This file is an amendment containing a question and answer clarification regarding the timeline for completing outhouse pumping services along the Taylor Highway in Alaska under BLM Solicitation 140L6326Q0003.

The question addresses whether the required work must be completed within a strict two-day window or if an extended timeline is acceptable between September 18-30. BLM's response clarifies that while a two-day window is preferred, work may be performed any time between September 18-30, provided the highway remains open. The rationale for this compressed timeframe is that BLM seeks completion shortly after the hunting season ends on September 17th to avoid the site remaining active with hunters, to prevent frozen conditions before spring thaw, and to account for deteriorating weather conditions later in September that could impede travel to remote sites. The critical constraint is highway accessibility, which becomes unreliable as fall weather progresses.

View the file

Other files

File Type Posted
Sol_140L6326Q0003_Amd_0002.pdf PDF
Sol_140L6326Q0003_Amd_0001.pdf PDF
Amendment0001_Q_A_0001.docx DOCX document
Sol_140L6326Q0003.pdf PDF
A04_Statement_of_Work_-_EIFO_(WSFM)_Outhouse_Pumping_FY26.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BLM Solicitation 140L6326Q0003 Amendment 0002 One Question with answer

QUESTION

Is it strictly needed to be done in 2 day window or can be extended provided that its between the dates of September 18-30?

ANSWER

1. BLM is trying to get the job done at the end of the season so it is empty and not frozen when spring comes.

1. Hunting season ends on September 17th of each year and some of the sites remain very active until that date.

1. Weather soon becomes a factor for traveling later in September.

In short, BLM needs it done as soon as possible after September 17th. Up to September 30 is fine as long as the highway remains open.