BDO_Gate_RFIs_0002.pdf
PDF 99 KB Posted
- Attached to
- BDO GATE CORRECTIVE ACTIONS Federal contract opportunity
- Solicitation number
- 140L2624Q0003
About this file
This solicitation requests quotes for a gate corrective action project located in Boise, Idaho. The Bureau of Land Management Idaho state office requires repairs to gates at the BDO complex, including replacing two posts and footers at Gate A in a way that isolates them from the adjacent walkway. Offerors must provide all labor, materials, and equipment to complete the project per specifications within 120 calendar days of notice to proceed. Electronic quotes are due by December 11, 2023. This acquisition is set aside for small businesses and will result in a firm-fixed price contract award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L2624Q0003_Amd_0002.pdf | ||
| Attachment_1_-_BDO_Complex_Gate_Corrective_Actions_SOW_13_Dec_23_0002.pdf | ||
| Sol_140L2624Q0003_Amd_0001.pdf | ||
| Attachment_2_-_BDO_Gate_Photo_Documentation.pdf | ||
| Attachment_1_-_BDO_Complex_Gate_Corrective_Actions_SOW_11_Nov_23.pdf | ||
| Attachment_4_-_UFC_4-022-03_Security_Fences_and_Gates.pdf | ||
| Attachment_5_-_Wage_Determination__ID20230110_4_AUG_23.pdf | ||
| Sol_140L2624Q0003.pdf | ||
| Attachment_3_-_BDO_Gate_Submittal_Register.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question Government response Reference
1 Can I add crash bar hardware and reuse the existing gates? No. The existing gates are to be removed and disposed of and new gates are to be installed. 2.6.2
Can I lift, rotate 180 degrees, and reuse the vertical poles surrounding gate A?
The vertical support poles around Gate A are not to be reused. Both posts around Gate A shall be replaced with new posts that are specifically constructed to support the new hinge and latch locations 2.6.1.1.2
3 Are there any requirements for the concrete walkway surrounding the southern post of Gate A?
Removal of the existing posts and concrete footers shall not damage the walkway on either side of the gate. New posts and footers shall be isolated from the walkway through the use of sonotubes or other means so as to eliminate or reduce vibrations from transmitting between post and sidewalk.
Request clarification regarding the preferred construction type for the new gate, I.e.: chain link, wrought iron, ornamental rods, etc.. new gates shall be chain link with 3 strands of barbed wire across the top 2.6.2.9 and 2.6.2.10
Contractor Questions and Government responses: BDO Gate Corrective Actions (140L2624Q0003)