Sol_140FS326Q0120_Amd_0002.pdf
PDF 238 KB Posted
- Attached to
- FL-J N DING DARLING NWR-DEBRIS REMOVAL
- Solicitation number
- 140FS326Q0120
- Issued by
- Not on record
About this file
This document is Amendment P00002 to solicitation 140FS326Q0120, issued by the Fish and Wildlife Service (FWS) on October 22, 2026, providing answers and clarifications to contractor questions regarding a debris removal project at J.N. Ding Darling National Wildlife Refuge.
The project requires removal of construction debris from approximately four acres at the refuge, with an estimated volume of 90-100 cubic yards. Contractors may use either dump trailers or roll-off dumpsters for collection and hauling, with only one container permitted on-site at a time due to space constraints near a public bike path and municipal water well. Non-motorized equipment such as wheelbarrows and sleds are acceptable for debris transport, and plywood or mats may be used to prevent soil compaction on soft ground. Hand-held powered tools including battery-operated and gas-powered chainsaws, circular saws, and power cutters are authorized for cutting and bucking operations. No live trees shall be removed; only stumps in access paths or blocking debris removal may be cut flush with ground surface. The staging area is located on the refuge with debris disposed of properly on-site. Contractors must conduct a reasonable visual search for debris but are not required to perform dewatering, pumping, or diving operations. Final inspection will occur within 30 days of contractor notification of completion. The solicitation is set aside for small businesses under NAICS Code 238910 (Site Preparation Contractors) with a $19 million threshold. The quote submission deadline has been extended to November 20, 2026, at 3:00 p.m. EST, with a performance period from November 27, 2026, to January 31, 2027. Site visits are scheduled for November 9 and 13, 2026, at 11:00 a.m., and all correspondence should be directed to Contracting Officer Merenica Banks at Merenica_Banks@ios.doi.gov. The Service Contract Act Wage Determination 2015-4529 applies to the award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Merenica Banks
See continuation page
FWS, SAT Team 3 5275 Leesburg Pike Falls Church VA 22041
FSE
140FS326Q0120
10/22/2026
10/22/2026
1 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140FS326Q0120/0002
Amendment P00002 - FL-J N DING DARLING
NWR-DEBRIS REMOVAL PPR2116353_LR4 - Answers and
Clarifications Part 2
1. The purpose of this modification is to provide answers and clarifications.
2. Question: Would the government permit contractors to utilize dump trailers (dumpsters on wheels) instead of traditional roll-off dumpsters for debris collection, hauling, and disposal?
2a. Answer: yes, either Dump Trailers or Roll off dumpster is acceptable
3. Question: Given the soft and wet ground conditions, would the government permit contractors to lay plywood along an approved access route to distribute the weight of dump trailers and prevent rutting or damage to the surrounding ground?
3a. Answer: yes, plywood or mats would be acceptable to prevent soil compaction and trip hazards
4. Question: What are Allowable
Manual/Mechanized Hauling Equipment: Could the
Government clarify whether non-motorized, low-ground-pressure transport aids¿such as heavy-duty wheeled hand carts, dual-wheel wheelbarrows, or motorized walk-behind tracked wheelbarrows (power barrows) equipped with turf/rubber tracks that maintain ground depression under the 4-inch limit.
4a. Amended Answer: AMENDED: non-motorized equipment, such as wheel barrows, sled etc..
are acceptable. no motorized wheeled or tracted equipment is authorized.
5. Question: Staging Footprint, Access
Constraints, and Container Placement at the
Gavin Site:
5a. Answer: Roll off dumpster or dump trailers are acceptable at the job site. The space is
Continued...
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) limited by the city of sanibel bike path which must remain open and a municple water well and other vegitation. 1 dump trailer or roll off dumpster is all the site can handle at 1 time.
The gavin site can be used if you need a staging area, additional parking etc.
6. Question: Is the disposal staging site on the refuge, or must the contractor haul debris off-site to a permitted facility?
6a. Answer: Yes the staging area is on the refuge and all materials should be disposed of properly.
7. Question: Please reconcile the site instruction that the debris must be removed by hand carrying without machinery or transport equipment with Amendment 0001, Question 7, which allows non-motorized wheelbarrows and sleds.
7a. Answer: non-motorized equipment, such as wheel barrows, sled etc are acceptable, no motorized equipment.
8. Question: Please distinguish prohibited machinery from portable hand-held cutting tools. For the cutting and bucking required by
PWS §3.3, may workers use battery-operated reciprocating or circular saws, chainsaws, and similar portable powered cutters, or must all cutting be performed with non-powered hand tools?
8a. Answer: Hand Tools such as battery powered
Circular saws, battery or gas powered chainsaws, power cutters, or similar cutting tools are allowed.
9. Question: "Please provide or field-mark the limits of the approximately four-acre removal area shown in Figure 1 and identify whether adjoining ditches, ditch bottoms, spoil mounds, access corridors, or debris outside the mapped boundary are included."
9a. Answer: On Construction Debris within the
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) boundary is to be removed. See the attached
KMZ (Google earth) file for the site boundary.
10 Question: Please clarify whether that estimate is loose or in-place volume and whether it includes submerged, partially buried, and root-entangled debris.
10a. Answer: 90 - 100 Cubic yards is a loose estimate for the amount of debris that would fill up 3 - 30 yard roll off dumpsters.
11. Question: Please define the required search and removal limits for material below the water surface or embedded in sediment. Does the base scope require probing for concealed debris, excavating buried material, removing debris from ditch bottoms, or performing any dewatering, pumping, underwater work, or diving? Please identify the applicable depth limits and the disposition process for debris that cannot be recovered by safe manual methods without disturbing protected soils or roots.
11a. Answer: remove any debris visible following a reasonable search of the site.
There will be no need to dewater or pump water or dive in the water.
12. Question: Please provide any available information on water depths, tidal influence, drainage fluctuations, and channels or holes within the required work area and access route.
Please identify any Government imposed wading, water-level, weather, or access restrictions and the process for authorizing work to resume in areas that are temporarily unsafe or inaccessible. This information will be the contractor's own safety and production plan.
incorporated into.
12a. Answer: The water visible at the time of the site visit is the deepest the water is during normal weather conditions. In the event of a storm surge or heavy rainfall that floods the Island, the government may ask the contractor to delay work as the waters recede back to where they are currently. There is no
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) information on the drainage or holes or channels beyond what can be seen on Google earth.
13. Question: "Please identify how an area will be documented as cleared and how newly deposited debris after a documented clearance will be distinguished from incomplete.
13a. Answer: This will be a visual inspection by refuge staff.
14. Question: "states that no mangrove clearing, dredging, or fill is proposed, while
PWS §4.7
discusses cutting vegetation under an approved operating plan. Please identify the precise vegetation and root-disturbance restrictions applicable to debris extraction and access."
original work."
14a. Answer: No live trees shall be removed.
Stumps that are in the access path or trees in the path of the removal can be cut flush with the ground surface.
15. Question: Please identify the approved hand-carry routes and crossing points from the debris field to the loading location. Amendment
0001 allows plywood or mats; please confirm whether hand-carried access mats, wallboards, or temporary pedestrian bridges may be used over soft ground or ditches, and state any footprint, anchorage, removal, environmental-review, or approval requirements.
No dredging, fill, or unauthorized vegetation clearing is proposed.
15a Answer: This was discussed in the site visit. The same point of access is what is authorized in this scope of work. Correct no dredge or fill of wetlands and no unauthorized veg. clearing is allowed.
16. Question: We understand that only one dump trailer or roll-off container may be at the job site at a time and that the public trail must remain open. Please identify the exact authorized container/loading footprint, NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) available dimensions, maximum container size, delivery and exchange access, and required pedestrian/bicycle protection.
16a. Answer: To be determined by the contractor.
17 Question: If suspect asbestos-containing material, lead-contaminated debris, containers, fuel, or other hazardous waste is encountered, please identify the notification and stop-work procedure and responsibility for testing, characterization, special handling, and disposal.
17a Answer: no suspected hazardous materials are known. If any is encountered, notification to the CO should be made immediately and those materials shall remain in place, until they can be tested. Testing will be the responsibility of the government. If it tests positive for hazardous asbestos or lead paint, the contractor will not be held responsible for removal of those items. If they test negative for hazrdous materials, the contractor will be held responsible for its removal.
18 Question: Identify any project-specific requirements for waste segregation, recycling, profiling/testing, designated disposal facilities, load measurement, weight tickets, manifests, or final disposal documentation beyond the generally applicable disposal requirements.
18a Answer: There are no requirements other than a final cubic yard amount disposed of.
19. Question: Please identify any site-specific visitor, wildlife, noise, utility-access, or seasonal work restrictions in addition to the stated 7:00 a.m.¿5:00 p.m. weekday window.
19a. Answer: Work should be done at daylight hours during the week. Approval to Work on weekends and holidays must be arranged 1 week in advanced.
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
20. Question: Support facilities decontamination and emergency access?
20a. Answer: There are no utilities on site.
Contractor is responsible for sanitation, port-a-potty restrooms etc.
21. Question: Final inspection acceptance and invoicing Please reconcile the final inspection timing in PWS §10.5 (30 days following treatments) and §11.5.1 (45 days or less, weather dependent), and replace vegetation/treatment terminology with the intended debris-removal requirements. Please confirm when inspection will occur after written notice of completion, whether individual cleared areas may be accepted progressively, and whether inspection must occur within the contract completion period.
21. Answer: Upon contractor notifying the CO of completion, the refuge manager and staff will schedule an inspection of debris removal site with in 30 days. Vegetation treatments terminology was intended to be debris removal.
22. Question: Please confirm the wage determination revision and service-contract labor provisions that will govern the award, including applicable paid-sick-leave coverage.
22. Answer: Attachment 4 - Service Contract Act
WD 2015-4529
23. Question: Please confirm the intended set-aside.
23a. Answer: Set aside is for small businesses under NAICS Code, 238910 Site Preparation
Contractors $19 Mil.
24. Will this solicitation be extended?
24 Answer: The quote due date is extended to
November 20, 2026 at 3pm EST.
25. Site visit contact is Kevin Godsea, NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
239-272-9829, contact him for any site visit times make sure your attendance is noted.
26. All other terms and conditions remain the same.
Quote Due Date: November 20, 2026 @ 3pm EST.
Site Visit Contacts: Tech POC: Kevin Godsea
(239) 472-1100
Site Visit Dates: Nov 9th at 11AM and Nov 13 at
11AM
Send all questions and correspondence to:
Contracting POC: Merenica Banks, (Contracting
Officer) Merenica_Banks@ios.doi.gov
Quote Submittal Email: Subject Line- Sol No.
140FS326Q0120 Quote Submittal
Question Email: Subject Line: Sol No.
140FS326Q0120 Questions
Period of Performance: 11/27/2026 to
01/31/2027
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .