This document contains two Excel spreadsheets outlining road decommissioning projects and a related federal contract opportunity notice.
The spreadsheets provide line item estimates for decommissioning over 2.5 miles of road, including mobilization of excavation equipment, general excavation and haul work using excavators and dump trucks, dewatering of streams if needed, and soil stabilization of disturbed areas using government provided seed and mulch. The projects are located on Bureau of Land Management property in Josephine County, Oregon.
The related federal contract opportunity is a solicitation notice for aquatic restoration services issued by the Bureau of Land Management's Oregon-Washington office. The notice seeks a contractor to perform aquatic restoration but provides no further details on required work, response deadline, or award date.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L4322Q0151_Amd_0001.pdf | ||
| RFQ_140L4322Q0151_and_Attachments.pdf | ||
| Sol_140L4322Q0151.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Keene Ck and Upper Jenny Ck
| South Fork Keene Creek Road Decommissioning Project: total road deco length 1.4 miles | |||||
| Legal description: T40S-R03E-21 | |||||
| Item | Description | Qyt | Unit of measure | Unit Price | Total Price |
| 1 | Mobilization-move equipment from contractor's point of origin to ordering office (Medford): Excavator | 1 | EA | ||
| 1A | Mobilization-non-street legal heavy equipment weighing over 12,000 pounds from ordering office to work site- Excavator to project access from Soda Mountain Road | 35 | Per Mile | ||
| 1C | Washing Equipment: prior to mobilization | 1 | EA | ||
| 7 | General Excavation and Haul Work | ||||
| 7A | Level 3: 30,000 lbs or greater | 210 | HR | ||
| 7B | Level 4: Dump Truck (10 yard capacity) | 10 | HR | ||
| 8 | Dewatering of streams during excavation (if needed) | 2 | EA | ||
| 9 | Soil Stabilization - general labor (govn't to provide seed and weed-free mulch) | 1 | acre | ||
| TOTAL | |||||
| Upper Jenny Creek Road Decommissioning Project: total road deco length 1.1 miles | |||||
| Legal description: T39S-R04E-22 | |||||
| 1 | Mobilization-move equipment from contractor's point of origin to ordering office (Medford): Excavator | 1 | EA | ||
| 1A | Mobilization-non-street legal heavy equipment weighing over 12,000 pounds from ordering office to work site- Excavator to project access from Soda Mountain Road | 50 | Per Mile | ||
| 1C | Washing Equipment: prior to mobilization | 1 | EA | ||
| 7 | General Excavation and Haul Work | ||||
| 7A | Level 3: 30,000 lbs or greater | 146 | HR | ||
| 8 | Dewatering of streams during excavation (if needed) | 1 | EA | ||
| 9 | Soil Stabilization -general labor (govn't to provide seed and weed-free mulch) | 1 | acre | ||
| TOTAL |