Text version

(x)

140FS323Q0055

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

FS3

Falls Church VA 22041 5275 Leesburg Pike FWS, SAT Team 3 FWS, SAT Team 3

FS3

Falls Church VA 22041 5275 Leesburg Pike FWS SAT Team 3 FWS SAT Team 3

03/20/20230001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

03/20/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of the Amendment is to extend the closing period and the Period of Performance.

As a result, the closing date is extended to April 17, 2023.

ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME

Period of Performance: 05/01/2023 to 04/30/2024

Change Item 00010 to read as follows(amount shown is the obligated amount):

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Tonia Ellen

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 6

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140FS323Q0055/0001

00010 Timber Cruise & Report

UNITED STATES FISH AND WILDLIFE SERVICE

REGION 5

James River National Wildlife Refuge

STATEMENT OF WORK

Timber Inventory

1.0 General. Timber Inventory

1.1 Introduction. Project needs include a timber

cruise of pine dominated forests tracts at the

James River National Wildlife Refuge. The information gathered will guide future thinning operations and habitat management decisions.

1.2 Background. James River National Wildlife

Refuge is 4,700 acres of varied habitat types:

pine-dominated forest, floodplain forest, and moist hardwood forest. A portion of the land which is now the wildlife refuge was managed as a loblolly pine plantation prior to acquisition by the USFWS. Those remnant forests remain in even-aged, over-stocked stands. In the early

2000¿s, several hundred acres were commercial thinned and prescribed fire was introduced to the site. The 2015 Comprehensive Conservation Plan identified more habitat manipulation to expand to slightly over 2,000 acres for the purposes of transitioning to a pine savanna ecosystem. An initial forest inventory occurred in 2006.

Additional, updated information of the forest diversity, density, and other stand dynamics is required to facilitate decision-making in advance of the large habitat conversion project. The timber inventory will assess and professionally estimate stand parameters.

1.3 Objectives. Upon completion of the timber

cruise a report will be provided to the staff at

James River National Wildlife Refuge that clearly outlines forest details, determined by stand variability and size. The 2,300-acres of pine dominated forest will be surveyed and inventoried to aid subsequent description of thinning needs and priorities.

1.4 Scope. A timber inventory is to be conducted

on 2,300-acres of largely pine-dominated forests at James River National Wildlife Refuge (see

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

3 6

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140FS323Q0055/0001

map). The contiguous tract will be subdivided by stand size and variability. Stand parameters will be evaluated for each tract. Parameters are to include basal area (BA) per acre, trees per acre (TPA), average diameter at breast height

(DBH), volume per acre for pine pulpwood, hardwood pulpwood, pine chip and saw, mixed hardwood saw timber, and snags. Cumulative totals are to be tabulated per category. Separate inventories are to be provided for pine and hardwood. Each tract will be inventoried to determine size of each DBH class by BA and TPA.

Once data is calculated, thinning recommendations are to be outlined for each tract. The report is to present data in tabular format for each stand.

Report will be completed by (date to be determined).

1.5 Contract Type. Preference for type of

contract (Firm Fixed Price).

1.6 Place of Performance/Hours of Operation. All

on-site work will be conducted at the James River

National Wildlife Refuge, located in Prince

George County, Virginia. Site is accessible from

Route 639 (Flowerdew Hundred Road) and Route 640

(Powell Creek Road). The property¿s dirt and gravel access roads are gated and arrangements will be made for entry through coordination with the FWS¿s on-site point of contact (Cyrus Brame, or other USFWS- identified agent). Work is to occur during daylight hours once an official start date has been determined. Certain areas will be prohibited from entry during limited times of the year due to public hunting programs or other conflicting refuge sponsored activities/operations.

1.7 Period of Performance. This project has a

strict period of performance as the data obtained from this contract will define subsequent thinning activities, scheduled for later in the year. The duration of the task will begin on the date of the award.

1.8 Privacy Act. Work on this project may require

that personnel have access to Privacy

Information. Personnel shall adhere to the

Privacy Act, Title 5 of the U.S. Code, Section

552a and applicable agency rules and regulations.

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

4 6

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140FS323Q0055/0001

1.9 Personal Service. The client has determined

that this order is not being used to procure personal services prohibited by the Federal

Acquisition Regulation (FAR) Part 37.104 titled

¿Personal services contract¿.

1.10 Security. The requirement(s) under this

order are unclassified and there are no requirements for security certification on the part of the contractor.

1.11 Key Personnel.

1.11.1 Contract Officer Representative (COR), Contract Officer (CO)

1.11.2 The contractor shall identify key

personnel in the proposal regardless of the type of task. NOTE: Key personnel may not be removed from the task without express approval of the

COR. The CO will attach a copy of the request and determination to the project files.

1.12 Quality Control. The contractor will be

provided regulated vehicle access to enter the site¿s vast network of wildlife refuge roads.

All other access is to occur by foot, no UTVs or other mechanical conveyance is allowed off roads.

1.13 Records/Data. A report with tabulated data

and narrative brief is to be provided as indicated in section Scope 1.4.

1.14 Packaging/Packing/Shipping Instructions. All

mailing are to be sent to the Eastern VA Rivers

NWR Complex Sub-office, to the attention of Cyrus

Brame, located at 11116 Kimages Road, Charles

City, VA 23030.

1.15 Applicable Documents. Sample timber cruise

report document can be provided upon request.

1.16 Points of Contact. COR- Identified after

Award

2.0 Definitions & Acronyms.

USFWS- United States Fish and Wildlife Service

JRNWR- James River National Wildlife Refuge

3.0 Government Furnished Items.

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

5 6

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140FS323Q0055/0001

JRNWR staff will provide Initial familiarization

/ orientation of the project area though a scheduled site visit. During the visit, staff will tour the selected contractor through the property, address logistical concerns, and describe access procedures.

4.0 Contractor Furnished Items. The contractor

will provide all labor, tools, and materials necessary to complete the requirements of the contract.

5.0 Specific Requirements.

5.1 Task Description. Complete comprehensive

timber cruise report for the JRNWR as outlined in

Section 1.4 Scope.

5.2 Proposal Submission. To receive award the

potential offerors shall register their organization in the System for Award Management

(SAM) at SAM.gov

5.2.1 Travel. Any travel costs must be

incorporated in the price.

5.2.2 (Un-priced CLINS)

5.3 Deliverables and Reports. In addition to the

applicable requirements, the contractor shall provide the following deliverables and reports:

5.3.1 Status Reports. Status reports must be

submitted weekly to the COR.

5.3.2 Failure to provide reports correctly will

cause resubmission by your company.

5.3.3 Other Reporting Requirements. In addition

to the weekly status reports, the contractor shall provide the final timber cruise report outlined in Section 1.4 Scope.

5.3.3.1 The contractor shall inform the COR in

writing of the actual task starting date on or before the starting date. If the actual task starting date will require the contractor to be physically on the James River National Wildlife

Refuge that day, the USFWS contact must be informed no less than five business days in advance.

5.3.3.2 The contractor shall bring problems or

potential problems affecting performance to the attention of the COR as soon as possible. Verbal reports will be followed up with written reports when directed by the COR.

5.3.3.3

5.3.3.4

5.3.4 Delivery Instructions. All deliverables

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

6 6

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140FS323Q0055/0001

shall be delivered to the client no later than the date specified in the SOW. Deliverables are to be transmitted with a cover letter, on the prime contractor¿s letterhead, describing the contents.

5.4 Inspection and Acceptance. In the absence of

other agreements negotiated with respect to time provided for government review, deliverables will be inspected and the contractor notified of the

COR findings within 5 work days of normally scheduled review.

5.5 Procedures for Payment. Billing and payment

shall be accomplished in accordance with the contract. The contractor shall have the invoice certified by the COR. The Contractor must use the

IPP website to register access and use IPP for submitting requests for payment. The Contractor

Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis

(FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP

Production Helpdesk via email

IPPCustomerSupport@fiscal.treasury.gov or phone

(866) 973-3131.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)