Sol_140L3724Q0097_Amd_0001.pdf
PDF 98 KB Posted
- Attached to
- Waugh Mtn and Stoney Face Fire Lines (Colorado)
- Solicitation number
- 140L3724Q0097
About this file
This document is an amendment to a solicitation (Solicitation Number: 140L3724Q0097) for a federal contract opportunity to create fire control lines for prescribed burns in the Waugh Mountain and Stoney Face areas in Colorado. The main objective is to remove heavy logging slash, natural dead and down, and ladder fuels within 1 or 2 chains (1 chain = 66 feet) of the designated saw lines and dug hand line. The total project area is 96 acres. The solicitation was amended to answer vendor questions, define the pricing structure as firm-fixed price per acre, and extend the period of performance to September 30, 2025. The solicitation is a total small business set-aside under NAICS code 115310. Award will be made on a lowest priced technically acceptable basis. Vendors were encouraged to attend a site visit on June 25, 2024 and submit pricing structure suggestions by July 1, 2024. Quotes are due by July 17, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140L3724Q0097 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
LFA
BOISE ID 83705
3833 S. DEVELOPMENT AVE.
BLM FA-NTL INTRAGCY FIRE CTR(FA250)
07/11/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/06/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 0001 is issued to answer questions received about the solicitation and to define the pricing structure.
The pricing schedule will be per acre:
96 acres @ $_________________ per acre = $______________________
Q1. Incumbent Information: Could you please share the name of the incumbent contractor
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140L3724Q0097/0001 currently performing these services?
A1. There is not an incumbent.
Q2. In the SOW it states 'removal' for multiple prescription line items. This does not mean removal via hauling off correct? All fuel and vegetation will be dispersed within Rx units, not physically removed from the project site via truck/trailer?
A2. Removal means cut and dragged and either dispersed into the RX Unit or incorporated into existing piles.
Q3. For price schedule reasons, how many acres does the project come out to?
A3. See attached maps. Waugh Mountain 28 acres, Stoney Face 68 acres.
Q4. How many acres does the project come out to?
A4. Total 96 acres, see above
Q5. Project Scope Clarification: We aim to fully understand the exact scope of work, including any potential challenges or specific requirements that are crucial for successful execution. Are there any particular areas within the project scope that require special attention or consideration?
A5. Items were addressed in the SOW or in the questions included here.
Q6. Understanding the key factors that will be evaluated in the proposal will help us align our submission with the client's expectations. Could you please elaborate on the most critical evaluation criteria for this project?
A6. The evaluation criteria are listed under provision 52.212-1 on page 5 of the solicitation.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
3 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140L3724Q0097/0001
The information we need to see with your quote is listed under each factor. Award will be made on a lowest priced technically acceptable basis and the criteria are not ranked in importance.
Q7. Site Conditions: Information regarding any recent changes or specific conditions of the project sites that might affect our approach and planning would be invaluable. Are there any site-specific details or recent developments that we should be aware of?
A7. A site visit was held on June 25. Per the SOW
"These areas have been recently logged. Google
Earth Imagery, NAIP imagery and other sources of imagery were captured prior to the completion of the logging efforts. Tree densities shown in the imagery may be vastly different in this imagery than actual conditions on the ground. Access into this treatment area requires entry through a locked gate, so the pre-bid tour would be the best time to see the treatment areas." This vendor was informed they should attend and afterwards let the Contracting Officer know if they had any questions that were not answered by the site visit.
One consideration that was discussed on the site tour was the elevation of the projects and timing of work to beat snow in the fall and if necessary, re-entry in the spring. Typical conditions in this area are snowfall begins late
October-early November, and snow melt in the spring would occur mid-late April.
Q8. Is it possible to extend the period of performance this work needs to be completed within?
A8. Yes. Per the discussion above the period of performance end date is extended to September 30, 2025. The POP will be date of award (approx.
July 22, 2024) through September 30, 2025.
Q9. Is this job is intended to have the fireline clearing done with machines or by hand, or both?
A9. By hand only
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
4 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140L3724Q0097/0001
Q10. There was a question or clarification that we were asked about the existing machine piles.
There are several within or near the project area.
A10. We are not asking the vendor to do anything with the machine piles. They are however allowed to add any material that they cut to the piles if they are nearby, we just ask that no new piles be created.
Q11. Would it be ok to allow some type of mower along the edge, particularly in the ground juniper?
A11. Mowers can not be utilized in this contract.
- End-
Period of Performance: 07/22/2024 to 09/30/2025
Change Item 00010 to read as follows(amount shown is the obligated amount):
00010 2024 Waugh Mountain and Stoney Face Line
Construction
The contractor shall perform services in accordance with the attached Statement of Work.
Product/Service Code: F014
Product/Service Description: NATURAL
RESOURCES/CONSERVATION- TREE THINNING
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
File details come from the government source that posted it. Updated .