This document contains questions and answers related to a solicitation for cooling tower repairs and upgrades at the United States Geological Survey facility in Sioux Falls, South Dakota. The solicitation seeks proposals for installing a fourth variable frequency drive and relocating existing VFDs to allow the cooling towers to operate fans at 10% speed or lower. Questions covered the roof warranty, approval of specified equipment manufacturers, the opportunity for a site visit, availability of documents, and an extension to the proposal due date. The response date was extended to April 14, 2023 at 2:00PM Eastern Time in order to allow suppliers additional time to provide quotes and lead times.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EROS Construction: Cooling Towers
RFP# 140G0123R0007
Questions and Answers
1. Could you provide information on the roof warranty and contractor that services the warranty?
Answer: The roof was installed in the Summer of 2010 and is a Sika Sarnafil product. It has a 20-year warranty per our contract. I cannot find solid information, but ARS of Sioux Falls, SD is likely the installation contractor.
2. I would like to formally request approval for the following manufacturers on the EROS
Construction Services in Sioux Falls, SD with project # 1936.00.
Spec. Section or
Drawing
Reference
Equipment Description Approval Requested For:
230700 HVAC Water Pumps Grundfos
230110 Pump Suction Diffusers Grundfos, American Wheatley
230110 Strainers Grundfos, American Wheatley
230110 Automatic Air Vent Grundfos, American Wheatley
230110 Circuit Setter/Balancing Valve Hays, HCi
230110 Auto Flow Control Valves Hays, Hci
230110 Ball Valves Hays, Hci
230110 Butterfly Valves, Swing Check
Valves, and Spring Check Valves Hays, Hci
230110 Triple Duty Valves Grundfos, American Wheatley
230110 Relief Valves Grundfos, American Wheatley
230110 Flexible Connectors Hays, HCi
Answer: The Government does not answer this question. It is up to the contractors to find the parts that meet the needs of the Government based on the Statement of
Work. The contractors can choose any manufacturer they would like for bidding purposes. Once the contract is awarded, the awardee with provide Submittals to the
Contracting Officer Representative (COR) for approval.
3. Is there a pre-bid site visit scheduled for this project?
Answer: The Site Visit was conducted on March 23, 2023, at 10:00AM Central
Time. There will not be another site visit.
4. Is there a product that was used as the basis of design?
Answer: No
5. The documents provided in the solicitation and their content are the only documents for this solicitation, correct?
Answer: Yes, all of the documents were provided.
6. Can the due date be extended until 14 April to allow suppliers time to provide quotes and lead times to us?
Answer: The RFP will be extended to April 14, 2023 at 2:00PM Eastern Time
7. Where should the fourth VFD be located?
Answer: The fourth VFD and existing VFDs need to be located and relocated close enough to the cooling towers to operate the cooling fans to operate at 10% speed or lower. The current location does not allow for the current cooling fans to be operated below 25%.