SOW_BLM_Alaska_Tower_Repairs_2024.docx

DOCX document 39 KB Posted

Attached to
TOWER REPAIR/ MICROWAVE INSTALL Federal contract opportunity
Solicitation number
140L0224Q0011
Issued by
Department of the Interior Bureau of Land Management

About this file

This document is a Statement of Work (SOW) issued by the Bureau of Land Management (BLM) for the repair of steel communications towers and installation of an Aviat Eclipse Microwave System at five radio infrastructure sites within the state of Alaska. The work involves coordinating with BLM points of contact, performing repairs identified in prior inspection reports, installing the microwave system, and providing documentation and photos of the completed work. The vendor must submit project submittals, a safety plan, and adhere to OSHA and other project requirements. The repairs must be completed by August 15, 2024, and the vendor will deliver site-specific reports and photos to BLM by September 15, 2024. This SOW is related to the federal contract opportunity with Solicitation Number 140L0224Q0011 for "TOWER REPAIR/ MICROWAVE INSTALL" issued by the Department of the Interior Bureau of Land Management.

View the file

Other files for this federal contract opportunity

Other files attached to TOWER REPAIR/ MICROWAVE INSTALL, newest first.
File Type Posted
Sol_140L0224Q0011_Amd_0001.pdf PDF
Sol_140L0224Q0011.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. INTRODUCTION

1.1. General

This statement of work (SOW) issued by the Bureau of Land Management (BLM) is for physical repair of steel communications towers within the state of Alaska and for installation of an Aviat Eclipse Microwave System. Physical climbing of the communication towers is required; This scope of work describes the minimum level of performance required by the government. Alternate locations are not accepted. A complete report of repairs will be needed upon completion of project.

1.2. Location

Five (5) Radio Infrastructure (RI) sites within the state of Alaska. See section 2 for specific locations.

1.3. Background Comment by Schumacher, Mariah L: Trim down

The Department of Interior Office of Chief Information Officer (DOI OCIO) policy requires that all DOI Telecommunications Towers must meet ANSI/TIA-222 standards. Per ANSI/TIA-222 Revision G, structural inspections are required for self-supported towers every 5 years, and guyed towers every three years. Inspections were performed in Spring of 2023 and identified a list of minor repairs required for each site. A new Aviat Eclipse Microwave System was purchased by BLM Alaska Fire Service in 2020, but tower inspections had to be performed before installation could commence. The intent of this project is to perform repairs needed for ANSI/TIA-222 compliance for each tower noted in this document, as well as install the Aviat Eclipse Microwave System on the Ester Dome and Fort Wainwright towers and add hot standby ODU to Totson Aviat Eclipse and realign path between Totson and Galena.

1.4. Description of Work

The vendor will contact BLM point of contact (POC) for the 5 Radio Infrastructure (RI) sites to coordinate scheduling and access to each RI site. Vendor will perform repairs identified in prior inspection report and install Aviat Eclipse Microwave System. Final report shall include formatted digital photos of repairs and installed equipment.

1.5. Government Furnished Items

Government shall provide all parts required for Aviat Eclipse Microwave installation. No additional items will be furnished by the BLM under this contract. The Contractor shall furnish all items associated with tower repair.

1.6. Government Furnished Transportation

BLM will provide fixed-wing air transportation from Fort Wainwright AK to Galena AK and Fort Yukon AK, ground transportation within Galena AK, and helicopter transportation from Galena AK to Totson Mt. site for all Contractor personnel and equipment. Contractor must coordinate with POC in advance for approval of personnel numbers and equipment weight for Totson Mt. site due to Helicopter weight/space limitations.

Contractor will provide own transportation to Fairbanks Alaska and ground transportation within the Fairbanks area to the Fort Wainwright and Ester Dome sites.

Fort Wainwright site is located on a US Army Installation. Contractor is responsible for obtaining base access passes for all personnel.

2. PROJECT OVERVIEW

The work under this project includes the following sites:

Site Name
Elevation (Feet)
Latitude
Longitude
Primary Access (Type and Period)
Tower Height
Fort Wainwright
382 ft
N 64° 50.5250'
W 147° 35.2369'
2WD, Year-Round
80 ft
Ester Dome
2360 ft
N 64° 52.5643'
W 148° 4.0566'
2WD, Year-Round
100 ft
Fort Yukon
474 ft
N 66° 34.2898'
W 145° 14.6273'
Fixed Wing, May-Sept
30 ft
Galena Station
128 ft
N 64° 44.311'
W 156° 56.273'
Fixed Wing, May-Sept
30 ft
Totson Mt.
2600 ft
N 64° 26.8738'
W 157° 17.9159'
Helicopter from Galena AK, May-Sept
20 ft

The vendor will use the current revision of ANSI/TIA-222 to determine structural reliability of steel communication tower. The vendor will submit final documentation and photos to the AFS Radio Shop

The vendor tasks will consist of:

1- Coordination with POC.

2- Perform repairs to all tower site findings in previous ANSI/TIA-222 inspection reports.

3- Install and align Aviat Eclipse Microwave System on Fort Wainwright and Ester Dome Towers.

4- Install hot standby ODU on Totson tower and realign path between Totson and Galena towers.

5-Prepare digital reports with repairs and formatted digital photos for each site above.
6-Files and all information associated with the performance of this task will be provided to BLM.

3. GENERAL REQUIREMENTS Comment by Schumacher, Mariah L: Competent climber requirement?

3.1. Scope of Work Requirements

The project will include the following:

1. Review site data.

2. Provide project submittals.

3. Provide schedule of work.

4. Provide project safety plan.

5. Plan site visits.

6. Secure work area and provide for continued access to the facility and BLM operations.

7. Perform tower repairs, microwave installation and path alignments.

8. Verify safety and operability of all project sites.

9. Provide documentation and photos of completed work.

3.2. Project Submittals

The following deliverables shall be submitted a minimum of one week prior to the first inspection:

A.Letter designating your Project Supervisor (individual must always be present during performance in the Government facilities).
B.Project Schedule
C.Accident Prevention Program
D.List of subcontractors (must be same as in the offeror’s response package). Prime contractor is responsible for making sure all subcontractors follow applicable labor standards.
E.Evidence of liability insurance coverage and workmen’s compensation for the contractor.

3.3. Accident Prevention

Accident Prevention Program: Prior to the first inspection, submit an accident prevention program. The program must be accepted by the BLM before any on site work can begin. The program shall comply with OSHA and project requirements. Include the following: Will sign letter of release of liability to the government before climbing towers.

Name of responsible supervisor to carry out the program; periodic safety meetings; first aid procedures; outline of each phase of work, hazards associated with each phase and methods proposed to ensure property protection and safety of the public, Bureau of Land Management staff and contractor employees; training; and planning for possible emergency situations.

Note: Work is to be performed at unprotected structures high above ground level. Work requires the submittal of Site-Specific Job Safety Analysis (JSA) and Site-Specific Fall Protection Plan.

Accident Prevention Products:

Provide the following:

A. First aid facilities.

B. Fall Protection Equipment: meet requirements of American National Standards Institute / American Society of Safety Professionals (ANSI/ASSE) Z359 Fall Protection and Fall Restraint Standards.

C. Fall protection plan.

D. Hard hats for all employees.

E. Designate and post signs in all hardhat areas.

Accident Reporting:

Reportable accidents, defined as death, occupational disease, traumatic injury to contractor’s personnel, BLM employees or the public, property damage of any accident in excess of $100, and fires, must be reported within seven days. Complete the Accident/Property Damage Report, and forward to the Contracting Officer.

4. Deliverables The vendor will provide all intellectual property to BLM via electronic delivery.

4.1. Schedule of Deliverables

Physical repair work will be completed by August 15th, 2024. Repairs will address issues identified in attached inspection reports.

Tower Deficiencies
Site
Materials Required
Solution/Repair
Foundation Coating Failing
Fort Wainwright
Rubberized coating
Apply Rubberized Coating to Foundation
Foundation Open Pipe
Fort Wainwright
New Cap Pipe
Cap Pipe
Peeling Paint
Fort Wainwright
Paint & Supplies
Prep/Prime/Coat -Match Aviation Colors
Ground Run Not Attached - Bottom
Fort Wainwright
Beam Clamp
Attach to Horizontal with Beam Clamp
Open Mounts
Fort Wainwright
Rigging Equipment
Remove and Lower Open Mounts
Build, Install, Align Aviat Eclipse Microwave
Fort Wainwright
Line Supporting Materials.
Dress Lines to tower & into shelter, Path Align
Ladder Rail Has Ant w/ Stand-Off
Fort Wainwright
Misc. Equipment
Move Ant to New Location using Open Mount
Build, Install, Align Aviat Eclipse Microwave
Ester Dome Tower
Line Supporting Materials.
Dress Lines to tower & into shelter, Path Align
Safety Cable Guides Need Extended
Ester Dome Tower
Guide Extenders
Install (2) Cable Guide Extenders
One Small Rust Spot (Sec 2-3 N Leg)
Ester Dome Tower
Cold Galvanized Paint
Sand, Coat W/ Cold Galvanized Paint
No Safety Cable Notch (3 Platforms)
Ester Dome Tower
Equipment & Blades
Notch Platforms So Cable Does Not Touch Gate
No Cap on Top of Lad-Saf System
Ester Dome Tower
Rain Cap
Remove/Replace w/ New Lad-Saf Rain Cap
Rusted 3/16" U-Bolts on Top of Lad-Saf
Ester Dome Tower
U-Bolts, Saw Blades
Remove/Replace Rusted Hardware on Lad-Saf
Hole In Rain-Cap on Top of Tower Leg
Ester Dome Tower
9" Metal Rain Cap
Remove/Replace W/ New 9" Rain-Cap
Bolt Touching Lad-Saf Cable @ Top
Galena Tower
Saw Blades, Cold Galv.
Cut Off Extra Bolt Lenth for Cable Clearance
Check and Path alignment to Totson Tower
Galena Tower
None
Path alignment to Totson Tower
Jumper Out Of Port / Open Port
Totson Tower
New 6' Jumper, WP
Remove/Replace/Weatherproof/Support
Topical Rust Foundation/Legs/Members
Totson Tower
Cold Galvanized Paint
Prep Coat w/ Cold Galvanized Paint
Broken Missing Lightening Rod
Totson Tower
New Lightening Rod
Remove/Replace w/ New Lightening Rod
Broken Lad-Saf Rain Cap @ Top
Totson Tower
Rain Cap
Remove/Replace w/ New Lad-Saf Rain Cap
Install New Radio to Micro, Reconfigure
Totson Tower
Line Supporting Materials.
Path alignment to Galena Tower
Rust On Tower Leg by Ground (E. Foot)
Fort Yukon
Cold Galvanized Paint
Sand Rust, Apply Cold Galvanized Coating
Failing Grout @ All Tower Leg Feet
Fort Yukon
Misc. Equipment
Chip out & Remove Grout Completely
Platform Gate Touching Lad-Saf Cable
Fort Yukon
Saw Blades, Cold Galv.
Notch Platforms So Cable Does Not Touch Gate
Rust on Lad-Saf Top Shackle
Fort Yukon
Rigging Equip / Shackle
Remove/Replace w/ New Shackle
Loose T-Arm Mount (25' W Leg)
Fort Yukon
Rigging Equip / New Bolt
Shim Mount & Replace w/ Longer bolt
Description
Action Required
Quantity Required
Delivery Date
Delivery Contact
Format
Ft. Wainwright ANSI/TIA 222 Repairs Report
Deliver to BLM
1
09/15/2024
POC
Electronic
Ester Dome ANSI/TIA 222 Repairs Report
Deliver to BLM
1
09/15/2024
POC
Electronic
Ft. Yukon ANSI/TIA 222 Repairs Report
Deliver to BLM
1
09/15/2024
POC
Electronic
Galena ANSI/TIA 222 Repairs Report
Deliver to BLM
1
09/15/2024
POC
Electronic
Totson Mt. ANSI/TIA 222 repairs Report
Deliver to BLM
1
09/15/2024
POC
Electronic
Ft. Wainwright Site Photos
Deliver to BLM
1
09/15/2024
POC
Electronic
Ester Dome Site Photos
Deliver to BLM
1
09/15/2024
POC
Electronic
Ft. Yukon Site Photos
Deliver to BLM
1
09/15/2024
POC
Electronic
Galena Site Photos
Deliver to BLM
1
09/15/2024
POC
Electronic
Totson Mt. Site Photos
Deliver to BLM
1
09/15/2024
POC
Electronic

4.2. Project Close-out

Cleaning: Before departing site after each inspection, remove all tools, equipment, surplus materials, and rubbish.

Reports: Provide report of repairs performed at each site.

Site Photos: Provide detailed, high-resolution photographs of each repair.