This document is Amendment P00001 to Solicitation 140FS326Q0120, issued by the Fish and Wildlife Service (FWS), SAT Team 3 on October 22, 2026, providing answers and clarifications to contractor questions regarding debris removal services at J.N. Darling National Wildlife Refuge.
The project requires debris removal and disposal of an estimated 90-100 cubic yards of construction materials from the refuge. Contractors may utilize either dump trailers or roll-off dumpsters for collection and hauling. Plywood or mats are acceptable to prevent soil compaction and trip hazards on soft, wet ground. Non-motorized equipment such as wheelbarrows and sleds are acceptable, as are small walk-behind motorized wheelbarrows under 600 pounds (dry weight) rated for low ground pressure. The site can accommodate only one dump trailer or roll-off dumpster at a time, with space constraints imposed by the City of Sanibel bike path, a municipal water well, and vegetation; the Gavin site may be used for staging and additional parking. Permits are not required as work occurs entirely on federal lands with no mangrove clearing, dredging, or fill proposed. The staging and disposal area is on the refuge, with all materials to be disposed of properly on-site. Site visits are scheduled for November 9 and November 13, 2026, at 11:00 AM; the technical point of contact is Kevin Godsea at (239) 472-1100. Quote submissions are due November 16, 2026, at 3:00 PM EST via email to Contracting Officer Merenica Banks at Merenica_Banks@ios.doi.gov with subject line "Sol No. 140FS326Q0120 Quote Submittal." The period of performance is November 17, 2026, through January 31, 2027. The previous contract award (140FS325P0141) to BAS Enterprises was valued at $18,000.00.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Merenica Banks
See continuation page
FWS, SAT Team 3 5275 Leesburg Pike Falls Church VA 22041
FSE
140FS326Q0120
10/22/2026
10/22/2026
1 5
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140FS326Q0120/0001
Amendment P00001 - FL-J N DING DARLING
NWR-DEBRIS REMOVAL PPR2116353_LR4 - Answers and
Clarifications
1. The purpose of this modification is to provide answers and clarifications.
2. Question: Would the government permit contractors to utilize dump trailers (dumpsters on wheels) instead of traditional roll-off dumpsters for debris collection, hauling, and disposal?
2a. Yes, either Dump Trailers or Roll off dumpster is acceptable
3. Question: Given the soft and wet ground conditions, would the government permit contractors to lay plywood along an approved access route to distribute the weight of dump trailers and prevent rutting or damage to the surrounding ground?
3a. Answer: Yes, plywood or mats would be acceptable to prevent soil compaction and trip hazards.
4.Question: Does the government have any additional photographs or videos showing the existing hurricane debris, ground conditions, and surrounding work area that could be provided to prospective contractors?
4a. Answer: Yes, we have additional photos, but a site visit is still necessary to truly evaluate the project.
5. Question: We contacted the designated site contact, Scott Norwood, at 239-446-6144;
however, the telephone number provided does not appear to be working.
5a. Answer: Scott No longer works for the refuge. contact Kevin Godsea at
239-272-9829
6. Question: Estimated Debris Quantity and
Composition Baseline:
6a. Answer: Government estimates 90- 100 Cubic yards of construction material, the site visit is necessary for bidders to take their own estimates.
Continued...
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
7. Question: Allowable Manual/Mechanized
Hauling Equipment: Could the Government clarify whether non-motorized, low-ground-pressure transport aids¿such as heavy-duty wheeled hand carts, dual-wheel wheelbarrows, or motorized walk-behind tracked wheelbarrows (power barrows) equipped with turf/rubber tracks that maintain ground depression under the 4-inch limit.
7a. Answer: non-motorized equipment, such as wheel barrows, sled etc are acceptable, small walk behind motorized wheel barrows less than
600 lbs (dry weight) that are rated as ground pressure is also acceptable.
8. Question: Staging Footprint, Access
Constraints, and Container Placement at the
Gavin Site:
8a. Answer: Roll off dumpster or dump trailers are acceptable at the job site. The space is limited by the city of Sanibel bike path which must remain open and a municipal water well and other vegetation. 1 dump trailer or roll off dumpster is all the site can handle at 1 time.
The gavin site can be used if you need a staging area, additional parking etc.
9. Question: Permits and Local Agency
Clearances:
9a. Answer: Permits are not required on this project as they are entirely on federal lands and no mangrove clearing, dredge or fill is being proposed on this project.
10. Question: Is there an estimated volume or tonnage of debris for each work area shown?
10a. Answer: The government estimates 90-100
Cubic yards of construction materials.
11. Question: Since heavy equipment can't be used in the mangrove areas, may small boats or hand-carry methods be used to move debris to the disposal staging site.
11a. Answer: A boat would not be appropriate.
This question is best answered by the contract at the site visit.
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
12. Question: Is the disposal staging site on the refuge, or must the contractor haul debris off-site to a permitted facility?
12a. Answer: Yes, the staging area is on the refuge and all materials should be disposed of properly.
Question Due Date: October 28, 2026 @ 3pm EST.
13. Question: There are conflicting bid due dates, which date is correct?
13a. Answer: The correct bid due date is
November 16, 2026 @ 3pm EST.
14. Question: Who do we turn our bid information in to?
14a. Answer: All bids/Quotes should be turned in via email to: Merenica Banks, (Contracting
Officer) Merenica_Banks@ios.doi.gov
15. Question: Was there an incumbent for this service? If so please share the award information.
15a. Answer: Yes, Contract No. 140FS325P0141 -
BAS Enterprises was awarded for $18,000.00.
16. All other terms and conditions remain the same.
Quote Due Date: November 16, 2026 @ 3pm EST.
Site Visit Contacts: Tech POC: Kevin Godsea
(239) 472-1100 Alt POC: Scott Norwood (239)
446-6144
Site Visit Dates: Nov 9th at 11AM and Nov 13 at
11AM
Send all questions and correspondence to:
Contracting POC: Merenica Banks, (Contracting
Officer) Merenica_Banks@ios.doi.gov
Quote Submittal Email: Subject Line- Sol No.
140FS326Q0120 Quote Submittal
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Question Email: Subject Line: Sol No.
140FS326Q0120 Questions
Period of Performance: 11/17/2026 to
01/31/2027
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .