connections for code compliance.
ac. All systems provided shall be from a common manufacturer. Surge protection requirements
ad. Primary AC circuit requires listed surge protector for all fire alarm control units. It shall be accessible and located adjacent the fire alarm control cabinet.
ae. All low voltage circuits entering or leaving the building as required by NEC section 800. The devices shall be mounted in an accessible junction box and marked with the circuits they serve.
af. All fire alarm devices shall be neatly marked with SLC/Address number on the base of the device.
NOTE: All Cameras must be compliant with the National Defense Authorization Act for Fiscal Year 2019, section 889 Prohibition on Certain Telecommunications and Video Surveillance Services or Equipment. This clause is included in this as an attachment and prohibits the use of equipment from certain manufacturers in government facilities. The list includes but is not limited to: Huawei Technologies, ZTE Corporation, Hytera Communication Corporation, Hangzhou Hikvision Digital Technology Company, Dahua Technology Company, and all subsidiaries. Contractor is responsible for ensuring submitted equipment is compliant.
Fire Alarm System Requirements A. Detection: The Contractor shall determine the type and quantity and location of devices as required to achieve the scope requirements B. Motion Sensors: Dual technology motion detectors be provided C. Duress Alarms: Panic alarm (duress) shall be provided D. Alarm Notification: Intrusion notification shall be 120 db exterior blue strobe/siren E. Additional Camera requirements as referenced in 4.2 F. Monitor replacement to 32” LCD as referenced in 4.2
Security System Requirements A. Fully Operational:
1. As new equipment is installed, it shall be labeled “NOT IN SERVICE" until new equipment is accepted.
2. Tags from new equipment shall be removed when put into service, and existing fire alarm equipment shall be tagged "NOT IN SERVICE" until removed from building.
B. Equipment Removal:
1. Package and legally dispose of the operational fire alarm and detection equipment that has been removed.
2. Damaged surfaces shall be patched and painted according to match existing to the satisfaction of the COR.
Pre-testing and Final Testing A. Prior to arrival of a Government representative for system acceptance/commissioning of the automatic fire alarm system, the system shall be 100% pre-tested in accordance with NFPA 72, National Fire Alarm Code and manufacture requirements. All test results shall be recorded. Any device or component failing pre-testing or not meeting the performance requirements, shall be repaired, or replaced and re-tested.
B. Upon final pre-testing, the Contractor shall demonstrate the performance of the installed system through the commissioning process with the COR, Security and Fire AHJ’s.
Training A. Manufacturer's factory-authorized service representative shall provide services to demonstrate and train Government maintenance personnel after completion of commissioning as specified below:
1. Provide four (4) hours of operational, maintenance, and troubleshooting training on the fire alarm system to Park maintenance personnel.
2. Provide at least three one (1) hour of fire system operational training sessions to the primary user of the system, typically the Park Ranger and/or the Facility staff.
3. Provide on laminated paper specific written instructions posted at control panels describing step-by-step procedures for seasonal electrical shutdown and startup of fire alarm system. Instructions should include contact information for troubleshooting purposes.
Inspection and Testing A. The Contractor shall provide:
1. Written certification the equipment has been inspected and tested by a manufacturer's certified representative.
2. Written certification the equipment is installed in accordance with the manufacturer's recommendations and ULI listings.
3. Written certification the equipment is in proper working order.
4. Completed Record of Inspection and Testing form(s) as outlined in NFPA 72 complete with device sensitivity values.
5. All required test equipment, including, but not limited to:
a. Heat producing devices (acceptable to manufacturer) for testing heat detectors.
b. Electrical test equipment, such as multi-meters
c. Smoke generating device for functional test, acceptable to manufacturer.
B. An AHJ Government representative will visit the job site to witness final acceptance tests when advised by the Contractor that the work is completed and ready for test. If the work has not been completed or the final acceptance tests are unsatisfactory, the Contractor shall be responsible for the Government’s extra expenses for reinspection and witnessing the re-testing of the work. Such extra fees shall be deducted from the payments made by the Government to the Contractor.
C. A Contractor representative shall be present at the site until an AHJ Government representative has accepted the system.
D. All Contractor testing shall conform minimally to the requirements of NFPA 72. Contractor testing shall include 100 percent of all devices, appliances, interfaced systems and control unit functions. The Contractor shall record the results of all tests as required by NFPA 72, Inspection & Testing Form.
Warranty A. Cleaning: Maintenance of the system shall be conducted by qualified personnel. Monthly, quarterly, semiannually and annual requirements of the fire/security alarm system as outlined by NFPA 72 Inspection and testing chapter.
B. Warranty and maintenance: Written warranty is required at the completion of the installation. Warranty shall be for a period of one (1) year and shall cover both parts and labor for the entire system installed. The language of the warranty shall include the following:
a. Devices require complete cleaning prior to the expiration of warranty.
b. Shall include 6 month written record of sensitivity settings (2 per warranty period)
c. Shall include provisions for ten minor programming changes.
d. Shall include provisions for a 4 hour response time for emergency related alarm conditions, and 12 hour response to trouble or supervisory conditions.
e. Shall include provisions for incurred costs to repair problems related to Spurious Alarms.
Design Submittals and Shop Drawings A. Shop Drawings: Shop drawings shall be prepared by the Contractor, submitted to the Government, and approved prior to work commencing on site. Note that As-Built drawings for the buildings and existing systems included in this project are generally not available. The Contractor shall document existing building conditions (floor plans, site plan, etc) as required to develop the proposed design / shop drawings. Shop drawings shall be revised by the Contractor as requested by the COR until they are approved at no additional cost to the Government.
B. Attachment A are the existing drawing for the fire alarm and intrusion system. Shop drawings consistent with industry standards are required for review by Fire and Security AHJ’s.
As-Built Drawings A. Provide “As-Built” versions of shop drawings based on actual installation conditions and any project modifications.
B. Provide both hard copy and electronic versions of as-builts. Hard copy versions shall be sheets of the same size (“C" Size 24" x 36" Preferred). Electronic versions shall be both .DWG and .PDF type.
Operation and Maintenance Manual A. Provide an Operation and Maintenance (O&M) Manual within fourteen (14) days after project completion. The O&M Manual shall including the following at a minimum:
1. All approved submittals.
2. Manufacturer maintenance instructions for all installed equipment.
3. Table of manufacturer, model, and serial number of all installed equipment.
Additional Requirements Project Schedule A. The Contractor shall develop a detailed project schedule. This schedule shall include key milestones of the project, including start and finish dates, as well as proposed work times. The Contractor shall submit this schedule for review and approval prior to work proceeding. The Contractor shall actively maintain and update the schedule as required by the COR.
Safety
A. The Contractor shall submit the following prior to work proceeding and maintain a copy onsite during the project:
1. Material Safety Data Sheets (MSDS)
2. Project specific site safety plan. This plan shall include the following at a minimum:
a. Description of work
b. Nomination of project management staff, including site safety representative
c. Contact information for project management staff
d. Contact and location information for local emergency services
e. Description of anticipated high safety risk activities, including activity hazard analyses and safety control measures
f. Site protection and traffic control measures, including sketches to illustrate provisions.
B. Contractor shall be responsible for complete and strict compliance with the park policies.
C. The Contractor shall fully comply with 29 CFR 1926.
D. The Contractor shall provide temporary safety barriers, as necessary, to provide a safe, hazard-free space for workers, pedestrians, and vehicles during construction.
E. The Contractor shall install protective measures to contain dust and debris during construction to assure a safe and irritant free work environment for building occupants. Return all areas to the original condition at the conclusion of work.
F. The Contractor shall remove and dispose of excess materials, debris, or waste at an approved off-site location in accordance with applicable Local, Tribal, State and Federal laws and regulations, and pay any related fees. Burning or burial of materials is not permitted.
Security A. The Contractor shall secure new equipment and materials. Limited storage space is available for the Contractor. However, the location of trailers, storage, sheds and staging areas shall be approved by the COR.
B. The Contractor shall comply with all park security policies.
Quality Assurance A. The Contractor shall develop and maintain a quality program to ensure services are performed in accordance with commonly accepted commercial practices. The quality of all work shall be the responsibility of the Contractor. Inspect and test all work as needed to ensure that the quality of materials, workmanship, work, finish, and functional performance is in compliance with the SOW.
B. The Government shall periodically evaluate the Contractor’s performance in accordance with this SOW.
C. All new equipment shall conform to the manufacturer’s instructions and guidelines for installation and start-up.
Travel A. Contractor shall be responsible for all travel related expenses for this project, including mobilization of equipment, tools, materials, labor, lodging, meals, and per diem.
Progress Payments A. Progress payments during work will be based on the percentage of work completed on items listed on the approved Bid Schedule, Schedule of Values or by Contract Line Item. Actual work completed and in place will form the basis for payment. Verification of the percentage (%) complete shall be initiated by the Contractor for approval by the COR. The Contractor shall make the computations for payment based on the Government’s verification of work completed and in place for any periods for which progress payments are requested.
B. The Contractor shall furnish the originals of all field notes, invoices and payroll reports, and all other records relating to the basis for payment, to the CO, who shall use them as necessary to determine the final amount of progress payments. The Contractor shall retain copies of all such material furnished to the CO.
Project Meetings A. Pre-construction meeting: The CO will arrange an on-site pre-construction meeting with the Contractor. Notes of the meeting shall be recorded by the Contractor and will be distributed after the meeting. The meeting agenda shall include the following as a minimum:
1. Park rules and regulations
2. Correspondence procedures
3. Progress meetings
4. Lines of authority
5. Roles and responsibilities
6. Coordination of sub-Contractors
7. Submittal process
8. Project schedule
9. Progress payments
10. Acceptance/rejection of the work
11. Labor standards and labor law application
12. Payroll reports
13. Modifications
14. Accident Prevention Plan and accident reporting
15. Medical emergency processes, availability, emergency numbers, and contacts
16. Park permits, burning work waste, rules of the road, alcohol use, housekeeping, firearms, pets, natural and cultural resource concerns
17. Visitation, access, and public relations
18. Site and schedule coordination
Site Coordination Existing Conditions and Coordination A. The Contractor shall fully inform himself regarding any and all peculiarities and limitations of the spaces available for the installation of all work and materials furnished and installed under the contract. Coordinate with all other trades, as well as with existing conditions, in advance of the work, including requirements for openings, recesses and chases in the walls, partitions, framing or openings and routing of piping, conduit, etc. relative to each trade to alleviate conflicts.
Special Construction Conditions A. The project shall be completed while the SAAN buildings remain operational. Scheduling of work shall be in close cooperation with the SAAN Facility Managers. Building tenants shall have no unplanned functional disruptions resulting from the Contractor’s planning and execution of project work and requirements. Buildings shall remain operational during normal business hours.
B. SAAN buildings generally operate from 8:00am – 5:00pm, Daily. Work shall be scheduled to minimize impact to facility operations.
C. Contractor requests to work afterhours shall be approved by the Contracting Officer’s Representative (COR). Requests to work outside normal business hours shall be submitted in writing to the COR not less than 48 hours in advance of the proposed after hours work. Any SAAN staff overtime required may be charged back to the Contractor.
Staging Areas A. Work sites shall be limited to the smallest feasible area. Ground disturbances and site management shall be carefully controlled to prevent undue damage to vegetation, soils, and archeological resources and to minimize air, water, soil, and noise pollution.
B. Confine storage of work materials and equipment to immediate vicinity of project site, unless directed otherwise by the COR. All staging areas shall be returned to pre-work conditions once work is complete. Standards for this, and methods for determining when the standards are met, shall be developed in consultation with the COR. If used, all temporary water, sewer, sanitary facilities, electric and other utilities and utility connections shall be completely removed upon project completion.
Work Zones A. Do not disturb portions of project site beyond areas in which the work is indicated. Work zones may require work barrier fencing, chain link, plastic or portable fencing as directed by the COR. The fencing shall define the work zone and confine activity to the minimum area required for work. All protection measures shall be clearly stated in the work documents, and workers will be instructed to avoid conducting activities beyond the work zone as defined by the work zone fencing.
B. Confine limits of work to the smallest safe and efficient working areas. Prevent compaction of soils by equipment, and do not damage existing plantings or their root systems. All left over construction material shall be disposed of by Contractor.
C. Establishment of a construction camp shall not be permitted.
Protection of Public A. The Contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs in accordance with MUTCD-2003 as applicable.
Parking of Work Vehicles A. Parking of vehicles shall be limited to existing parking lots, in designated areas close to the jobsite, and within approved staging area.
Temporary Materials, Equipment and Services A. Temporary materials may be new or used, but shall be adequate in capacity for the required usage, shall not create unsafe conditions, and shall not violate requirements of applicable codes and standards.
Hot Work Permit A. A Hot Work Permit in accordance with park policies is required for any welding, cutting, brazing, soldering or any work that generates sparks or excessive heat. Contractor shall provide at least a 24 hour advanced notice to obtain a Hot Work Permit. A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include providing and maintaining fire protection equipment and establishing and maintaining safe torch cutting and welding procedures.
Smoking A. Smoking at the work site is prohibited. Due to drought conditions and the danger of wildland fire, smoking is allowed only within Contractor vehicles.
Electricity A. SAAN will provide electricity from existing receptacles for construction.
Telephone A. Cell phone service is should be readily available at the project site in the event that emergency services are needed at the site.
Water A. Water is available as advised by SAAN.
Sanitary Facilities A. Restrooms are available in the existing buildings.
Hauling Restrictions A. Comply with all legal and local load restrictions in the hauling of materials.
Waste Management A. Employ processes that ensure the generation of as little waste as possible. Minimize waste generation due to over-packaging, poor planning, breakage, mishandling, contamination, error or other factors. Of the waste generated, as much as is economically feasible shall be reused, salvaged or recycled. Waste disposal in landfills shall be minimized. All material unsuitable for recycling shall be disposed of, in a legal manner, at public or private dumping areas outside the park.
Submittals A. Submit the items listed below for review and approval within 14 calendar days of contract award and receipt of Contractor bonds (unless otherwise noted). Government review comments will be returned within 7 calendar days after receipt of submittals.
1. Schedule of values
2. Project schedule
3. Material safety data sheets
4. Safety plan
5. Shop drawings
6. System operations matrix
7. Qualifications
a. Fire Alarm system designer
b. Fire Alarm system installer
c. Security and CCTV system designer
d. Security and CCTV system installer
8. Product data
a. Fire/Security system, CCTV and device cutsheets
b. Battery calculations
9. Certifications (Submit prior to final testing)
a. Written certification the equipment has been inspected and tested by a manufacturer's certified representative.
b. Written certification the equipment is installed in accordance with the manufacturer's recommendations and ULI listings.
c. Written certification the equipment is in proper working order.
d. Completed Record of Inspection and Testing form(s) as outlined in NFPA 72 complete with device sensitivity values.
e. Laminated paper specific written instructions posted at control panels describing step-by-step procedures for seasonal electrical shutdown and startup of fire alarm system. Instructions should include contact information for troubleshooting purposes.
Final deliverables A. Contractor shall provide the following within seven (7) calendar days of project completion and prior to the punchlist site visit. Submit draft versions of these items electronically (PDF). Once reviewed and approved, provide deliverables in two (2) 3-ring binders with section dividers for each deliverable. Final deliverables shall include a CD (or thumb drive) with all approved deliverables in electronic form (PDF). Contractor shall provide the following PRIOR TO FINAL PAYMENT.
1. As-Built drawings – 2 hard copies and 2 digital (DWG and PDF)
2. Warranty Certificates – 2 hard copies and 1 digital (PDF)
3. Operation and Maintenance Manual - 2 hard copies and 1 digital
4. Record of training attendees – 2 hard copies and 1 digital
5. Spare devices: type and quantities as noted in the SOW image1.wmf