This is Amendment Two to a federal solicitation (140G0326Q0190) issued by the USGS OAG Sacramento Acquisition Branch for a pump skid procurement. The amendment extends the quote due date to August 17, 2026, at 10:00 AM EDT and provides supplemental process information in response to vendor inquiries.
The procurement is for a pump skid system to replace an existing sulfur dioxide gas dechlorination system at a laboratory facility. The new system shall inject liquid calcium thiosulfate (CaTS), 30% w/v NSF-certified solution (approximately 10.4 lb/gal), into an existing 1/2" Schedule 80 PVC carrier line that discharges into a process water culvert/mixing basin. Process water flows at 125–250 GPM (typical approximately 150 GPM) and is chlorinated to approximately 2.5 ppm free chlorine residual with allowances for excursions to 3 ppm at peak flow. The estimated CaTS dosing range is 0.10–0.23 GPH (approximately 2.5–5.5 gal/day). The system requires 115V/60Hz single-phase power with standard NEMA 5-15 receptacle, Siemens Desigo BMS integration (4–20 mA input/output signals, remote start/stop, alarm and run/status outputs), suction from an existing 275-gallon tote, and a new injection assembly (diffuser, injection quill, fittings, and all materials) compatible with liquid CaTS injection. All other requirements remain as stated in the original Statement of Need. No additional drawings, specifications, or P&IDs beyond the Statement of Need will be provided. The solicitation point of contact is Elizabeth Adam, Contracting Officer, at elizabeth_adam@ios.doi.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140G0326Q0190_Amd_0001.pdf | ||
| Sol_140G0326Q0190.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Elizabeth Adam
See continuation page
USGS OAG SACRAMENTO ACQUISITION BR.
MODOC HALL, CSUS
3020 STATE UNIVERSITY DRIVE EAST
SACRAMENTO CA 95819-6027
GSB
140G0326Q0190
08/05/2026
08/05/2026
1 5
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140G0326Q0190/0002
AMENDMENT TWO
The purpose of this Amendment is to answer vendor questions and extend the due dates for quotes:
The due date for quotes is extended to August
17, 2026, at 10:00am EDT.
The Government offers the following supplemental process information in response to a vendor inquiry. No drawings, specifications, or P&IDs beyond the Statement of Need (SON) are available for release. This is a pump skid procurement to replace an existing sulfur dioxide gas dechlorination system. The new skid shall inject liquid calcium thiosulfate (CaTS) into the existing carrier line that discharges the dechlorination stream into the process water culvert/mixing basin; existing SO2 injection hardware is not compatible and shall not be reused. The SON remains the governing document for all requirements.
Q: Do you have drawings, specifications, or a
P&ID available?
A: No. No additional drawings or P&IDs will be provided. A site walk is not being offered; the
SON is sufficient to scope and quote the requirement. The supplemental process data below is provided to assist with pump sizing and quoting.
Application: Dechlorination of laboratory lake process water prior to discharge.
Chemical: Liquid calcium thiosulfate, 30% w/v
(24% w/w), NSF-certified (reference basis:
Tessenderlo Kerley CaTS/Captor, specific gravity approximately 1.22¿1.32, approximately
10.4 lb/gal).
Continued...
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Process configuration: Process water (125¿250
GPM, typical approximately 150 GPM) flows from the settling tank into a culvert/mixing basin.
Dechlorination is performed on a separate branch (carrier) line that delivers a small slipstream of process water, carrying the metered CaTS, into the same culvert/mixing basin, where blending with the full process stream occurs. CaTS is metered into this carrier line, not into the full-flow process stream.
Chlorine load: Process water is chlorinated with 0.8% sodium hypochlorite to approximately
2.5 ppm free chlorine residual following a
1-hour dwell in the settling tank prior to dechlorination. Representative current reading is approximately 150 GPM at approximately 2.25 ppm free chlorine residual. Offerors should allow for excursions up to approximately 3 ppm at peak flow.
Existing dechlorination duty being replaced:
approximately 9 lb/day sulfur dioxide gas.
Estimated CaTS dosing duty (per the manufacturer dechlorination dosage chart, approximately 5.1 gal per million gallons per ppm chlorine at neutral pH, based on the full process flow and chlorine load):
- Typical (150 GPM, 2.25 ppm): approximately
0.10 GPH (approximately 2.5 gal/day)
- Low flow (125 GPM, 2.5 ppm): approximately
0.10 GPH
- Peak (250 GPM, 2.5 ppm): approximately 0.19
GPH
- Peak with excursion (250 GPM, 3.0 ppm):
approximately 0.23 GPH (approximately 5.5 gal/day)
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
The resulting operating band is approximately
0.10¿0.23 GPH, consistent with the high-turndown, low-flow peristaltic metering pump specified in the SON. Estimated values are provided for reference only and do not modify the salient characteristics in Section 4.0.
Chemical storage: Liquid CaTS is supplied and stored in a 275-gallon tote at the storage location; totes are delivered and removed by the chemical supplier as needed. Pump suction shall be configured for tote draw-down.
Utilities and interfaces:
- Power: 115V / 60Hz, single phase, standard
NEMA 5-15 receptacle.
- Controls: Facility BMS is Siemens Desigo.
Required signals are 4¿20 mA input (dosing speed control) and 4¿20 mA output (flow/status feedback), plus remote start/stop, alarm output, and run/status output.
- Suction: CaTS suction shall be run from the existing 275-gallon tote at the storage location.
- Discharge/injection: The new system shall tie into and inject CaTS into the existing 1/2"
Schedule 80 PVC carrier line, which delivers the dechlorination stream into the culvert/mixing basin. The carrier line is a low-flow branch, not the full 125¿250 GPM process stream. Existing SO2 injection hardware is not compatible and shall not be reused; the offeror shall provide a new injection assembly
(diffuser/injection quill, fittings, and all materials) suitable for liquid CaTS injection into the 1/2" Schedule 80 PVC carrier line.
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
All other requirements remain as stated in the
Statement of Need.
No further questions will be accepted.
Solicitation POC:
Elizabeth Adam, Contracting Officer elizabeth_adam@ios.doi.gov
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .