Kimama_and_Rogerson_Flooring_Spec.pdf

PDF 1 MB Posted

Attached to
KIMAMA & ROGERSON GUARD STATIONS FLOORING Federal contract opportunity
Solicitation number
140L2626Q0005
Issued by
Department of the Interior Bureau of Land Management Idaho Region

About this file

This document is a federal construction specification for flooring work at two U.S. Department of the Interior Bureau of Land Management facilities located in Idaho. The project involves flooring installation and renovation at the Kimama Guard Station (Minidoka County) and Rogerson Guard Station (Twin Falls County), with work scheduled for January 2026.

The scope includes selective demolition of existing flooring, wall tile, and base materials, followed by installation of ceramic tile, resilient tile flooring, resilient base trim, and modular carpet tile. Specific products specified include ceramic floor tile (Daltile Core Fundamentals – Prime, Dynamic Beige 12x24) and wall tile (Crossville Shades 2.0 SPO, Frost 6x24), solid vinyl floor tile (Mannington Mills Spacia Woods – Muted Oak or approved equal), thermoplastic-rubber base (Roppe Pinnacle Cove Base in Dark Brown, 4 inches high), and modular carpet tile (J&J Invision Kintex Put a Cork in It in Drum color). Work must be performed during regular office hours (8:00 a.m. to 4:30 p.m.), and the contractor must provide three business days' notice before starting to allow government furniture relocation. The contract includes mobilization and construction management; payment is structured through lump sum and unit price items. All installations must comply with referenced ANSI standards, ASTM testing requirements, and manufacturer specifications for quality assurance and warranty purposes, with ceramic tile and carpet tile carrying 10-year and 15-year warranties respectively.

View the file

Other files for this federal contract opportunity

Other files attached to KIMAMA & ROGERSON GUARD STATIONS FLOORING, newest first.
File Type Posted
Kimama_Rogerson_Flooring_Kimama_Pics_0001.pdf PDF
Kimama_Rogerson_Flooring_Rogerson_Pics_0001.pdf PDF
Sol_140L2626Q0005_Amd_0001.pdf PDF
Site_inspection_Prebid_conference_record_0001.pdf PDF
Sol_140L2626Q0005.pdf PDF
Kimama___Rogerson_Flooring_DWG_s.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior

Bureau of Land Management

Kimama & Rogerson Flooring

Twin Falls District

Burley, ID

January 2026

JANUARY 2026 TABLE OF CONTENTS

KIMAMA & ROGERSON FLOORING 1

TABLE OF CONTENTS

SPECIFICATIONS ........................................................................................................................... # OF PAGES

DIVISION 01 - GENERAL REQUIREMENTS

011000 SUMMARY

017113 MOBILIZATION

012200 UNIT PRICES AND SCHEDULE OF VALUES

013300 SUBMITTAL PROCEDURES

014000 QUALITY REQUIREMENTS

016000 PRODUCT REQUIREMENTS

017300 EXECUTION REQUIREMENTS

017700 CLOSEOUT PROCEDURES

DIVISION 02

024119 SELECTIVE DEMOLITION

DIVISION 09

093013 CERAMIC TILING

096513 RESILIENT BASE AND ACCESSORIES

096519 RESILIENT TILE FLOORING

096813 TILE CARPETING

END OF TABLE OF CONTENTS

JANUARY 2026 SUMMARY

KIMAMA & ROGERSON FLOORING 011000-1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Use of premises.

3. Specification formats and conventions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Identification: Kimama & Rogerson Flooring.

1. Project Location: Kimama Guard Station, 1500 N 600 W Paul, Idaho 83347 Minidoka

County

2. Project Location: Rogerson Guard Station, 2295E 1500 N Rogerson, Idaho 83302 Twin

Falls County

B. The Work consists of the following:

1. Demolition of old flooring.

2. Demolition of old wall tile.

3. Installing Carpet

4. Installing Ceramic Tile

5. Installing Base

6. Installing Resilient Tile Flooring

C. Project will be constructed under a single prime contract.

D. The Government will relocate all furniture that is not permanently affixed to walls, floors, or other structural surfaces. The Contractor shall provide the government a minimum of three business day notice prior to the start of work to allow sufficient time for furniture relocation.

1.3 USE OF PREMISES

A. Contractor shall have full use of premises for construction operations during construction period. Contractor's use of premises is limited only by Government right to perform work or to retain other contractors on portions of work.

B. Schedule operations so that Work is conducted during regular office hours which are 8:00 a.m.

to 4:30 p.m.

KIMAMA & ROGERSON FLOORING 011000-2

C. Schedule and sequence operations necessary to complete the work, including coordination with other crafts relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.

D. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of

Project site beyond areas in which the Work is indicated.

1.4 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: The Specifications are organized into Divisions and Sections using the

50-division format and CSI/CSC's "MasterFormat" numbering system.

1. Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the Specifications.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract

Documents is abbreviated. Words and meanings shall be interpreted as appropriate.

Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications.

Requirements expressed in the imperative mood are to be performed by Contractor.

Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

C. Terminology: In Divisions 2 through 33 specification sections, all references to “Owner” have been replaced with the term “Government” (when referring to the person acting for the

Government). All references to “Architect” have been replaced with the term “Government”.

D. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the work of all Sections in the Specifications.

E. Contract Times: “Days” referred to in the Specifications are defined as calendar days.

KIMAMA & ROGERSON FLOORING 011000-3

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

JANUARY 2026 MOBILIZATION

KIMAMA & ROGERSON FLOORING 017113-1

SECTION 017113 – MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the Contract. This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site, as well as construction management activities as described in Division

01 specifications and in the Contract Clauses, including applicable Federal Acquisition

Regulations (FARs).

B. This item also includes the cost of transportation of Contractor’s personnel, materials, and equipment to and from the job site during accomplishment of the project.

C. The cost of any required bonds may also be included in mobilization.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall perform the necessary preparatory work and operations, including but not limited to, those required for the movement of contractors personnel, equipment, supplies, and incidentals to the project site to assure completion of the project within the required time frames.

B. The contractor shall also perform all project coordination and construction management as described in Division 01 specifications or incidental/managerial work from other Divisions and

FARs, including, but not limited to, following contract procedures for providing submittals, shop drawings, construction schedules, safety and traffic management plans, environmental compliance, maintaining project documents and records, and all associated work as described or otherwise required.

C. The Government will relocate all furniture that is not permanently affixed to walls, floors, or other structural surfaces. The Contractor shall provide the government a minimum of three business day notice prior to the start of work to allow sufficient time for furniture relocation.

JANUARY 2026 MOBILIZATION

KIMAMA & ROGERSON FLOORING 017113-2

3.2 BASIC MOBILIZATION

A. Mobilization for contact work at or near major administrative or recreational sites as identified in the contract documents.

PART 4 - MEASUREMENT AND PAYMENT

4.1 PROGRESS PAYMENTS WILL BE MADE AS FOLLOWS:

A. When 5 percent or more of the original bid amount (per site) is earned from other pay items, 25 percent of the amount for mobilization will be paid.

B. When 10 percent or more of the original bid amount (per site) is earned from other pay items, 50 percent of the amount for mobilization will be paid.

C. When 50 percent or more of the total amount (per site) is earned, 100 percent of the amount bid for mobilization will be paid.

D. The total of all payments shall not exceed the original contract amount for this item.

END OF SECTION 017113

JANUARY 2026 UNIT PRICES AND SCHEDULE OF VALUES

KIMAMA & ROGERSON FLOORING 012200-1

SECTION 012200 - UNIT PRICES AND SCHEDULE OF VALUES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for unit prices and requirements to prepare schedule of values.

1.2 DEFINITIONS

A. Unit price is a price per unit of measurement for materials or services added to or deducted from the Contract Sum by appropriate modification, if estimated quantities of Work required by the

Contract Documents are increased or decreased.

1.3 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

B. Government reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government expense, by an independent surveyor acceptable to Contractor.

C. List of Unit Prices: A list of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LUMP SUM PAYMENT ITEMS

A. Payment items for the work of this Contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below.

B. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved.

C. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated

KIMAMA & ROGERSON FLOORING 012200-2

Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

3.2 UNIT PRICE PAYMENT ITEMS

A. Payment items for the work of this Contract for which unit price payments will be made are listed in the BIDDING SCHEDULE and described below.

B. Unit price items are inclusive of all materials, labor, parts, assembly, and installation in order to produce a unit of the product. All costs for items of work, which are not specifically mentioned to be included in a particular unit price payment item, shall be included in the listed unit price item most closely associated with the work involved.

C. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

D. Quantities regarding unit prices shall be assumed to follow the quantities listed in the bid schedule. If the Contractor suspects a change in the unit quantities, measurement can be made to adjust the final quantity of an item. If the quantity of an item cannot be measured at final condition the contractor shall produce construction documentation collected during construction to demonstrate the quantity.

3.3 SUMMARY OF BID ITEMS

A. The intent of the following paragraphs is to explain, in general, what is and what is not included in a bid item, and the limits or cut-off points where one bid item ends and another begins. If no bid item exists for a portion of the work, include the costs in a related bid item.

B. BID ITEM 1 - MOBILIZATION AND CONSTRUCTION MANAGEMENT: This item includes all preparatory work and operations, including those necessary to the movement of

Contractors personnel, equipment, supplies and incidentals to the project site; bonds, work layout; other work and operations which must be performed or costs incurred prior to beginning work on the various items on the project site. Construction management includes ongoing tasks such as environmental controls, temporary facilities and controls, temporary traffic control, and field office operations. Item also includes preparation and installation of erosion control measures and features. Item will be paid for as a Each.

C. BID ITEM 2 – DEMOLITION: This item includes labor and equipment necessary for the removal of Vinyl flooring, Tile, and Base as indicated in the drawings at Rogerson and

Kimama. Item will be paid for as a Each.

D. BID ITEM 3 – CERAMIC TILE: This item includes providing all labor, materials, engineering, and equipment necessary to install the Ceramic Tile per the specifications and drawings. Item will be paid for by the Square Foot.

KIMAMA & ROGERSON FLOORING 012200-3

E. BID ITEM 4 – CERAMIC WALL TILE: This item includes providing all labor, materials, engineering, and equipment necessary to install the Ceramic Wall Tile per the specifications and drawings. Item will be paid for by the Square Foot.

F. BID ITEM 5 – RESILIENT BASE: This item includes labor, materials, and equipment to install

Resilient base per specifications and drawings. Item will be paid for by the Lineal Foot.

G. BID ITEM 6 – RESILIENT TILE: This item includes providing all labor, materials, engineering, and equipment necessary to install the Resilient Tile per the specifications and drawings. Item will be paid for by the Square Foot.

H. BID ITEM 7 –TILE CARPET: This item includes providing all labor, materials, engineering, and equipment necessary to install the Tile Carpet per the specifications and drawings. Item will be paid for by the Square Yard.

END OF SECTION 012200

JANUARY 2026

KIMAMA & ROGERSON FLOORING

SUBMITTAL PROCEDURES

013300 - 1

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require

Government's responsive action. Action submittals are those submittals indicated in individual

Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Government's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification

Sections as "informational submittals."

1.3 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Project name.

2. Date.

3. Name of Government.

4. Name of Contractor.

5. Name of firm or entity that prepared submittal.

6. Names of subcontractor, manufacturer, and supplier.

7. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals.

8. Category and type of submittal.

9. Submittal purpose and description.

10. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

11. Drawing number and detail references, as appropriate.

12. Indication of full or partial submittal.

13. Location(s) where product is to be installed, as appropriate.

14. Other necessary identification.

15. Remarks.

16. Signature of transmitter.

B. Options: Identify options requiring selection by Government.

SUBMITTAL PROCEDURES

013300 - 2

C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Government on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.

D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

1.4 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Email: Prepare submittals as PDF package, and transmit to Government by sending via email. Include PDF transmittal form. Include information in email subject line as requested by Government.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification

Section as separate packages under separate transmittals.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.

Time for review shall commence on Government's receipt of submittal. No extension of the

Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Government will advise

Contractor when a submittal being processed must be delayed for coordination.

2. Resubmittal Review: Allow 15 days for review of each resubmittal.

D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Government's action stamp.

SUBMITTAL PROCEDURES

013300 - 3

1.5 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. Submit Product Data before Shop Drawings, and before or concurrent with Samples.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base

Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional engineer if specified.

2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit

Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 30 by 42 inches.

C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other materials.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Permanently attach label on unexposed side of Samples that includes the following:

a. Project name and submittal number.

b. Generic description of Sample.

c. Product name and name of manufacturer.

d. Sample source.

e. Number and title of applicable Specification Section.

SUBMITTAL PROCEDURES

013300 - 4

f. Specification paragraph number and generic name of each item.

3. Email Transmittal: Provide PDF transmittal. Include digital image file illustrating Sample characteristics, and identification information for record.

4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

a. Samples not incorporated into the Work, or otherwise designated as Government's property, are the property of Contractor.

5. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit one full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Government will return submittal with options selected.

6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit two sets of Samples. Government will retain one

Sample set; remainder will be returned.

1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated.

2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least two sets of paired units that show approximate limits of variations.

D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

E. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of Government, and other information specified.

F. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.

SUBMITTAL PROCEDURES

013300 - 5

G. Certificates:

1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide a notarized signature where indicated.

2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents.

Include evidence of manufacturing experience where required.

4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding

Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.

H. Test and Research Reports:

1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

4. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

1.6 DELEGATED-DESIGN SERVICES

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are insufficient to perform services or certification required, submit a written request for additional information to Government.

B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF file and one paper copy of certificate, signed

SUBMITTAL PROCEDURES

013300 - 6 and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the

Contract Documents. Include list of codes, loads, and other factors used in performing these services.

1.7 CONTRACTOR'S REVIEW

A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents.

Note corrections and field dimensions. Mark with approval stamp before submitting to

Government.

B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the

Contract Documents.

1. Government will not review submittals received from Contractor that do not have

Contractor's review and approval.

1.8 GOVERNMENT'S REVIEW

A. Action Submittals: Government will review each submittal, indicate corrections or revisions required, and return it.

1. PDF Submittals: Government will indicate, via markup on each submittal, the appropriate action, as follows:

a. APPROVED: Where submittals are marked “Approved”, that part of the Work covered by the submittal may proceed provided it complies with requirements of the Contract Documents; final acceptance will depend upon that compliance.

b. APPROVED, SUBJECT TO COMPLIANCE WITH ATTACHED COMMENTS:

Where submittals are marked “Approved, Subject to Compliance with Attached

Comments”, that part of the Work covered by the submittal may proceed provided it complies with notations or corrections on the submittal and requirements of the

Contract Document; final acceptance will depend upon that compliance.

c. NOT APPROVED: Where submittals are marked “Not Approved”, do not proceed with that part of the Work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal in accordance with the notations; resubmit without delay. Repeat if necessary to obtain a different action mark.

B. Informational Submittals: Government will review each submittal and will not return it, or will return it if it does not comply with requirements. Government will forward each submittal to appropriate party.

SUBMITTAL PROCEDURES

013300 - 7

C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Government.

D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

E. Government will return without review submittals received from sources other than Contractor.

F. Submittals not required by the Contract Documents will be returned by Government without action.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013300

JANUARY 2026 QUALITY REQUIREMENTS

KIMAMA & ROGERSON FLOORING 014000-1

SECTION 014000 - QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the

Contract Document requirements.

1. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Document requirements.

2. Requirements for Contractor to provide quality-assurance and -control services required by Government or authorities having jurisdiction are not limited by provisions of this

Section.

C. See Divisions 2 through 33 Sections for specific test and inspection requirements.

1.2 DEFINITIONS

A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by Government.

C. Preconstruction Testing: Tests and inspections that are performed specifically for the Project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria.

D. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with industry standards.

E. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.

F. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

KIMAMA & ROGERSON FLOORING 014000-2

G. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.

H. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

1. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespeople of the corresponding generic name.

I. Experienced: When used with an entity, "experienced" means having successfully completed a minimum of five previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

1.3 CONFLICTING REQUIREMENTS

A. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Government for a decision before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits.

To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Government for a decision before proceeding.

1.4 SUBMITTALS

A. Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

B. Reports: Prepare and submit certified written reports that include the following:

1. Date of issue.

2. Project title and number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples and tests or inspections.

5. Names of individuals making tests and inspections.

6. Description of the Work and test and inspection method.

7. Identification of product and Specification Section.

8. Complete test or inspection data.

9. Test and inspection results and an interpretation of test results.

KIMAMA & ROGERSON FLOORING 014000-3

10. Record of temperature and weather conditions at time of sample taking and testing and inspecting.

11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.

12. Name and signature of laboratory inspector.

13. Recommendations on retesting and reinspecting.

C. Permits, Licenses, and Certificates: For Government records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1.5 QUALITY ASSURANCE

A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

D. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar to those indicated for this

Project in material, design, and extent.

F. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.

1. Requirement for specialists shall not supersede building codes and regulations governing the Work.

G. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 548; and with additional qualifications specified in individual Sections; and where required by authorities having jurisdiction, that is acceptable to authorities.

1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.

2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory

Accreditation Program.

KIMAMA & ROGERSON FLOORING 014000-4

H. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this

Project.

1.6 QUALITY CONTROL

A. Government Responsibilities: Where quality-control services are indicated as Government responsibility, Government will engage a qualified testing agency to perform these services.

1. Government will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspecting they are engaged to perform.

2. Costs for retesting and reinspecting construction that replaces or is necessitated by work that failed to comply with the Contract Documents will be charged to Contractor.

B. Tests and inspections not explicitly assigned to Government are Contractor's responsibility.

Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.

1. Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality-control services.

a. Contractor shall not employ same entity engaged by Government, unless agreed to in writing by Government.

2. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.

3. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.

4. Testing and inspecting requested by Contractor and not required by the Contract

Documents are Contractor's responsibility.

5. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.

C. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Division 1 Section "Submittal

Procedures."

D. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents.

E. Testing Agency Responsibilities: Cooperate with Government and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.

1. Notify Government and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.

KIMAMA & ROGERSON FLOORING 014000-5

2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.

3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.

4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.

5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work.

6. Do not perform any duties of Contractor.

F. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:

1. Access to the Work.

2. Incidental labor and facilities necessary to facilitate tests and inspections.

3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.

4. Facilities for storage and field curing of test samples.

5. Delivery of samples to testing agencies.

6. Preliminary design mix proposed for use for material mixes that require control by testing agency.

7. Security and protection for samples and for testing and inspecting equipment at Project site.

G. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and

-control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.

1. Schedule times for tests, inspections, obtaining samples, and similar activities.

1.7 SPECIAL TESTS AND INSPECTIONS

A. Special Tests and Inspections: Contractor will engage a qualified special inspector to conduct special tests and inspections required by authorities having jurisdiction as the responsibility of

Contractor, and as follows:

1. Verifying that manufacturer maintains detailed fabrication and quality-control procedures and reviewing the completeness and adequacy of those procedures to perform the Work.

2. Notifying Contractor promptly of irregularities and deficiencies observed in the Work during performance of its services.

3. Submitting a certified written report of each test, inspection, and similar quality-control service to Contractor and to authorities having jurisdiction.

4. Submitting a final report of special tests and inspections at Substantial Completion, which includes a list of unresolved deficiencies.

5. Interpreting tests and inspections and stating in each report whether tested and inspected work complies with or deviates from the Contract Documents.

6. Retesting and reinspecting corrected work.

KIMAMA & ROGERSON FLOORING 014000-6

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 REPAIR AND PROTECTION

A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.

1. Provide materials and comply with installation requirements specified in other

Specification Sections. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.

B. Protect construction exposed by or for quality-control service activities.

C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.

END OF SECTION 014000

JANUARY 2026 PRODUCT REQUIREMENTS

KIMAMA & ROGERSON FLOORING 016000-1

SECTION 016000 - PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; product substitutions; and comparable products.

B. See Division 1 Section "Closeout Procedures" for submitting warranties for Contract closeout.

C. See Divisions 2 through 33 Sections for specific requirements for warranties on products and installations specified to be warranted.

1.2 SUBMITTALS

A. Substitution Requests: Submit one electronic copy of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified material or product cannot be provided.

b. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Government and separate contractors that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated. Provide sufficient calculations and data to justify selection of proposed item and permit comparisons.

d. Product Data, including technical data, drawings, performance information, and descriptions of products and fabrication and installation procedures. Show complete layout of system, except that which is identical to Contract Documents, unless unchanged portion must be shown to indicate clearances. Include drawings, same (or larger) scale as Contract Drawings, marked to show differences. Include detail drawings of supports for equipment and load calculations, stamped and signed by a registered professional engineer.

e. Samples, where applicable or requested.

f. List of similar installations for completed projects with project names and addresses and names and addresses of COR’s and Government’s.

g. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

KIMAMA & ROGERSON FLOORING 016000-2

h. Research/evaluation reports evidencing compliance with building code in effect for

Project, from a model code organization acceptable to authorities having jurisdiction.

i. Detailed comparison of Contractor's Construction Schedule using proposed substitution with products specified for the Work, including effect on the overall

Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating lack of availability or delays in delivery.

j. Cost information, including a proposal of change, if any, in the Contract Sum.

k. Contractor's certification that proposed substitution complies with requirements in the Contract Documents and is appropriate for applications indicated.

l. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

2. Government Action: If necessary, Government will request additional information or documentation for evaluation within 7 days of receipt of a request for substitution.

Government will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Form of Acceptance: Modification.

b. Use product specified if Government cannot make a decision on use of a proposed substitution within time allocated.

B. Comparable Product Requests: Submit one electronic copy of each request for consideration.

Identify product or fabrication or installation method to be replaced. Include Specification

Section number and title and Drawing numbers and titles.

1. Government Action: If necessary, Government will request additional information or documentation for evaluation within one week of receipt of a comparable product request. Government will notify Contractor of approval or rejection of proposed comparable product request within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Form of Approval: As specified in Division 1 Section "Submittal Procedures."

b. Use product specified if Government cannot make a decision on use of a comparable product request within time allocated.

C. Basis-of-Design Product Specification Submittal: Comply with requirements in Division 1

Section "Submittal Procedures." Show compliance with requirements.

1.3 DEFINITIONS

A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material,"

"equipment," "system," and terms of similar intent.

KIMAMA & ROGERSON FLOORING 016000-3

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature, that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility, except that products consisting of recycled-content materials are allowed, unless explicitly stated otherwise. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

B. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

C. Basis-of-Design Product Specification: Where a specific…