B12_Q_A_TO_SOLICITATION_140L3923Q0153_0001.docx

DOCX document 16 KB Posted

Attached to
CCDO UNINTERRUPTED POWER SUPPLY (UPS) UNIT SERVICE
Solicitation number
140L3923Q0153
Issued by

About this file

This document contains questions and answers related to solicitation number 140L3923Q0153 for uninterrupted power supply (UPS) unit service for the Department of the Interior Bureau of Land Management Nevada Region. The solicitation requires replacement of batteries for a UPS system located on the ground floor of a single-story building approximately 3,000 feet from the loading dock. No modifications are needed to transport batteries as there are no narrow doorways or other obstructions. Service shall be performed during normal business hours. The solicitation specifies delivery of 20 replacement batteries by November 30, 2023. Clarification was provided that this is a one-time battery replacement service, not an annual UPS unit service.

View the file

Other files

File Type Posted
Sol_140L3923Q0153_Amd_0001.pdf PDF
Sol_140L3923Q0153.pdf PDF
B03_Service_Contract_Act_WD_2015-5591.pdf PDF
A04_SOW_UPS.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PR 40632144

SOLICITATION# 140L3923Q0153

UNINTERRUPTED POWER SUPPLY

QUESTIONS & ANSWERS

Q1 Is there a loading dock or forklift on site?

A1 Yes, and yes

Q2 Approximately how far from the dock/drop point to the UPS system?

A2 Approximately 3,000 feet

Q3 What floor is the UPS systems on if not ground floor? Is there an elevator we can access if not on same floor as shipping dock/drop?

A3 The building is a single story, therefore the system is on the ground floor.

Q4 Any narrow doorways that would not permit standard pallet (40"x 40") or any other obstructions (carpet, etc.) from the shipping drop or dock to the UPS location?

A4 No, and No

Q5 Service performed during normal business hours or after hours?

A5 Service shall be performed during normal business hours.

Q6 Are you open to battery alternatives?

A6 No

Q7 How quickly do you need the batteries?

A7 The batteries should be delivered by the date specified in the solicitation, 11/30/2023.

Q8 As we were going through the documents, the SOW mentioned that the required service is an annual service on the UPS unit.

However, on the pricing section in the SF we found “20” in the quantity.

Therefore, we would like to kindly request your clarification on what does the number 20 refer to exactly.

A8 This is a one-time service and the 20 represents the number of batteries that currently needs to be replaced.