This is a Questions and Answers document for federal contract opportunity 140L5726Q0017. The document clarifies the scope of work regarding livestock piping procurement for the Bureau of Land Management (BLM) Cedar City Field Office.

The primary requirement is for HDPE (High-Density Polyethylene) livestock pipe supplied in 5,000 linear foot rolls with no substitution permitted for smaller increments. The contracting officer explicitly confirmed that the requirement is limited to livestock pipe only, with no elbows, fixtures, valves, miscellaneous fittings, butt fusion machines, generators, or other ancillary equipment required, despite references to these items in the Statement of Work. All piping reels must be delivered to the BLM Cedar City Field Office Coal Creek Yard located at 1770 North Airport Road, Cedar City, UT 84721.

View the file

Other files

File Type Posted
Sol_140L5726Q0017_Amd_0002.pdf PDF
Sol_140L5726Q0017_Amd_0001.pdf PDF
Sol_140L5726Q0017.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140L5726Q0017 Questions & Answers

Q1. Can the 5k Linear ft HDPE increments be substituted for 2.5K Linear ft increments if supplier or manufacturer cannot provide 5K linear ft?

A1. No, the requirement is for 5000 linear ft. rolls.

Q2. Does the customer need a specified quantity of elbows, 45's, Tee's as its mentioned in SOW however not quantified for ktr to provide cost?

A2. This requirement is for the livestock pipe only, no elbows, fixtures, or valves are required.

Q3. Does the customer need a specified quantity of valves by type and size whether ball, butterfly, gate, globe, regulators as mentioned in SOW but not quantified for ktr to provide cost?

A3. This requirement is for the livestock pipe only, no elbows, fixtures, or valves are required.

Q4. Does the customer require a butt fusion machine for 2 inch or below; or a bigger size specified by customer with cutting, reaming, heating plates? If so how many would you like for quote?

A4. This requirement is for the livestock pipe only, no elbows, fixtures, or valves are required.

Q5. Does the customer need a generator for power support of the hot plates for the butt fusion machine?

A5. This requirement is for the livestock pipe only, no elbows, fixtures, or valves are required.

Q6. Does the customer need a specified quantity of miscellaneous fittings by type, size, quantity as miscellaneous fittings are mentioned in SOW, however not identified or quantified for ktr to provide cost?

A6. This requirement is for the livestock pipe only, no elbows, fixtures, or valves are required.

Q7. Does the customer need a specified quantity of Fixtures by model number/SSN and quantity as fixtures are mentioned in SOW, however not identified or quantified for ktr to provide cost?

A7. This requirement is for the livestock pipe only, no elbows, fixtures, or valves are required.

Q8. To confirm all reels of piping to be delivered to BLM Cedar City Field Office:

Coal Creek Yard 1770 North Airport Road, Cedar City, UT 84721

A8. That is the correct delivery address.