ECONOMIC_PRICE_ADJUSTMENT-MATERIAL_CLAUSE_0005.pdf
PDF 91 KB Posted
- Attached to
- INFRASTRUCTURE UPGRADES ACROSS DELTA Federal contract opportunity
- Solicitation number
- 140G0321R0010
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140G0321R0010_Amd_0008.pdf | ||
| Economic_Price_Adjustment-_Material_(Updated)_0008.pdf | ||
| Attch_3_Pricing_table_(Updated)_0008.pdf | ||
| Sol_140G0321R0010_Amd_0007.pdf | ||
| Sol_140G0321R0010_Amd_0006.pdf | ||
| Questions_and_Answers_Round_2_0005.pdf | ||
| Sol_140G0321R0010_Amd_0005.pdf | ||
| Sol_140G0321R0010_Amd_0004.pdf | ||
| Sol_140G0321R0010_Amd_0003.pdf | ||
| Sol_140G0321R0010_Amd_0002.pdf | ||
| Questions_and_Answers_0002.pdf | ||
| (2)_Attch_2_Statment_of_Work.pdf | ||
| (4)_Attch_4_Exhibit_A.pdf | ||
| (3)_Attch_3_Pricing_table.pdf | ||
| (1)_Attch_1_T_Cs.pdf | ||
| Sol_140G0321R0010.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
52.216-4 Economic Price Adjustment-Labor and Material. (Edited)
ECONOMIC PRICE ADJUSTMENT-MATERIAL
(a) The Contractor shall notify the Contracting Officer if, at any time during contract performance, the rate of pay for the unit prices for material shown in the Schedule either increase or decrease. The Contractor shall furnish this notice within 60 days after the increase or decrease, or within any additional period that the Contracting Officer may approve in writing, but not later than the date of final payment under this contract. The notice shall include the Contractor’s proposal for an adjustment in the contract unit prices to be negotiated under paragraph (b) of this clause, and shall include, in the form required by the Contracting Officer, supporting data explaining the cause, effective date, and amount of the increase or decrease and the amount of the Contractor’s adjustment proposal.
(b) Promptly after the Contracting Officer receives the notice and data under paragraph (a) of this clause, the Contracting Officer and the Contractor shall negotiate a price adjustment in the contract unit prices and its effective date. However, the Contracting Officer may postpone the negotiations until an accumulation of increases and decreases in the unit prices of material shown in the Schedule results in an adjustment allowable under paragraph (c)(3) of this clause. The Contracting Officer shall modify this contract (1) to include the price adjustment and its effective date and (2) to revise the unit prices of material as shown in the Schedule to reflect the increases or decreases resulting from the adjustment. The Contractor shall continue performance pending agreement on, or determination of, any adjustment and its effective date.
(c) Any price adjustment under this clause is subject to the following limitations:
(1) Any adjustment shall be limited to the effect on unit prices of the increases or decreases in the rates of pay for unit prices for material shown in the Schedule. There shall be no adjustment for-
(i) Supplies for which the production cost is not affected by such changes;
(ii) Changes in unit prices other than those shown in the Schedule; or
(iii) Changes in the quantities of material used from those shown in the Schedule for each item.
(2) No upward adjustment shall apply to supplies that are required to be delivered or performed before the effective date of the adjustment, unless the Contractor’s failure to deliver or perform according to the delivery schedule results from causes beyond the Contractor’s control and without its fault or negligence, within the meaning of the Default clause.
(3) There shall be no adjustment for any change in rates of pay for unit prices for material which would not result in a net change of at least 3 percent of the then-current total contract price. This limitation shall not apply, however, if, after final delivery of all line items, either party requests an adjustment under paragraph (b) of this clause.
(4) The aggregate of the increases in any contract unit price made under this clause shall not exceed 10 percent of the original unit price. There is no percentage limitation on the amount of decreases that may be made under this clause.
(d) The Contracting Officer may examine the Contractor’s books, records, and other supporting data relevant to the cost of material during all reasonable times until the end of 3 years after the date of final payment under this contract or the time periods specified in subpart 4.7 of the Federal Acquisition Regulation (FAR), whichever is earlier.
(End of clause)