This is a Statement of Work (SOW) for an Amended Reading Island Paving Repairs project managed by the Bureau of Land Management (BLM) Redding Field Office in Cottonwood, California. The contractor must furnish all labor, equipment, materials, supervision, and incidentals necessary to complete asphalt pavement repair and overlay work over approximately 94,000 square feet of site road and parking lot within a 45-calendar-day performance period from issuance of Notice to Proceed.

The work comprises eight primary tasks: Mobilization (including pre-work site meeting, mix design submission, and project coordination); Full-Depth Repairs of approximately 4,000 square feet involving sawcutting, removal of failed asphalt and unsuitable base to competent subgrade, placement of 6 inches of aggregate base and 2 inches of HMA, with undercut not to exceed 10 inches without written COR approval; Surface Preparation including sweeping, vegetation removal, crack sealing with hot-applied rubberized asphalt sealant for cracks 1/4 inch or greater, and leveling course application; Tack Coat application between all lifts following FP-14 rates; Asphalt Overlay consisting of two 0.10-foot compacted lifts (0.20-foot total) of 1/2-inch NMAS PG64-10 mix compacted to minimum 92 percent Maximum Theoretical Density; Shoulder Backing of 3 inches compacted Class II aggregate base; Quality Control including mix design submission, haul tickets, and density testing verification; and Site Restoration and Demobilization. Work occurs at Reading Island Campground, accessed via the Adobe Road bridge over Anderson Creek, with all construction traffic subject to California legal load limits (80,000-pound gross vehicle weight maximum), single-vehicle crossing requirements, and bridge access restrictions. Prior to NTP, the contractor must submit and obtain COR approval for project schedule, Quality Control Plan, and HMA mix design and material submittals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C, UNIFORM CONTRACT FORMAT (UCF)

DESCRIPTION / SPECIFICATION / STATEMENT OF WORK (SOW)

SOW Page i

Amended Reading Island Paving Repairs Bureau of Land Management / CA-NOD / Redding FO

Table of Contents SOW 1.0 Background on the Government’s Requirement

SOW 2.0 General Scope of Work

Place of Performance:

Period of Performance:

SOW 3.0 Overall Objectives

SOW 4.0 Specific Tasks

Task 1 – Mobilization

Task 2 – Full-Depth Repairs (~4,000 SF)

Task 3 – Surface Preparation

Task 4 – Tack Coat

Task 5 – Asphalt Overlay

Task 6 – Shoulder Backing

Task 7 – Quality Control

Task 8 – Site Restoration and Demobilization

SOW 5.0 Delivery / Performance Schedule

SOW 6.0 Government-Furnished Property

General

Applicable Publications (Current Editions)

SOW 7.0 Security and Administrative Matters

SOW 8.0 Technical Exhibits and Definitions

EX-1 Schedule of Work Deliverables

EX-2 Maps

EX-3 Photos

SOW Page ii

THIS PAGE INTENTIONALLY LEFT BLANK

SOW Page 1

SOW 1.0 Background on the Government’s Requirement BLM Redding Field Office requires pavement rehabilitation at Reading Island Campground. Reading Island Campground is a high-volume use area that offers numerous recreation opportunities for hunting, camping, hiking, boating, picnicking, and wildlife viewing.

The parking lot and site road have extensive cracking and full-depth pavement failure with unsafe shoulder drop-off. They were last paved over 30 years ago. The site road and parking lot exhibit fatigue cracking, potholes, and structural degradation. This project will perform targeted full-depth repairs, and a two-lift asphalt overlay to extend service life and improve safety.

SOW 2.0 General Scope of Work The Contractor shall furnish all labor, equipment, materials, supervision, and incidentals necessary to complete asphalt pavement repair and overlay over approximately 94,000sf of site road and parking lot.

Place of Performance:

See Technical Exhibit 4 – Maps.

Reading Island Campground Cottonwood, California Approx. Coordinates: 40.389944°, -122.197759°

Period of Performance:

45 calendar days from Notice to Proceed.

SOW Page 2

SOW 3.0 Overall Objectives The objective of this work is to restore pavement integrity, extend functional life, and improve safety. The work will be performed in four areas of the campground: (1) entrance site road, (2) parking lot, (3) full depth repair within parking lot, (4) lower site road. See Figure 3. Project Site Map.

• Site Roads o Upper half from the county bridge to the parking lot o Lower half from the parking lot to group camp site o 20ft wide x 2,700ft long o Approximately 54,000 sf o See EX-3 Photos

• Parking Lot (3) o Approximately 40,000 sf o Site of 4000sf of Full Depth Repair – see Task 2 o See EX-3 Photos

SOW 4.0 Specific Tasks Task 1 – Mobilization

• Coordinate with COR to arrange pre work site meeting

• Confirm Delivery/Performance Schedule

• Submit mix design and material order sheets

• Upon receiving NTP, mobilize as per approved Delivery/Performance Schedule

• Survey/Layout: No formal construction surveying is anticipated. The work generally follows the existing paved footprint and existing grades except for localized corrections necessary to provide positive drainage and smooth transitions. The Contractor remains responsible for construction layout and measurements necessary to execute the work in accordance with the contract requirements.

Task 2 – Full-Depth Repairs (~4,000 SF)

• Full-depth repair areas shown on Figure and will be field marked by COR before

NTP.

• Quantity is estimated, actual may vary within contract terms

• Contractor shall sawcut neat boundaries

• Contractor shall remove failed asphalt and unsuitable base to competent subgrade.

SOW Page 3

• Existing asphalt within designated full-depth repair areas may be ground or pulverized as part of the Contractor’s means and methods. Suitable reclaimed asphalt/grindings may be reused as fill/base within the repair areas when properly placed, graded, and compacted to provide a firm and stable section prior to localized leveling and placement of the final HMA overlay. Unsuitable material shall not be incorporated into the pavement section.

• Proof roll subgrade

• Place 6 inches aggregate base

• Place 2 inches HMA

• Compact to required density

• Full-depth repair areas shall be repaired to section depth as specified, then incorporated into the final two-lift overlay work.

o If unsuitable subgrade material is encountered below the specified excavation depth, the Contractor shall notify the COR. The COR will determine the limits of additional excavation (undercut) required.

o Undercut is anticipated to be a minor quantity adjustment and shall be handled within the contract.

o Undercut shall not exceed 10 inches below the specified section without written approval from the COR.

• Excess rock, pavement grindings, and other suitable inert construction material not incorporated into the work may be stockpiled in the BLM-designated clearing immediately north of the parking lot. The COR will identify the stockpile location in the field. Unsuitable material shall be disposed of by the Contractor in accordance with applicable requirements.

Task 3 – Surface Preparation

• Sweep and clean pavement

• Remove vegetation and debris

• Clearing/Tree Limbs: No general clearing and grubbing is anticipated or required as a separate work item. If minor tree-limb trimming is necessary for safe equipment access, the Contractor shall coordinate trimming limits with the COR before performing the work. Approved vegetative debris shall be lopped and scattered within the swale east of the parking lot. Removal of trees is not authorized unless specifically approved by the Government.

• Cracks 1/4 inch or greater in width outside designated full-depth repair areas shall be cleaned of loose material, vegetation, dirt, and debris and sealed prior to HMA placement using a hot-applied, rubberized asphalt crack sealant suitable for flexible asphalt pavement.

SOW Page 4

• Crack sealant shall be installed in accordance with the manufacturer's recommendations. Cold-applied crack fillers or sealants shall not be used unless specifically approved by the COR.

• Crack sealant shall be allowed sufficient time to cool, set, and cure as applicable in accordance with the manufacturer's recommendations prior to application of tack coat and placement of HMA. Excess sealant or other material that would interfere with tack coat application or bonding of the HMA overlay shall be removed or corrected prior to paving.

• A leveling course may be applied as needed to correct surface irregularities prior to placement of the asphalt overlay. Leveling course shall be included in the unit price for asphalt overlay and shall not be paid for separately.

• Apply leveling course as necessary to provide a smooth, uniform surface suitable for placement of the specified HMA overlay.

Task 4 – Tack Coat

• Apply tack coat between all lifts

• Follow FP-14 application rates

Task 5 – Asphalt Overlay

• Place two lifts of HMA (0.10 ft each)

• For bidding and construction, the required overlay is two 0.10-foot compacted HMA lifts, for a total compacted overlay thickness of 0.20 foot.

Placement as a single 0.20-foot lift is not an approved substitution.

• Roadway Width: Match the existing paved roadway width. The project does not require widening roadway sections to a uniform 18-foot width. The new overlay shall generally follow the existing pavement limits unless otherwise directed by the COR.

• Use 1/2-inch NMAS PG64-10 mix

• Compact HMA to a minimum of 92 percent of Maximum Theoretical

Density (Rice Density).

Task 6 – Shoulder Backing

• Shoulder backing shall consist of 3 inches of compacted Class II aggregate base at the finished asphalt edge, placed level with the finished asphalt grade and tapered to match existing grade over an approximately 2-foot horizontal width along each side of the site road.

Task 7 – Quality Control

• Submit mix design

• Provide haul tickets

SOW Page 5

• Density testing shall verify a minimum of 92 percent of Maximum Theoretical Density (Rice Density). The Government anticipates use of a calibrated nuclear density gauge operated by qualified personnel for routine density testing. Alternate non-destructive methods, including PQI, may be proposed for Government review and approval. The Government reserves the right to require verification by asphalt core sampling where necessary to resolve discrepancies or verify compliance.

• Correct deficiencies

Task 8 – Site Restoration and Demobilization

• Cleanup all construction debris

• Arrange final walkthrough of site with COR

SOW 5.0 Delivery / Performance Schedule Contractor shall complete all work within 45 calendar days from issuance of Notice to Proceed (NTP).

Prior to issuance of NTP, the Contractor shall submit the following for Government review and approval:

• Project schedule (including sequencing of all major tasks)

• Quality Control (QC) Plan

• HMA mix design and material submittals

All submittals must be reviewed and accepted by the Contracting Officer’s Representative (COR) prior to issuance of NTP.

A pre-work (preconstruction) site meeting shall be held between the Contractor and the Government prior to start of construction activities, see Task 1 – Mobilization.

The meeting shall include, at a minimum:

• Review of project scope and schedule

• Identification of full-depth repair areas

• Discussion of traffic control, site access, and staging

• Review of safety requirements and communication protocols

• Coordination of inspection and quality control procedures

SOW Page 6

No on-site construction work shall begin until:

1. Required submittals have been approved, and

2. The pre-work site meeting has been completed, and

3. NTP has been formally issued

The Contractor shall perform the work in accordance with the approved schedule and coordinate all activities with the COR.

The Government will review submittals within a reasonable period before issuing NTP;

however, delays due to incomplete or inadequate submittals shall not justify extension of the period of performance.

SOW 6.0 Government-Furnished Property General The Contractor shall furnish all personnel, materials, equipment, supplies, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the work tasks defined in this Statement of Work.

Applicable Publications (Current Editions)

• FHWA Standard Specifications for Construction of Roads and Bridges (FP)

• AASHTO Guide Specifications for Design of Pavement Structures

• ASTM standards for asphalt materials and compaction testing

SOW 7.0 Security and Administrative Matters Contractor shall comply with OSHA, Federal, State, and BLM safety requirements. Site closed to public. Contractor responsible for safety, environmental compliance, and coordination with COR.

Security:

The Contractor shall be responsible for safeguarding all Contractor property outside of normal business hours. BLM not responsible for any acts of vandalism or theft of unsecured Contractor property.

SOW Page 7

Site Access:

Reading Island Campground is located on an island and is accessed through a locked gate. The COR will provide the Contractor with the gate combination. The campground will be closed to the public during construction.

Construction Water:

BLM will not provide a construction water source. The Contractor shall furnish and transport all water required to perform the work. The cost of construction water may be incorporated into applicable bid items or separately identified in the Contractor’s price proposal.

Bridge Access and Construction Traffic:

• The project is accessed via the Adobe Road bridge over Anderson Creek (Shasta County Bridge No. 06C0203). The bridge is a single-lane bridge maintained by Shasta County.

• Shasta County Roads has confirmed that the bridge accommodates California legal loads without special load restrictions.

• All construction vehicles and equipment shall comply with applicable California legal vehicle weight and dimensional limits. Applicable California legal-load limits generally include a maximum gross vehicle weight of 80,000 pounds (40 tons), maximum single-axle weight of 20,000 pounds (10 tons), and maximum tandem-axle weight of 34,000 pounds (17 tons).

• These limits are not interchangeable. Vehicles shall comply with all applicable requirements for gross vehicle weight, axle and axle-group loading, axle spacing, tire loading, vehicle dimensions, and other California legal-load requirements.

• Construction traffic shall cross the bridge one vehicle at a time.

• Staging, parking, or storage of construction vehicles, equipment, or materials on the bridge is prohibited.

• Oversize or overweight vehicles requiring special permits shall not be assumed acceptable for access to the project site without prior coordination with the appropriate roadway authority.

• The Contractor is responsible for selecting construction vehicles, equipment, and haul configurations that comply with applicable legal-load and access requirements.

Vault Toilet:

The existing vault toilet will be available for Contractor use during the construction period. The Contractor shall maintain the facility and surrounding area in a clean condition and shall not use the facility for disposal of construction-related materials or waste.

SOW Page 8

Safety:

Contractor shall not require, or allow any employee, engaged in the performance of this Contract to work under conditions which are unsanitary, hazardous, or dangerous to his/her health or safety, as determined under safety and health standards promulgated by the Secretary of Labor under Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C. 327 et seq.) as amended and other Federal, State and applicable local government safety standards.

Department of Labor Code of Federal Regulations Title 29 and other Federal, State and local government safety standards will apply in its entirety to the Contractor.

Examples of applicable safety standards are OSHA 29 CFR 1910, OSHA 29 CFR 1926, California Title 19, "Public Safety", California Title 8, "General Industry Safety Orders", and 41 CFR, Subpart B, "Public Contracts, General Safety and Health Standards."

The Contractor shall also use the “BLM SAFETY AND HEALTH STANDARDS” (The Yellow Book) for reference.

Should the Contractor fail to comply with any of these standards and regulations, the Contractor shall be found to have defaulted on the terms of the contract.

Hazardous Materials and Hazardous Response:

The Contractor shall comply with all applicable Federal, State, and local requirements governing the use, storage, handling, spill response, and disposal of fuels, asphalt products, and other hazardous materials or wastes associated with the work. Any release to the environment shall be immediately controlled when safe to do so and reported to the COR. The Contractor is responsible for cleanup and proper disposal of Contractor-generated hazardous materials and wastes in accordance with applicable requirements.

Public contact:

Contractor personnel may encounter adjacent landowners or members of the public during the performance of their work.

Contractor personnel will present a professional appearance and be able to provide appropriate identification, including display of proper identification by each employee.

All Contractor and subcontractor personnel shall comply with all Federal and State laws relative to citizenship.

Contractor personnel shall inform any trespassers along the right of way of hazards and, as necessary and appropriate, ask trespassers to leave fenced off or restricted areas.

SOW Page 9

If Contractor personnel may encounter emergency personnel, policemen, or firemen along the right of way, the Contractor personnel shall notify the On-Site Foreman

If Contractor personnel encounter the news media, they should refer all questions to the On-Site Foreman, who shall keep the COR informed of all news media contacts.

Government Observations:

Government personnel other than COR may from time to time observe, photograph, or otherwise record Contract operations.

However, these personnel will not interfere with Contractor performance.

Regular Work Hours:

The performance period established for this contract is based upon all work being conducted during regular working hours between 8:00am and 4:30pm, Monday through Friday, excluding government holidays.

If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the COR in sufficient time to allow satisfactory arrangements to be made for access to the work site.

Communications:

“Time” for communications received after 3:00pm, after 12:00 pm locally on Fridays, or after 12:00 pm locally prior to a holiday will not start until the next business day. All times are local Pacific Standard Time.

Federal Holidays:

The following Federal Legal Holidays are observed:

New Year’s Day Martin Luther King, Jr. Day President’s Day Memorial Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day

Fire Danger Season:

If the Contracting Officer Representative (COR) allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.

SOW Page 10

Preservation of Historical and Archeological Data:

The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.

If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.

Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.

The Contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the Contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.

SOW Page 11

SOW 8.0 Technical Exhibits and Definitions

Standard Definitions:

Physical Condition The Physical appearance of Federal equipment or facilities that considers cracks, chips, dents, abrasions, rust, corrosion, general cleanliness, vibration, operating temperature, and discoloration and other items as identified by the COR..

Physical condition may be determined by visual as well as diagnostic means.

Contracting Officer (CO) The Secretary of the Interior or designated authorized representative who is the only agent capable of signing a federal award or obligating funds.

Contracting Officer’s Representative (COR) The Contracting Officer’s designated representative as indicated in a delegation of authority letter.

Quality Assurance (QA) Surveillance of Contractor performance to determine performance requirements are met.

Performance Requirements Summary (PRS) (see Technical Exhibit below) The PRS identifies the key performance indicators of the Contract that will be evaluated by the Government to assure Contract performance standards are met by the Contractor.

Quality Control Those actions taken by the Contractor to control the production of goods or services so that they meet the requirements of the performance work statement.

SOW Page 12

Technical Exhibits

EX-1 Schedule of Work Deliverables Contractor shall submit the proposal documentation required by the solicitation, including the Technical Capability Documentation specified in Sections L and M.

Following award and prior to NTP, the Contractor shall submit the project schedule, QC Plan, HMA mix design, and material submittals required by SOW 5.0.

AMENDMENT CLARIFICATION: Volume 2 technical proposal requirements are governed by the amended solicitation Sections L and M. The applicable Technical Capability Documentation subfactors are: (1) Relevant Construction Experience (Past Performance), (2) Estimated Material Takeoff, (3) Key Personnel Qualifications, and (4) Preliminary Performance Schedule. Superseded requirements for a separate construction plan/project schedule and references to shared-use paths, trails, conformed grinding, or pavement markings are not applicable to the Reading Island project.

SPECIFIC TASK

DELIVERABLE

START DATE END DATE

Task 1 – Mobilization Task 2 – Full-Depth Repairs

Task 3 – Surface Preparation

Task 4 – Tack Coat Task 5 – HMA Overlay

½” NMAS, PG64-10,

placed in two lifts at 0.10 ft compacted thickness per lift

Task 6 – Shoulder Backing

Task 7 – Quality Control Task 8 – Site Restoration and Demobilization

SOW Page 13

EX-2 Maps

Figure 1 - Project Location - Approximately 5.5 miles east of Cottonwood, CA

SOW Page 14

Figure 2. Road Access to Campground - ~5.5 miles east of Cottonwood, CA

SOW Page 15

Figure 3. Project Site Map

SOW Page 16

EX-3 Photos

START ON NEXT PAGE

SOW Page 17

Figure 4. Reading Island Site Road Entrance

SOW Page 18

Figure 5. Reading Island Full Depth Repairs Area

SOW Page 19

Figure 6. Reading Island Site Road to Group Campsite

SOW 1.0 Background on the Government’s Requirement
SOW 2.0 General Scope of Work
SOW 3.0 Overall Objectives
SOW 4.0 Specific Tasks
Task 1 – Mobilization
Task 2 – Full-Depth Repairs (~4,000 SF)
Task 3 – Surface Preparation
Task 4 – Tack Coat
Task 5 – Asphalt Overlay
Task 6 – Shoulder Backing
Task 7 – Quality Control
Task 8 – Site Restoration and Demobilization
SOW 5.0 Delivery / Performance Schedule
SOW 6.0 Government-Furnished Property
General
Applicable Publications (Current Editions)
SOW 7.0 Security and Administrative Matters
SOW 8.0 Technical Exhibits and Definitions
EX-1 Schedule of Work Deliverables
EX-2 Maps
EX-3 Photos