This document is a Questions and Answers (Q&A) file for Solicitation #140L4025Q0023, covering vault and septic pumping services for Santa Cruz Lake and Diablo Canyon. The Q&A reveals key operational details, including water availability (yard hydrants only at Northshore, water must be hauled to other sites), waste disposal options (multiple dump sites in Santa Fe and Rio Arriba Counties), and trash removal procedures (using scooping tools or trash grabbers). The Bureau of Land Management (BLM) indicates a final contract decision is expected by June 30, 2025. Contractors should note that water and waste management will require additional logistical planning, particularly for the Overlook Campground and Diablo Canyon locations where water is not readily available on-site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L4025Q0023_Amd_0003.pdf | ||
| B04_Evaluation_Criteria_(LPTA)_Updated_8_8_2025_0003.pdf | ||
| Sol_140L4025Q0023_Amd_0002.pdf | ||
| Sol_140L4025Q0023_Amd_0001.pdf | ||
| B09_-_Price_Schedule_TFO_Edited.xlsx | XLSX spreadsheet | |
| Sol_140L4025Q0023.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #: 140L4025Q0023
Question # Question Answers
1 Could you let us know who the incumbent is for this contract?
BLM contracts are publicly available
2 Could we please get the contract value for this particular solicitation?
BLM contracts are publicly available
3 Are water-spigots present at all of the sites listed that will need to be serviced?
Water yard hydrants are available at the Northshore at Santa Cruz Lake. Water is not available at the Overlook Campground at Santa Cruz Lake or Diablo Canyon. Water would need to be hauled to these two latter locations.
4 Do you happen to know when a final decision will be made for this year's opportunity?
A final decision is expected to be made by June 30, 2025.
5 Is there a dump site nearby that a septic pump driver would use?
There are several locations within Santa Fe and Rio Arriba Counties where dumping of septic waste is available, including this site operated by the City of Santa Fe: Septic discharge site | City of Santa Fe
6 How is trash cleared out from the vaults normally handled?
Once the septic waste has been pumped, the contractor would use a scooping tool (e.g., shovel or net) on an extension or a trash grabber tool on an extension to remove any remaining trash materials.
7 Is there an incumbent? What is the contract number?
BLM contracts are publicly available https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fsantafenm.gov%2Fpublic-utilities%2Fwastewater-division%2Fseptic-discharge-site&data=05%7C02%7Clhubbard%40blm.gov%7C06f95d49816247e5a65b08ddada62fb9%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C638857651471623492%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=EgHncMK61h5Rd2lW8qS2SZh1dFEjezheNEk%2FbBtq354%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fsantafenm.gov%2Fpublic-utilities%2Fwastewater-division%2Fseptic-discharge-site&data=05%7C02%7Clhubbard%40blm.gov%7C06f95d49816247e5a65b08ddada62fb9%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C638857651471623492%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=EgHncMK61h5Rd2lW8qS2SZh1dFEjezheNEk%2FbBtq354%3D&reserved=0