140G0124Q0032-_sections_B_through_M_0002.pdf

PDF 804 KB Posted

Attached to
HIGH DENSITY MOBILE SHELVING
Solicitation number
140G0124Q0032
Issued by

About this file

This document is a Request for Quotation (RFQ) for the procurement of High Density Mobile Shelving systems for the U.S. Geological Survey (USGS) Reston Library in Reston, Virginia. The RFQ specifies the procurement of electronic power assist, mobile shelving system components and installation services to convert USGS-owned, static steel cantilever shelving units into a high-density, mobile shelving system.

The RFQ is a Firm-Fixed Price contract and is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB). Delivery of the new system is expected within 90 days of award, with an additional 90 days to upgrade any legacy systems originally installed in 1991 and 1997, if those options are exercised. The RFQ includes detailed technical specifications, submittal requirements, and clauses. Interested vendors must submit quotations via email no later than 2:00PM EST on June 3, 2024. A site visit is scheduled for May 9, 2024 at 11:00AM Eastern Time.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Quotation Document No.

140G0124Q0032

Document Title

High Density Mobile Shelving

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 Purpose

The purpose of this contract is to obtain High Density Mobile Shelving for the U.S. Geological Survey (USGS) Reston

Library in Reston, Virginia.

B.2 Contract Type and Services

This is a Firm-Fixed Price contract. The USGS will issue a Firm Fixed Price (FFP) contract for the High Density Mobile

Shelving.

B.3 Pricing

Provide a Discounted Firm Fixed Price for the High Density Mobile Shelving rendered on the Open Market under NAICS

Code: 337215 Showcase, Partition, Shelving, and Locker Manufacturing.

(END OF SECTION B)

Document Title

SECTION C -- DESCRIPTIONS AND SPECIFICATIONS – STATEMENT OF WORK

Reconfiguration, Modification, and Installation of High Density Mobile Shelving

With Optional Upgrade to Existing Shelving Electronics

US Geological Survey Library

Technical Requirements

GENERAL REQUIREMENTS

Contractor shall furnish all facilities, labor, and materials to provide goods/services in accordance with the terms and conditions herein and the specifications set forth below, entitled "Technical Specifications."

TECHNICAL SPECIFICATIONS

1.0 Introduction

The U.S. Geological Survey, Reston Library has a requirement to convert Library owned, steel cantilever shelving into a high-density, mobile shelving system. This procurement is for the fabrication and installation of electronic power assist, mobile shelving system components and installation services to convert static steel cantilever shelving units into a mobile shelving system with moveable aisles.

1.1 Background

As part of nation-wide space efficiencies and consolidation effort by the USGS Libraries Program, the library is transferring all print materials to the Reston Library. Space is limited and will require high density mobile shelving to accommodate the materials within the current space footprint.

Design plans for the new library facility call for conversion of library owned, steel shelving into an electronic powered mobile shelving system to maximize space utilization. The mobile shelving system will house active collections and be available for use by both staff and the public; therefore, the library requires a reliable system designed and constructed for frequent use, ease of movement, and patron safety. As a permanent installation to the library building, the mobile shelving system must be durable, operate in a smooth and even manner to minimize wear on components, and maintain integrity of alignment over the course of many years.

1.2 Scope

Work to be performed includes fabrication and installation of decking, rails, carriages, face-panels, and installation of

Government furnished steel cantilever shelving onto mobile carriages to form a complete mobile shelving system that optimizes library shelving capacity within the defined area designated on the approved architectural furniture plan.

Disassembly of existing Government-furnished shelving and installation through mounting on carriages on-site is required under this contract.

Unloading and reloading of library materials is required under this contract. Need for temporary storage on or off-site is possible and vendor must supply adequate amount of library carts to store and transport library materials. Exact numbers to fill need will be determined during walk-through and final plans for project.

Document Title

Contractor shall supply all supervision, labor, materials, tools, equipment, supplies, and expertise to perform the installation of electronic power assist, high-density mobile shelving. The work shall be coordinated with USGS, General

Services Administration (GSA), and appropriately sequenced with the library construction project.

Contractor is responsible for compliance of all products and installation with all applicable state, local and federal building codes, local ordinances, and regulations.

1.2.1 Location

The mobile shelving system is to be installed at:

USGS Reston Library

950 National Center, Room 1D-100

12201 Sunrise Valley Drive

Reston, VA 20192

Loading Dock and Elevator Available

1.2.2 Updated Approved Construction Drawing Furniture Plan (Attachments 1 and 2)

The mobile shelving system shall be installed in the basement area of the library.

1.2.3 Government Furnished Shelving

The shelving Owner, the Government, will provide and stage at the installation site the double-faced and single-faced shelving units in quantities needed for conversion into a mobile shelving system.

A. Shelving Description: Steel Cantilever Bracket Type Shelving

1. Double-faced units are 20 ½ inches in depth (actual) x 36 inches wide x 84 inches high, with 9-inch-wide base shelves and 8-inch-wide adjustable shelves. Shelving units have a 3-inch-high base plate and shelf, with 5 adjustable shelves on each side of the unit.

2. Single-faced units are 11 1/4 inches in depth (actual) x 36 inches wide x 84 inches high, with 9-inch-wide base shelf and 8-inch-wide adjustable shelves. Shelving units have a 3-inch-high base plate and shelf, with 5 adjustable shelves.

1.3 Date of Delivery and Period of Performance

Delivery of system is expected 90 days from date of award for the new system with an additional 90 days to upgrade legacy systems originally installed in 1991 and 1997, if options 1 and 2 are implemented. Separate requirements are included in Section 5 for options to upgrade legacy systems out of warranty and at end of life.

Document Title

2.0 Scheduling and Coordination

2.1 Scheduling

Upon contract award, a product and installation schedule shall be developed and approved by the Government. Contractor is required to plan an installation schedule which meets the completion dates herein.

2.2 Coordination

Contractor shall provide on-site management and coordination with the USGS and/or GSA project management during the installation.

Parts are to be checked at factory prior to shipping to ensure order is complete and that installation shall not be delayed because of missing parts or an incomplete delivery.

Contractor shall arrange and coordinate all materials deliveries, meet delivery trucks, inspect products, and move products to desired locations.

Coordinate mobile shelving system installation with other work to minimize possibility of damage and soiling.

USGS will provide limited space for staging of mobile system components.

3.0 Supporting Information

Contractor shall follow all National Center security procedures while in accordance with any Federal Protective Service, General Services Administration, or USGS security guidelines.

3.1 National Center Access

Drivers will be required to show valid driver’s license at the National Center Gate. Trucks will be inspected on entry by

Federal Protective Service.

3.2 Parking

Contractor staff may park in any space within the Visitor Lot.

The library will work with facilities managers to ensure the highest availability possible for truck parking during normal business hours.

3.3 Building Access

Contractor shall coordinate with USGS for building access and be responsible for confining crew and work to the designated project areas. Contract staff shall carry visible identification by uniform attire and visitor ID badge, which clearly identifies them as associated with the Contractor.

3.4 Time of Work

Installation shall be conducted during regular business hours. Building hours are 8:00 am – 5:00 pm, Monday – Friday.

Document Title

3.5 Public Access to Library

The facility will be closed to the public and USGS library patrons during the project.

3.6 Storage of Tools and Materials

Contractor may store materials and tools only within the library facility as necessary. Contractor is advised to secure materials, tools, boxes, etc., during the period of work.

4.0 High Density, Electronic Powered Mobile Shelving System Technical Specifications

RELATED DOCUMENTS

Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1

Specification Sections, apply to this Section.

SUMMARY

This Section includes the following:

Electric, carriage mounted high-density mobile storage units, support rails, fabrication, and installation including leveling of support rails.

Related Work, Not Furnished:

1. Structural floor system capable of supporting live and dead loads required by prevailing building codes, including loads of storage units to be installed. Provide a maximum allowable sub floor deflection of L/480 or

L/360 with Automatic Brake under specified mobile storage loads.

2. Finish floor covering and edging materials and installation on raised floors and ramps, or when on concrete with recessed rail installation.

3. Power wiring to units from adequate power supply. Final connections to units shall be provided by the installer or electrician.

4. Fire suppression system is by others.

REFERENCES

American Library Association (when applicable)

Cantilever Bracket Type Metal Library Bookstacks; Library Technology Reports.

American National Standards Institute (ANSI) Standards

Applicable standards for fasteners used for assembly.

American Society for Testing and Materials (ASTM) Standards

Applicable standards for steel sheet materials used for fabrication.

American Institute of Steel Construction (AISC) Standards

Applicable standards for steel materials used for fabrication.

Document Title

Underwriters’ Laboratories (C-UL US)

Listings for electrical equipment and devices described in this specification.

SYSTEM DESCRIPTION

General: The system consists of manufactured, or Government furnished storage units mounted on manufacturer’s track-guided carriages to form a compact storage system. System design permits access to any single aisle by moving units until the desired aisle is opened. The manufacturer’s proprietary unit interlock system prevents units from being moved while the open aisle is occupied. The carriage/rail system provides uniform carriage movement along the total length of travel, even with unbalanced loads.

Carriage System Design and Features: The carriage system consists of a formed structural steel frame with hardened steel or ductile iron wheels riding on steel rails recessed or even with surface mounted to the floor. Rails shall be types selected by the manufacturer to ensure smooth operation and self-centering of mobile storage units during travel without end play or binding. Rail types, quantities and spacing shall be selected by the manufacturer to suit installation conditions and requirements. All bearings used in the drive mechanism shall be permanently shielded and lubricated.

Movement Controls: Provide a carriage control panel on the accessible (open) end of each moveable carriage, located

44 inches (1118 MM) above the base, centered on the face panel. Minimum controls shall include directional control buttons/icons, STOP/RESET push-button/icon and a red reset light/icon.

System controls shall start motors on each movable carriage “sequentially” to minimize power demands or “block” to start all at once and shall provide dynamic braking to provide smooth operation. No additional hardware shall be required to change between “sequential” and “block” movement. Maximum running speed shall be limited to 3.3 inches (84 mm) per second.

Provide solid state controls and indicator lights/icons for a visual indication of safety system operation. Provide each aisle with a programmable distance sensor to ensure proper timing for start/stop operation.

Pushing the directional control button/icon on any moveable carriage adjacent to the desired aisle location in the direction away from the desired aisle location opens the system at the desired aisle. The selected aisle shall open automatically regardless of the position of the carriages.

Manual Reset: The carriage control head will display a flashing red reset light/icon at the newly opened aisle indicating that the aisle is locked open and requires resetting before another aisle can be opened. Provide for automatic lockout and manual reset of controls if selected aisle is not moved within a preset time period.

(Optional) Automatic Reset: The carriage control heads will display a constant green light, or green arrow icon, at all carriages indicating that the system is ready for the next aisle access. Provide for automatic reset if system is equipped with optional sensor system safety feature, or other redundant safeties.

Controls shall feature safety activated message and direction indicator designating which aisle safety was activated or back lit message indicating which aisle is in use (i.e., “Right Aisle in use” or “Left Aisle in use”).

Provide Bluetooth control to replace or in addition to the standard powered control or touch technology system controls.

Infrared Capable Controls and Infrared Remote Control Keys: Provide infrared capable control panel at end of each motorized carriage and two additional handheld infrared remote control user key(s). In lieu of standard control moveable on carriage.

Drive System: The system shall be designed with a positive type of motorized drive which minimizes end play and that carriages will stop without drifting. All system components shall be selected to ensure a smooth, even movement along the entire carriage length.

Document Title

Each electric carriage shall be provided with a current limited fractional horsepower gear motor, connected to drive wheel assembly with a roller chain.

System shall include a chain sprocket drive system to ensure that carriages move uniformly along the total length of travel, even with unbalanced loads.

A tensioning device shall be provided on each chain drive (when applicable).

All bearings used in the drive mechanism shall be permanently shielded and lubricated.

System shall operate on 115 V.A.C. 50/60 hertz, 20-amp dedicated circuit provided by others, one per module.

Overhead mounted power pantograph distribution system shall conceal all interconnecting wiring.

Safety Features:

Visual indicators/icons shall provide verification that carriages are in the locked or unlocked mode.

One safety sweep shall be provided in each aisle. A full-length infrared photoelectric safety sweep shall be provided to stop carriage movement if the sweep contacts an obstruction while in motion. Sweep must be equipped with OSHA approved safety demarcation tape.

Entire system shall be C-UL US system listed.

Sensor system with electric braking devices shall be provided to prevent new carriage movement if the system detects objects or persons in the open aisle when an attempt is made to open another aisle.

An Automatic Battery Backup shall be provided for emergency operations in case of primary power failure.

A handheld rechargeable power pack shall be provided for emergency operations in case of primary power failure.

Finishes:

Fabricated Metal Components and Assemblies: Manufacturer’s standard powder coat paint finish.

End Panels, Accessible Ends: Plastic laminate, manufacturer’s standard available textures and patterns OR

Manufacturer’s standard powder coat paint finish in standard available colors.

PERFORMANCE REQUIREMENTS

Design Requirements:

System height must be a minimum of 18-inches below sprinkler system to provide proper clearance.

Seismic Performance: Provide mobile storage units capable of withstanding the effects of earthquake movement when required by applicable building codes.

SUBMITTALS

Product Data: Submit manufacturer's product literature and installation instructions for each type of shelving, track and installation accessory required. Include data substantiating that products to be furnished comply with requirements of the contract documents.

Shop Drawings: Show fabrication, assembly, and installation details including descriptions of procedures and diagrams. Show complete extent of installation layout including clearances, spacings, and relation to adjacent construction in plan, elevation, and sections. Indicate clear exit and access aisle widths; access to concealed components; assemblies, connections, attachments, reinforcement, and anchorage; and deck details, edge conditions, and extent of finish flooring within area where units are to be installed.

Document Title

Show installation details at non-standard conditions. Furnish floor layouts, technical and installation manuals for every unit shipment with necessary dimensions for rail layout and system configuration at the project site. Include installed weight, load criteria, furnished specialties, and accessories.

Provide layout, dimensions, and identification of each unit corresponding to sequence of installation and erection procedures. Specifically include the following:

a. Location, position, and configuration of tracks on all floors.

b. Plan layouts of positions of carriages, including all required clearances.

c. Details of shelving, indicating method and configuration of installation in carriages.

Provide location and details of anchorage devices to be embedded in or fastened to other construction.

Provide installation schedule and complete erection procedures to ensure proper installation.

Show locations of wiring and disconnects required for operating movable carriage units.

Samples: Provide minimum 3 inch (76MM) square example of each color and texture on actual substrate for each component to remain exposed after installation.

Selection Samples: For initial selection of colors and textures, submit manufacturer's color charts consisting of actual product pieces, showing full range of colors and textures available.

Warranty: Submit draft copy of proposed warranty for review.

Reference List: Provide a list of recently installed mobile storage systems (5 minimum) to be visited by Government, Architect, and Contractor. Intent of list is to aid in verifying the suitability of manufacturer's products and comparison with materials and product specified in this section.

QUALITY ASSURANCE

Manufacturer Qualifications: Engage an experienced manufacturer who is ISO 9001 certified for the design, production, installation, and service of motorized, carriage mounted high-density mobile storage units and support rails. Furnish manufacturer’s ISO 9001 quality system registration certificate.

Installer Qualifications: Engage an experienced installer who is a manufacturer's authorized representative for the specified products for installing carriages and anchoring shelving units to carriages.

Minimum Qualifications: 1-year experience installing systems of comparable size and complexity to specified project requirements.

Guaranteed 24-hour minimum response time to service call.

DELIVERY, STORAGE AND HANDLING

Follow manufacturer’s instructions and recommendations for delivery, storage, and handling requirements.

PROJECT CONDITIONS

Field Measurements: Verify dimensions before fabrication. Indicate verified measurements on Shop Drawings.

Coordinate fabrication and delivery to ensure no delay in progress of the Work.

Established Dimensions: Where field measurements cannot be made without delaying the Work, establish dimensions and proceed with fabricating mobile storage units without field measurements. Coordinate construction to ensure actual dimensions correspond to established dimensions.

Document Title

SEQUENCING AND SCHEDULING

Sequence storage shelving system installation with other work to minimize possibility of damage and soiling during remainder of construction period.

Schedule installation of specified products and accessories after finishing operations, including painting have been completed.

Provide components, which must be built in at a time which causes no delays general progress of the Work.

Pre-installation Conference: Schedule and conduct conference on project site to review methods and procedures for installing mobile storage units including, but not limited to, the following:

Review project conditions and levelness of flooring and other preparatory work performed under other contracts.

Review and verify structural loading limitations.

Recommended attendees include:

Government's Representative.

Prime Contractor or representative.

The Architect, Architect/Engineer, Engineer/Architect, Engineer, Designer.

Manufacturer's representative.

Sub-Contractors or installers whose work may affect, or be affected by, the work of this section.

WARRANTY

Provide a written warranty, executed by Contractor, Installer, and Manufacturer, agreeing to repair or replace units which fail in materials or workmanship within the established warranty period. This warranty shall be in addition to, and not a limitation of, other rights the Government may have under General Conditions provisions of the Contract

Documents.

Warrant the entire movable compact shelving installation against defects in materials and workmanship for a period of five years from date of acceptance by the Government.

MAINTENANCE

Provide manufacturer’s extended maintenance agreement for Five (5) years commencing on the day the standard maintenance warranty ends.

PRODUCTS

MANUFACTURERS

General: Products are based upon mobile shelving system products potentially manufactured by Spacesaver

Corporation. Contingent on meeting specification requirements, other acceptable manufacturers will be considered.

Document Title

BASIC MATERIALS

General: Provide materials and quality of workmanship which meet or exceed established industry standards for products specified. Use furniture grade sheet metal for component fabrication unless indicated otherwise. Material thickness/gauges are manufacturer’s option unless indicated otherwise.

Plastic Laminates: NEMA LD-3, GP-28, Vertical Grade.

Electrical Devices and Controls: C-UL US System Listed for type of application and service.

GROUT

General: Provide non-shrink, non-staining hydraulic cement compound conforming to the following requirements, based on the performance of the test specimens at room temperature and in laboratory air, as stated by the grout manufacturer.

Linear Movement: No shrinkage while setting; maximum expansion limited to .002 inches per linear inch.

Compressive Strength: Based on two-inch cubes made following ASTM standards, tested on a Balding-Southward machine of 60,000 pounds capacity, will meet or exceed the following:

Age: 1 hour ---- 4,500 psi

7 days ---- 8,000 psi

MANUFACTURED COMPONENTS

Rails:

• General: Provide manufacturer's proprietary design units with the following properties:

• Material: ASTM/AISI Type 1035 or 1045 steel, manufacturer’s selection.

• Capacity: 1,000 pounds per lineal foot (1385kg/M) of carriage.

• Minimum Contact Surface: 5/8 inch (16MM) wide.

• Provide rail sections in minimum 6-foot (1.83M) lengths.

• Rail configuration shall permit attachment to top of structural floor system with provision for leveling rails to compensate for variations in floor surface level.

• Provide rail connections designed to provide horizontal and vertical continuity between rail sections, to gradually transfer the concentrated wheel point load to and from adjoining rail sections. Butt joints without connections are not permitted.

• Anti-Tip Rail Form Covers: Manufacturer shall provide for protection if required to prevent damage to rails during concrete back pours when anti-tip devices are installed.

• Once rails are leveled, they shall be supported the full length with the specified grout.

Floor / Ramp:

• Floor/Ramp Sheathing: Minimum 3/4 inch (19MM), 7-ply underlayment grade plywood. Particleboard sheathing materials are not permitted. Provide low volatile organic compound (VOC)-emitting material for floor/ramp sheathing.

• Provide fire retardant treated floor/ramp materials when required by code.

• Finished flooring materials shall be provided by the Government.

Document Title

• Ramps at entrances to system. Full floor between all rails.

Carriages:

• Provide manufacturer's design movable carriages fabricated of welded steel construction. Galvanized structural components and/or riveted carriages are unacceptable. Must meet 1,000 pounds per foot

(1385kg/M) minimum capacity.

• Provide fixed carriages of same construction and height as the movable carriages, anchored to rails. Setting fixed shelving directly on floors is not permitted.

• When required, provide bolted carriage splices designed to maintain proper unit alignment and weight load distribution.

• Design carriages to allow the shelving uprights to recess and interlock into the carriages a minimum of 3/4 inch (19MM). Top mount carriages are unacceptable.

• Provide each carriage with two wheels per rail.

Drive / Guide System:

• Design: Provide drive system which prevents carriage whipping, binding and excessive wheel/rail wear under normal operation.

• If line shafts are used, all wheels on one side of carriage shall drive.

• If synchronized drives are used, a minimum of one wheel assembly driving both sides of carriage at center location required. Drive shaft shall exhibit no play or looseness over the entire length of that assembly.

• Shafts: Solid steel rod or tube.

• Shaft Connections: Secured couplings.

• Bearing Surfaces: Provide rotating load bearing members with ball or roller bearings. Provide shafts with pillow block or flanged self-aligning type bearings.

Wheels:

• Materials: Type - 1045 solid steel. ASTM A 536 specification 65/45/12 machined ductile iron. Minimum load capacity per wheel: 3200 lbs. (1455kg).

• Size: Minimum 5 inches (127MM); 3 inches (76 MM), outside diameter drive wheels.

• Guides: Determined by manufacturer; minimum 2 locations.

Motors:

Type: 90VDC

Face Panels:

Materials: Plastic laminate clad particleboard with plastic edging on vertical edges. Steel.

Finishes: Selected from manufacturer’s standard available colors and patterns.

End panels must cover the full height and width of shelving.

Shelving: Choose from Cantilever, Four Post, Case-Type, or Wire.

Storage Panels and Cabinets: Choose from Framed Art Storage Panels, File Cabinets, Laboratory Cabinets, Museum

Cabinets, or Weapons Cabinets

Document Title

ACCESSORIES

Touch Technology Control: Provide a touchscreen control head on every carriage that has standard system start/stop/reset controls, Infrared Capable Controls and Infrared Remote Controls, and Touch Technology Aisle

Access Controls as described below. Depending on access rights user can perform the following system controls at each control head: Access aisle left or right of Touchscreen, Toggle stationary locally, Toggle power for the system, Toggle the auxiliary relay output, Tutorials for basic system and safety operation, and administrative functions.

Touch Technology Aisle Access Control: Provide a numeric touchscreen keypad at each carriage. 3–15-digit Pin-code access can be programmed and reprogrammed by the user, as needs dictate.

Touch Technology Aisle Access Control with Pin-code and Card: Provide a numeric touchscreen keypad at each carriage. 3-15-digit Pin-code access. Provide a Card access at one or more carriage location(s). Both Pin and Card access can be programmed and reprogrammed by the user, as needs dictate.

Touch Technology Control Audio: Provide audible, volume controlled, voice prompts and tone activation upon pressing icon controls.

Touch Technology Control Tutorials: Provide audio/visual system use tutorials on touchscreen control head.

Infrared Capable Controls and Infrared Remote Controls: Provide infrared capable control panel at end of each motorized carriage and one or two additional handheld infrared remote control user key(s). In lieu of standard or touchpad controls.

Dual Controls: Provide additional control panel at end of each motorized carriage.

Provide Bluetooth control in replace of or in addition to the standard powered control or touch technology system controls. Option exists to not allow system movement from local controls while connected to the Bluetooth control.

Connection to system will timeout via set time configuration when the apps are no longer in use.

Universal remote control to open and close aisles, enter and search for items, and view safety notifications.

Bluetooth Control: Updates systems software/firmware, configurations, and reports diagnostics wirelessly.

Communicates system status, faults, and last stops real-time. Save and send diagnostic and configuration information file via email. During connection auto-move is disabled.

Programmable Aisle: Provide the ability to create more than one aisle per mobile storage module.

System controls shall start motors on each movable carriage “sequentially” to minimize power demands or “block” to start all at once and shall provide dynamic braking to provide smooth operation. No additional hardware shall be required to change between “sequential” and “block” movement.

Automatic Battery Backup: Provide an integrated uninterruptible power supply for emergency operations in case of primary power failure. Includes the Plug-In-The-Wall Power option.

Power Pack Override: Provide two additional handheld rechargeable battery pack units to operate modules in case of main power failure.

Plug-In-The-Wall Power: Provide a plug-in-the-wall power option, if permitted by local building code. In lieu of permanent power connection.

Automatic Aisle Lighting: Provide top-mounted fluorescent light fixtures.

Stationary aisle lock: Provide key switch to make a movable carriage into a stationary carriage.

Document Title

Automatic Brake: Provide an automatic security brake on each motorized carriage.

Auto Move Interface: Provide the capability for the motorized mobile storage shelving system to move automatically depending upon the Government’s requirements. Select System Auto Cycle, System Priority Aisle, System Closed

Park, and [System Ventilation Park.

Building Management Interface: Provide the capability for the motorized mobile storage shelving system to interface with the building’s fire alarm system or building management system for fire protection, System Fire Park, and security, System Closed Park.

FABRICATION

General: Coordinate fabrication and delivery to ensure no delay in progress of the Work.

Wheels: Provide precision ground and balanced units with permanently shielded and lubricated bearings.

Carriages: Fabricate to ensure no more than 1/4 inch (6MM) maximum deviation from a true straight line. Splice and weld to ensure no permanent set or slippage in any spliced or welded joint when exposed to forces encountered in normal operating circumstances.

Shelving, Supports and Accessories: See individual descriptions in “Shelving” paragraphs.

FINISHES

Colors: Selected from manufacturer’s standard available colors. Provide in custom colors as selected by Architect, Architect/Engineer, Engineer.

Paint Finish: Provide factory applied electrostatic powder coat paint. Meet or exceed specifications of the American

Library Association.

Laminate Finish: Provide factory applied laminate panels at locations indicated on approved shop drawings.

Edgings: Provide preformed edging, color-matched to unit colors selected.

EXECUTION

EXAMINATION

Examine floor surfaces with Installer present for compliance with requirements for installation tolerances and other conditions affecting performance of mobile storage units.

Verify that building structural system is adequate for installing mobile storage units at locations indicated on approved shop drawings.

• In new construction, ensure that recesses for rails in floors are at proper spacing and depths, with allowance for grouting.

• For installations on existing floors, ensure that rail spacings indicated on shop drawings are in proper locations so existing load-bearing structural members are not over stressed.

Verify that intended installation locations of mobile storage units will not interfere with, nor block established required exit paths or similar means of egress once units are installed.

Document Title

Verify that adequate capacity permanent power sources have been installed at locations indicated on approved shop drawings.

Prepare written report, endorsed by Installer, listing conditions detrimental to proper performance of mobile storage units, once installed.

Proceed with installation only after unsatisfactory conditions have been corrected.

INSTALLATION

Rails:

• Lay out rails using full-length units to the maximum extent possible. Use cut lengths only at ends to attain total length required. Locate and position properly, following dimensions indicated on approved shop drawings. Verify thickness of finished floor materials to be installed (by others) and install level 1/16 inch

(1.6MM) above finished floor surfaces.

• Verify level, allowing for a minimum 1/4 inch (6MM) of grout under high points. Position and support rails so that no movement occurs during grouting.

• Set rails in full grout bed, completely filling any voids entire length of all rails including rail connectors. Trim up sides flush with rails to ensure proper load transfer from rail to supporting floor. Using shims in lieu of full grouting is not permitted.

• Installation Tolerances: Do not exceed levelness of installed rails listed below:

• Maximum Variation from True Level Within Any Module: 3/32 inch (2.4MM).

• Maximum Variation Between Adjacent (Parallel) Rails: 1/16 inch (1.6MM), perpendicular to rail direction.

• Maximum Variation in Height: 1/32-inch (.8MM), measured along any 10-foot (3.05M) rail length.

• Verify rail position and level; anchor to structural floor system with anchor type and spacings indicated on approved shop drawings.

Floors/Ramps:

• General: Finished elevation shall be 1/16 inch (1.6MM) below top of rails.

• Place floors and ramps to the extent indicated on approved shop drawings. Extend ramps under all movable and stationary ranges. Do not extend ramps beyond the ends of carriages.

• Construct floors and ramps to prevent warping or deformation of floor panels in a normal operating environment. Support panels on levelers at maximum 16 inches (406MM) on center.

• Ramp Slope: Do not exceed the following:

o ADA Accessible Ramps: Maximum 1:12 slope (4.76 degrees).

o Other Ramps: Maximum 9-degree slope (1.9:12).

o Vertical Transition, Ramp edge to floor: Maximum 1/8 inch (3MM).

Shelving Units Installation:

General: Follow layout and details shown on approved shop drawings and manufacturer's printed installation instructions. Position units level, plumb; at proper location relative to adjoining units and related work.

Document Title

Carriages:

• Place movable carriages on rails. Ensure all wheels track properly, and centering wheels are properly seated on centering rails. Fasten multiple carriage units together to form single movable base where required.

• Position fixed carriage units to align with movable units; make final leveling adjustments with leveling screws.

Shelving Units:

• Permanently fasten shelving units to fixed and movable carriages with vibration-proof fasteners.

• Stabilize shelving units following manufacturer's written instructions. Reinforce shelving units to withstand the stress of movement where required and specified.

Wiring:

• Make final control wiring connections between modules under single control.

• Test wiring for continuity and proper connections with regulated field power supply before making final power connections.

• Make final wiring connections to permanent power source. Connection to power source by others.

• Test system operation by cycling all units through complete operations sequences.

FIELD QUALITY CONTROL

• Verify shelving unit alignment and plumb after installation. Correct if required following manufacturer’s instructions.

• Remove components which are chipped, scratched, or otherwise damaged and which do not match adjoining work. Replace with new, undamaged, matching units.

ADJUSTING

Adjust components and accessories to provide smoothly operating, visually acceptable installation.

CLEANING

Immediately upon completion of mobile shelving installation, clear components, and surfaces. Remove surplus materials, rubbish and debris resulting from mobile shelving installation upon completion of work and leave areas of installation in neat, clean condition.

DEMONSTRATION/TRAINING

Schedule and conduct demonstration of installed equipment and features with Government's personnel.

Schedule and conduct maintenance training with Government's maintenance personnel. Training session should include lecture and demonstration of all maintenance and repair procedures that end user personnel would normally perform.

PROTECTION

Advise Government of additional protection needed to ensure that system will be without damage or deterioration at time of substantial completion.

Document Title

SCHEDULES

Equipment Schedules, See next page.

5. OPTIONAL UPGRADE REQUIREMENTS FOR LEGACY 1991 AND 1997 SYSTEMS

UP GRADING EXISTING ELECTRONIC POWERED MOBILE STORAGE SHELVING SYSTEMS

INSTALLED IN 1991 AND 1997 TO OPERATE USING THE SAME NEWLY OBTAINED SYSTEM AS PART

OF THIS CONTRACT. (ATTACHMENTS 3 AND 4)

Requirements listed here are those specific to upgrades needed to update legacy 1991 and 1997 systems to match the full requirements listed above for the new system being installed.

5.1 SYSTEM DESCRIPTION

Movement Controls: Each of the Powered Carriages will have same type of Touch Pad Control Panels as the System that was installed in 1997 on each of the accessible (open) ends of each moveable carriage, located 44 inches (1118 MM) above the base, centered on the face panel. Minimum controls shall include directional control buttons/icons, STOP/RESET push-button/icon and a red reset light/icon.

System controls shall start motors on each movable carriage “sequentially” to minimize power demands or “block” to start all at once and shall provide dynamic braking to provide smooth operation. No additional hardware shall be required to change between “sequential” and “block” movement. Maximum running speed shall be limited to 3.3 inches (84 mm) per second.

Provide solid state controls and indicator lights/icons for a visual indication of safety system operation. Provide each aisle with a programmable distance sensor to ensure proper timing for start/stop operation.

Pushing the directional control button/icon on any moveable carriage adjacent to the desired aisle location in the direction away from the desired aisle location opens the system at the desired aisle. The selected aisle shall open automatically regardless of the position of the carriages.

• Manual Reset: The carriage control head will display a flashing red reset light/icon at the newly opened aisle indicating that the aisle is locked open and requires resetting before another aisle can be opened. Provide for automatic lockout and manual reset of controls if selected aisle is not moved within a preset period of time.

• (Optional) Automatic Reset: The carriage control heads will display a constant green light, or green arrow icon, at all carriages indicating that the system is ready for the next aisle access. Provide for automatic reset if system is equipped with optional Sensor system safety feature, or other redundant safeties.

Controls shall feature safety activated message and direction indicator designating which aisle safety was activated or back lit message indicating which aisle is in use (i.e., “Right Aisle in use” or “Left Aisle in use”).

Provide Bluetooth control in replace of or in addition to the standard powered control or touch technology system controls.

(Optional) Infrared Capable Controls and Infrared Remote-Control Keys: Provide infrared capable control panel at end of each motorized carriage and two additional handheld infrared remote control user key(s). In lieu of standard control moveable on carriage.

5.2 SUBMITTALS

SHOP DRAWINGS: SHOW FABRICATION, ASSEMBLY, AND INSTALLATION DETAILS INCLUDING

DESCRIPTIONS OF PROCEDURES AND DIAGRAMS. SHOW COMPLETE EXTENT OF INSTALLATION

LAYOUT INCLUDING CLEARANCES, SPACINGS, AND RELATION TO ADJACENT CONSTRUCTION IN

Document Title

PLAN, ELEVATION, AND SECTIONS. INDICATE CLEAR EXIT AND ACCESS AISLE WIDTHS; ACCESS TO

CONCEALED COMPONENTS; ASSEMBLIES, CONNECTIONS, ATTACHMENTS, REINFORCEMENT, AND

ANCHORAGE; AND DECK DETAILS, EDGE CONDITIONS, AND EXTENT OF FINISH FLOORING WITHIN

AREA WHERE UNITS ARE TO BE INSTALLED.

• Show installation details at non-standard conditions. Furnish floor layouts, technical and installation manuals for every unit shipment with necessary dimensions for rail layout and system configuration at the project site.

Include installed weight, load criteria, furnished specialties, and accessories.

• Provide layout, dimensions, and identification of each unit corresponding to sequence of installation and erection procedures. Specifically include the following:

a) Location, position, and configuration of tracks on all floors.

b) Plan layouts of positions of carriages, including all required clearances.

c) Details of shelving, indicating method and configuration of installation in carriages.

5.3 MANUFACTURED COMPONENTS

Automatic Battery Backup: Provide an integrated uninterruptible power supply for emergency operations in case of primary power failure. Includes the Plug-In-The-Wall Power option.

Power Pack Override: Provide two additional handheld rechargeable battery pack units to operate modules in case of main power failure.

Plug-In-The-Wall Power: Provide a plug-in-the-wall power option, if permitted by local building code. In lieu of permanent power connection.

Shelving Units Installation:

Wiring:

• Make final control wiring connections between modules under single control.

• Test wiring for continuity and proper connections with regulated field power supply before making final power connections.

• Make final wiring connections to permanent power source. Connection to power source by others.

• Test system operation by cycling all units through complete operations sequences.

(End Statement of Work)

(END OF SECTION C)

Document Title

SECTION D – PACKAGING AND MARKING

D.1 GS0501 Packaging and Marking - Commercial Practice July 2001

(a) Preservation, packaging, and marking for all items delivered hereunder shall be in accordance with standard commercial practice and adequate to insure acceptance by common carrier and safe arrival at destination.

(b) All containers shall be plainly marked on or adjacent to the exterior shipping label to show the contract number, task order number, description of contents, and contractor's name.

D.2 Delivery Addresses for Deliverables

The delivery address of any deliverables specified under this contract will be to:

U.S. Geological Survey

D.3 Product Delivery - Storage-Handling

The Contractor shall arrange for deliveries of all materials to be delivered directly to the point of installation.

The Contractor shall be responsible for receiving deliveries on site at USGS and shall reconcile bills of lading for deliveries of contractor-furnished materials for the contracted project. Government personnel will not be responsible for reconciling bills of lading for contractor-furnished materials delivered to the USGS for a Contractor. The Contractor shall furnish a Contractor point-of-contact to vendors for receipt of material deliveries. The Contractor shall not provide the names of Government personnel to vendors as the point-of-contact for deliveries. The Contractor shall be responsible for scheduling and tracking the deliveries of all contractor-furnished materials for the project.

(END OF SECTION D)

Document Title

SECTION E -- INSPECTION AND ACCEPTANCE

E.1 52.252-02 CLAUSES INCORPORATED BY REFERENCE

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:

FAR | Acquisition.GOV

Clause Title Date

52.246-16 Responsibility for Supplies April 1984

E.2 GS0715 PLACE OF INSPECTION JULY 2001

Government inspection of delivered items will be performed at destination by the COR or a Government authorized inspector.

E.3 FINAL INSPECTION AND ACCEPTANCE

Upon completion of the contracted work, the Contractor shall notify the COR. The COR will schedule an inspection of the work site and will perform the inspection at the site to determine if all work performed by the Contractor meets the requirements of the Statement of Work, Specifications and Drawings. The Contractor shall be present at the site during final inspection by the COR. The Date of Acceptance of the work by the Government will be determined by the

Government after the final inspection has been performed.

E.4 GENERAL ACCEPTANCE CRITERIA

• General quality measures, as set forth below, will be applied to each work product received from the contractor under this Contract.

• Accuracy - Work shall be accurate in presentation, technical content, and adhere to accepted elements of style.

• Clarity - Work shall be clear and concise all diagrams shall be organized and relevant to the supporting narrative(s).

• Consistency to Requirements - All work shall satisfy the requirements of this contract.

• File Editing - All text and diagrammatic files shall be editable by the Government.

• Format - Work shall be submitted in hard copy (where applicable) and in media mutually agreed upon prior to submission, unless otherwise specified herein. Hard copy formats shall follow any specified Directives or Manuals.

• Timeliness - Work shall be submitted on or before the due date specified herein or submitted in accordance with a later scheduled date determined by the Government.

(END OF SECTION E)

https://www.acquisition.gov/browse/index/far

Document Title

SECTION F -- DELIVERIES OR PERFORMANCE

F.1 52.252-02 CLAUSES INCORPORATED BY REFERENCE

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be

52.242-15 Stop-Work Order August 1989

F.2 GS0905 PLACE OF PERFORMANCE JULY 2001

Services to be provided hereunder shall be performed at the following location(s):

US Geological Survey

F.3 GS0911 PERIOD OF PERFORMANCE JULY 2001

Delivery of system is expected 90 days from date of award for the new system with an additional 90 days to upgrade legacy systems originally installed in 1991 and 1997 if options 1 and 2 are implemented. Separate requirements are included in Section 5 for options to upgrade legacy systems out of warranty and at end of life.

F.4 GS0916 PERIOD FOR EXERCISE OF OPTION TO EXTEND

SERVICES

JULY 2001

For the purposes described in FAR 37.111, the Government may exercise the option to extend the contract under the clause 52.217-8, Option to Extend Services, by written notice issued to the Contractor prior to the expiration of the initial contract period or any option period, including any previous extensions under this clause. When such date falls on the last day of a fiscal year, notification must be provided within 7 days after funds are appropriated and available for the new fiscal year.

F.5 GS0919 LEGAL HOLIDAYS JANUARY 2002

The following legal holidays are observed by this Government agency:

New Year’s Day January 01

Martin Luther King’s Birthday 3rd Monday in January

Presidents Day 3rd Monday in February

Memorial Day Last Monday in May

Juneteenth June 19

Document Title

Independence Day July 04

Labor Day 1st Monday in September

Columbus Day 2nd Monday in October

Veterans Day November 11

Thanksgiving Day 4th Thursday in November

Christmas Eve December 24

Christmas Day December 25

When a holiday falls on Saturday or Sunday, it is observed on the adjacent Friday or Monday, respectively.

In addition to the holidays listed above, the contractor agrees to observe leave days or closures designated by Federal

Statute, Executive Order, or Presidential Proclamation.

F.6 GS0924 Unscheduled Closures July 2001

(a) The USGS facility where contractor employees are working may occasionally have unscheduled closures in which federal employees are dismissed on administrative leave (such as for inclement weather, holiday early closings, power outages, or other emergencies). In these cases, the Contracting Officer or COR will advise the contractor whether any of the contractor's activities are considered critical and require continued performance. In most cases, the Contractor employees not performing critical tasks will not be allowed to remain in the facility after federal employees are dismissed.

(b) If the contractor opts to treat these nonproductive hours as paid leave, these hours are billable at the established contract rates. The total number of hours billed on such days may not exceed the number scheduled for affected employees and may not include overtime hours.

(c) Paragraph (b) does not apply, and nonproductive hours are not billable as direct hours worked where the contractor's accounting system normally treats leave of the type used as an indirect or fringe benefit pool expense.

F.7 GS0925 Unscheduled Closures - Fixed Price March 2003

(a) The USGS facility where contractor employees are working may occasionally be closed temporarily and federal employees dismissed, such as for inclement weather, holiday early closings, power outages, or other emergencies. In these cases, the Contracting Officer or COR will advise the contractor whether any of the contractor's activities on

Government facilities are considered critical and require continued performance. In most cases, the Contractor will be required to dismiss employees at Government facilities who are performing noncritical tasks after federal employees are dismissed.

(b) If the unscheduled closure causes an increase in the cost of contract performance or if any contract term or condition is affected by the closure, the Contractor may request an adjustment pursuant to Clause FAR 52.242-17 Government Delay of Work.

(c) Contractor performance at locations that are not affected by the unscheduled closure will not be subject to this clause.

(END OF SECTION F)

Document Title

SECTION G -- CONTRACT ADMINISTRATION DATA

G.1 GS1101 CONTRACT ADMINISTRATION OFFICE JULY 2001

(a) This contract will be administered by:

United States Geological Survey

Nicole Demby, Contracting Officer ndemby@usgs.gov

Reston VA 20192

(b) Written communications to the Administrative Contracting Officer shall make reference to the contract number and shall be emailed to the above address.

G…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .