GAOA_CDA_Site_Furnishings__-_Prebid_Tour_Meeting_at_Huckleberry_Campground_Notes_8_6_25_ammended_0001.docx
DOCX document 41 KB Posted
- Attached to
- GAOA COEUR D'ALENE SITE FURNISHINGS
- Solicitation number
- 140L2625R0007
About this file
This document is a pre-bid tour meeting notes for the GAOA CDA Site Furnishings Replacement project by the Bureau of Land Management in the Coeur d'Alene District. The solicitation (140L2625R0007) is for heavy construction services in Kootenai and Shoshone County, Idaho, with a project magnitude between $250,000 and $500,000. The contract will be awarded on a Firm Fixed Price, Lowest Price Technically Acceptable (LPTA) basis, with proposals due August 25th, 2025 at 10:00 MT.
Key project details include a 300-day performance period from September 8, 2025 to July 18, 2026, involving site furnishings replacements at various recreation and campground locations. The scope includes specific site modifications such as removing and reinstalling fire rings, picnic table deadheads, and concrete work, with contractors required to be registered in SAM.gov. Performance and payment bonds are due within 10 days of contract award, and liquidated damages are set at $1,000 per day. The project will follow Davis-Bacon Act wage requirements and includes a Buy American Clause, with some recreation sites remaining partially accessible during construction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GAOA CDA Site Furnishings Replacement, Coeur d’Alene District Solicitation 140L2625R0007, Pre-bid Tour Notes
Aug 6, 2025
Questions and Answers:
Attendees:
| Name |
| Phone |
Richard Fries BLM – District Engineer
| rfries@blm.gov |
| 208-769-5025 |
Joe O’Neill BLM – State GAOA Engineering Recreation ORP
| jfoneill@blm.gov |
| 208-962-3790 |
Johnathan Stein BLM CDA – Recreation ORP
| jstein@blm.gov |
| 208-769-5015 |
| Greg Sternberg NNAC |
| greg.sternberg@NNACINC.com |
208-635-5400
| Andy Watson NNAC |
| Same as above |
208-635-5400
| Ken Howell ADAPT |
| jenni@adaptgc.com |
| 626-773-2637 |
| Matt Wenger |
| matt@trailheadnid.com |
208-654-3637
Time & Location:
· Huckleberry Campground, 12:00 pm (PDT) Aug 6, 2025 Instructions, Conditions, and Notices to Offerors:
· The offeror is to submit a fully compliant proposal to the following email address: pfort@blm.gov
· Questions due Aug 12th at 10:00 MT
· Proposals due Aug 25th at 10:00 MT
· Award Selection: Firm Fixed Price; Lowest Price Technically Acceptable
· Whose quote conforms to all solicitation requirements and is most advantageous to the Government.
· LPTA Evaluation Process
· Magnitude: $250,000 -- $500,000
· Heavy Construction – Kootenai and Shoshone County, Idaho
· Contractor must be in SAM.gov to be awarded. Recommend requesting and/or renewing profile immediately to allow for enrollment timeline to be completed by the award date.
· Performance and Payment Bonds due within 10 days of contract award.
· Davis-Bacon Act wage requirements – wage rates and fringe benefits for classification of work.
· Heavy Construction; Kootenai and Shoshone County
· Buy American Clause
· The contactor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits…applicable to the performance of the work.
· Toilets will be available at each site, some sites have water, and some don’t (water is only on certain times of the year at some sites), a few sites have power available to use.
Project Milestones
· The Contractor shall begin performance within 10 calendars days and complete it within 300 days from Notice to proceed.
· Period of performance is 300 days which includes weather delay days.
· Anticipated contract performance timeline -- 9/8/2025 to 7/18/2026.
· Some recreation/campgrounds will remain partially open (example access to a boat ramp but closed to camping), others will be closed completely during the performance time.
· Performance and Payment Bonds within 10 days of contract award.
· Within ten days after the work commences provide schedule showing the order in which the contractor proposes to perform work.
· Payrolls and Invoices
· Email payrolls (prime and subs) to COR for review and invoices for pre-acceptance.
· IPP for invoice payments.
· Approved payrolls need to be up to date for Invoice approval.
· Liquidated Damages - $1000/day.
GAOA CDA Site Furnishings Replacement, Coeur d’Alene District Solicitation 140L2625R0007, Pre-bid Tour Notes
Aug 6, 2025
(Q)On page 5 of the site pics in mica (second photo). It shows the current fire ring sitting on the riser, and the riser appears to be on a large pad. Are we saw cutting a hole in the slab to install the ring? Of is it placed on top of current slab?
(A)Remove the round elevated pad under the fire ring at site #2 and site #4, including any concrete under the elevated pad, if present. Recommend saw cutting an approximately 48” x 48” square around the fire ring to be removed. Ensure there is sufficient room to install footings for new fire ring as required by manufacturer. Install the new fire ring footings and anchors in the concrete tubes per manufacturer requirements. After the fire ring is anchored – pour concrete to the same depth of the existing slab and tie into the existing concrete slab with 8 dowels (2 per side of square) up to the outside of the fire rings so there is a smooth transition between existing concrete and the new concrete slab around the new fire ring. Dowels shall be 1/4" smooth straight pins, 12” long, wrapped with 1/8” foam sheet material; embed 6” into existing concrete and secure with chemical epoxy grout. Fire ring installation must meet ABA requirements, ensure mounting height and surface repair follow ABA guidelines.
(Q)For mineral ridge. On the site pic page 9, and page 5 of the specifications page. One calls out for 2 dead heads, and the other calls out for 3. For the replacements. Just trying to clarify if its 2 or 3?
(A) Remove 3 deadheads/chains total and install 3 new deadheads/chains for the picnic tables. Specification 011000 1.2 A. 1 f was changed to 3 deadheads.
(Q) On a couple sites the ground could be solid rock. If we need to hammer out the dig areas, would change order be awarded to the areas needed?
(A)Will address if the contractor runs into a problem at the time if necessary.
(Q)Would we be able to have a local pre cast company provide some products. Such as the deadheads and some of the pads for the BBQs. We would share all specs from the manufacturer.
(A) Pre-cast concrete would be allowed as long as they meet manufacturer installation requirements and meet or exceed the salient characteristics of the cast-in-place footings and anchors as described in the drawings and specifications.
(Q)Concrete- spec calls for a 4,000psi 28day break test on the concrete. Are we required have a tester on site when we pour or provide cylinders with break test results? There was another note about having an onsite slump tester as well. I couldn’t see why we would need to supply all the extra testing and such for a non structural project. I wouldn’t have a problem with supplying detailed spec on what product we would be using.
(A)Remove 033000 3.17 from the specs – concrete testing will not be required.