B08_SOW_0001.docx

DOCX document 17 KB Posted

Attached to
IMPERIAL SAND DUNES RE-SURFACING 52, 000 tons of ag
Solicitation number
140L1221Q0028
Issued by

About this file

This scope of work document outlines requirements for a federal contract to deliver aggregate base materials for road resurfacing projects within the Imperial Sand Dunes Recreation Area. The Bureau of Land Management seeks a contractor to furnish labor, equipment, supplies and materials to produce and deliver 22,525 tons of Class II aggregate base meeting Caltrans specifications. Delivery will occur over 28 consecutive calendar days, with 1,500 to 1,625 tons delivered per day via bottom dump trucks to three specified sites. The contractor must provide weighmaster certificates and have the ability to complete five delivery rounds per day with trucks departing two minutes apart. Performance is expected to begin on July 12, 2021, with the BLM coordinating start times and locations.

View the file

Other files

File Type Posted
A06_Road_Location_Map.pdf PDF
Sol_140L1221Q0028.pdf PDF
A04_SOW_Revised.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work or Services:

OBJECTIVE:

The Bureau of Land Management (BLM) seeks a qualified contractor/vendor to deliver natural aggregate road base material for Wash Road Re-surfacing Project and Campground pads along Gecko Road. Gecko Road is a paved road while Wash Road is an aggregate/natural surfaced roadway. The supplies to be delivered, and all related work to be accomplished, under this contract includes all labor, supervision, transportation, equipment, tools, supplies, and materials necessary for producing and delivering 22,525 tons of aggregate base as specified.

A. Description of Work: Furnishing labor, equipment, supplies, and material, to complete the necessary work as described.

1) Class II aggregate road base meeting Caltrans Standard Specification Section 26 – Aggregate Base (3/4 minus). Natural aggregate road base only.

2) Deliver 1,500 to 1,625 tons per day. Each delivery round consists of 12 to 13 trucks, departing rock quarry two (2) mins apart, a total of five (5) delivery rounds per day.

A. Site #1 - 14,500 tons B. Site #2 - 4,750 tons C. Site #3 - 3,275 tons

3) Deliver aggregate road base by bottom dump trucks.

4) The contractor shall provide the weighmaster certificate tickets to BLM Point of Contact (POC)

PERFORMANCE PERIOD:

Contractor will have 28 consecutive calendar days to deliver all aggregate road base with NO weekend delivery. The anticipated work is planned for Monday July 12th, 2021. The BLM will coordinate with the contractor for starting site and time.

LOCATION:

Imperial Sand Dunes Recreation Area Site #1 - Wash Road (Lat/Long: 32.9623, -115.0238) Site #2 – Gecko (Lat/Long: 32.9441, -115.1460) Site #3 - Roadrunner (Lat/Long: 32.9102, -115.1168) See location map