Attachment_6_Questions_and_Answers_1_0001.pdf

PDF 65 KB Posted

Attached to
FILLMORE ADMINISTRATIVE SITE REPAIRS
Solicitation number
140L0625Q0012
Issued by

About this file

This document is a Questions and Answers (#1) attachment for the Fillmore Administrative Site Repairs solicitation (140L0625Q0012). The Q&A provides seven key clarifications for potential contractors, including specifics about lighting, HVAC, and renovation work. Notable details include: LED light replacements should use Spaulding Lighting from Hubbell Lighting (Cimarron Series CL1-A-90LU-5K-3-DB), only fan motors need replacement for restroom fans, O&M manuals will be available post-contract award, and the contractor is responsible for removing wall hanging items before work. Additional technical specifications clarify that new water piping must be Type L copper tubing, existing countertop bull nose pieces can be reattached from stored materials, and only lever locks need replacement for door hardware, not entire door hardware assemblies.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fillmore Administrative Site Repairs Solicitation: 140L0625Q0012 Questions & Answers #1

Question Answer

1 Can the pulse start metal halide lights be converted to LED?

Yes. An LED replacement should be Spaulding Lighting from Hubbell Lighting, Cimarron Series CL1-A-90LU-5K-3-DB or an approved equal. This note has been updated on drawing sheet E100 also and will be included in Amendment #1 of the Solicitation.

2 Does the entire restroom fan need to be replaced or just the motor? Just the fan motor's need to be replaced.

Are O&M manuals available for HVAC units to aid in selecting the correct motor replacements?

Yes O&M manuals can be made available after contract award.

The motor types and sizes have also been called out on sheet M100 in the drawings.

Who's responsibility is it to remove wall hanging items prior to patching and painting sheetrock?

It will be the Contractor's responsibility to remove all wall hanging items including TV's in conference room.

Do the countertop bull nose pieces need to be replaced with new pieces?

No, all of the existing pieces that have fallen off are stored at the Field Office and will be made available prior to commencing work. The pieces just need to be re-attached.

6 Is PEX piping allowed?

No, all new water piping shall be Type L copper tubing as specified in Section 221116 - Domestic Water Piping.

Sheets A100-A300 call for door hardware to be replaced on selected doors. Does all hardware need to be replaced including hinges, closers, etc? No, only the lever locks need to be replaced.