Government_Responses_to_Contractor_Questions_0001.pdf

PDF 93 KB Posted

Attached to
Henry's Lake Aggregate Hauling
Solicitation number
140L2623Q0080
Issued by

About this file

This document contains the government's responses to contractor questions regarding solicitation number 140L2623Q0080 for Henry's Lake Aggregate Hauling from the Department of the Interior Bureau of Land Management Idaho Region. The government clarified that the contractor will be required to provide all necessary equipment for the project, including any loaders needed for transporting crushed aggregate spoil material.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question Government response Reference 1 Will this project require a loader as well as the truck to transport or will there be a loader on site. Contractor will provide all required equipment 2 What type of aggregate is being transported? Crushed aggregate spoil material <3/4 minus.

Can you specify how the aggregate will be presented at pickup? WIll it be loaded into super sacks or palletized? We are trying to identify what equipment will be needed at pickup site Piles of rock on compacted earth. see Fr-65-s Reject Piles

By the description below the word 'Stockpiles". I just want to verify that the trucks will just be dumping "Piles''? Which would be an end dump trailer versus using side dump trailers. What would BLM prefer?

End dump trailers or side dump trailers? Stockpiles may be dumped piles. Method at contractors discretion.

PWS 1.6.6 Project Boundary Marking

You state you need weight tickets to confirm quantities. Are you supplying a scale or do we need to go find one in the area?

Government is not supplying scales. Also acceptable method - Truck bucket size and approximate fill level. Contractor verifies bucket fill level/volume via ticket.

I wanted to reach out and ask if there is any bonding required for the Henry's Lake Aggregate Hauling project? Bonding is not required.

7 What type of aggregate material will be hauled? Crushed aggregate spoil material <3/4 minus.

In Attachment 1 it states “All material shall be verified by delivery ticket with delivery volume.” We are questioning how this is to take place?

Truck bucket size and approximately fill level. Contractor verifies bucket fill level/volume via ticket.

What type of trucks are allowed for "conventional type hauling" (ie. dump truck, side dump or belly dump) Dump truck, side dump and belly dump are allowed.

10 Could you please clarify what is required for the traffic control plan? Traffic control plan should be sufficient to demonstrate warning and handling of traffic. PWS 4.2.3 11 When bidding is complete, will we see results for who gets the job? Notice of award will be posted on SAM.

Contractor Questions and Government responses: Henry's Lake Aggregate Hauling (140L26-23-Q-0080)

Sheet1

File details come from the government source that posted it. Updated .