SOW_UPDATED_Sealing_and_Striping_0001.pdf

PDF 75 KB Posted

Attached to
MN RICE LAKE NWR PARKING LOT SEALING & RESTRIPING
Solicitation number
140FS226Q0195
Issued by

About this file

This is a Statement of Work (SOW) for parking lot sealing and restriping services at Rice Lake National Wildlife Refuge Headquarters located at 36289 State Highway 65, McGregor, Minnesota 55760.

The contract (140FS226Q0195) requires the contractor to seal approximately 34,256 square feet of asphalt surface, including the main parking lot and roadway on 363rd Lane (approximately 695' x 24'), and apply approximately 565 linear feet of pavement markings matching the existing layout. Work scope includes surface preparation (debris and vegetation removal, ensuring dry surfaces, crack preparation), crack sealing per manufacturer specifications, asphalt sealing in accordance with manufacturer specifications and MN DOT Standards, and pavement striping conforming to MN DOT Standards. All sealcoat products, crack-seal products, and pavement striping materials must be MN DOT–approved, with application methods following MN DOT application tolerances, including specifications for product composition, certification requirements, surface preparation, temperature and humidity restrictions, application thickness, coverage, curing, performance criteria, and pavement marking visibility, durability, reflectivity, and color standards.

The contractor must provide a minimum of one week advance notice before work begins or alternatively perform work without impeding refuge or headquarters building access. Work completion is requested before the end of October 2026, with a typical timeframe of 3–7 days depending on weather conditions; if weather or scheduling prevents performance within that period, work will be postponed until April 2027. Deliverables include completed sealing and striping work plus a completion report documenting materials used, work dates, and recommended maintenance. The government will provide access to all work areas and an existing striping layout reference. The point of contact is Clint DeMenge, Heavy Equipment Manager – Region 3, at 218-821-5608.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140FS226Q0195 Parking Lot Sealing and Restriping Page 1 of 3 Rice Lake National Wildlife Refuge

Statement of Work (SOW)

Parking Lot Sealing and Restriping – Rice Lake National Wildlife Refuge Headquarters

36289 State Highway 65 McGregor, MN 55760

1. Project Overview

This project consists of sealing an estimated total of approximately 34,256 square feet of asphalt surface.

This estimated total area includes the parking lot and roadway on 363rd Lane (approximately 695’ x 24’).

Work also includes restriping an estimated 565 linear feet of pavement markings to match the existing layout.

2. Scope of Work

2.1 Surface Preparation

Contractor shall:

• Remove debris, vegetation, dirt, and loose aggregate.

• Ensure surfaces are fully dry prior to sealing.

• Prepare cracks as necessary.

2.2 Crack Sealing (If Applicable)

• Apply crack-seal material per manufacturer specifications and industry standards.

• Ensure a smooth, flush finish.

2.3 Asphalt Sealing

Contractor shall:

• Seal an estimated total of 34,256 sq ft, including the parking area and the roadway.

• Apply sealcoat in accordance with manufacturer specifications, industry best practices, weather and temperature requirements, and MN DOT Standards.

2.4 Pavement Striping

140FS226Q0195 Parking Lot Sealing and Restriping Page 2 of 3

Contractor shall:

• Apply an estimated 565 linear feet of pavement striping.

• Striping must match the existing layout.

• All striping materials and installation shall conform to MN DOT Standards.

3. Traffic Control & Access Requirements

Contractor shall:

• Provide a minimum of one (1) week advance notice before work begins so refuge staff can plan closures accordingly.

• Alternatively, perform work in a manner that does not impede access to the refuge or Headquarters building.

4. Performance Standards

4.1 General Requirements

All work shall comply with:

• Manufacturer specifications

• Industry standards

• Weather and temperature requirements

• MN DOT Standards

4.2 MN DOT Materials & Application Clause

All sealcoat products, crack-seal products, and pavement striping products, as well as all associated application methods, shall fully conform to MN DOT Standards, including (but not limited to):

• Product composition and certification requirements

• Approved materials lists

• Surface preparation requirements

• Temperature, humidity, and weather restrictions

140FS226Q0195 Parking Lot Sealing and Restriping Page 3 of 3

• Application thickness, coverage, curing, and performance criteria

• Pavement marking visibility, durability, reflectivity, and color standards

Contractor shall ensure all materials are MN DOT–approved and all workmanship follows MN DOT application tolerances.

5. Deliverables

• Completed sealing and striping per this SOW

• Completion report documenting materials used, dates of work, and recommended maintenance

6. Period of Performance

Work shall be completed within an agreed-upon timeframe, typically 3–7 days depending on weather conditions. Completion is requested before the end of October 2026. If weather or scheduling prevents performance within that period, the work will be postponed until April 2027.

7. Government-Provided Information

• Access to all work areas

• Existing striping layout reference

8. Point of Contact

Clint DeMenge Heavy Equipment Manager – Region 3

218-821-5608 Rice Lake NWR – McGregor, MN