This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the Bureau of Land Management (BLM) Oregon-State Office Procurement Management Branch. The amendment pertains to solicitation 140L4326Q0002, dated February 4, 2026, with an effective date of February 4, 2026. The document is administered by the BLM OR-ST OFC PROC MGMT BR located at 1220 SW 3rd Avenue, 12th Floor, Portland, OR 97204.
The amendment addresses six Requests For Information (RFI) and adds Attachments A-D to the solicitation. Key clarifications include: material stockpiling should occur closer to the quarry as indicated in Exhibit A of Attachment D; crushing cannot begin before July 15, 2026 due to incomplete owl surveys and wildlife restrictions that run from March 1 through July 15; previously shot rock reports are available in Attachment A; and removed vegetation can be piled on the western side of the quarry or the northwest tip of the crushing pad/stockpile location shown in Exhibit A of Attachment D. The solicitation period is extended to Friday, February 20, 2026 at 9:00 AM, Pacific Time. The Period of Performance is established as July 15, 2026 through October 31, 2026. The amendment requires offerors to acknowledge receipt of this amendment prior to the extended deadline by completing items 8 and 15 on the form and returning it, by acknowledging receipt on each copy of the offer submitted, or by separate letter or electronic communication referencing the solicitation and amendment numbers.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_A__Mt__Ruben_Rock_Inventory_0001.pdf | ||
| Attachment_B-Rueben_mtn_water_righst_0001.pdf | ||
| List_of_Attachments_0001.docx | DOCX document | |
| Attachment_D_-_Catergorical_Exclusion_and_Decision_Record_0001.pdf | ||
| Attachment_C-_Possible_Water_Sources_0001.pdf | ||
| Sol_140L4326Q0002.pdf | ||
| B03_Wage_Determination__2015-5571_Rev_27_12-3-2025.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Matthew Duane
See continuation page
BLM OR-ST OFC PROC MGMT BR(OR952)
1220 SW 3rd Avenue, 12th Floor
PORTLAND OR 97204
LHA
140L4326Q0002
02/04/2026
02/04/2026
1 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140L4326Q0002/0001
This amendment to the solicitation is issued to answer Requests For Information (RFI) provided below and to add Attachments A-D.
Question: Can material be stockpiled at pit, or does it need to be hauled to intersection of pit road, where it looks like there was a stockpile in the past?
Answer: It should be stockpiled closer to the quarry as indicated in Exhibit A of Attachment
D.
Question: Is it possible to crush earlier than
July 15 , or is that set in stone due to owl?
Answer: No, it will not be possible to crush earlier than July 15 due to no owl surveys being completed in this area to clear work prior to July 15.
Question: Is there any wildlife restrictions
Answer: Yes, that is the reason for a July 15th start date is that the wildlife restriction goes from March 1 ¿ July 15 (See Section
C.1.3)
Question: Do you have shot report of previously shot rock, like drill log, hole logs anything that would tell depth.
Answer: See Attachment A
Question: Site clearing, is there a dump site for vegetation? There is not much vegetation that will need to be removed?
Answer: Removed vegetation can be piled on the western side of the quarry or in the very northwest tip of crushing pad/stockpile location in Exhibit A of Attachment D.
The solicitation period is extended to Friday, February 20, 2026 at 9AM, Pacific Time.
Period of Performance: 07/15/2026 to
10/31/2026
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |