This is Amendment 0001 to federal solicitation 140FS126Q0171 for deepwell diagnostic, repair, and rehabilitation services at Merced National Wildlife Refuge in Merced, California.
The amendment converts the acquisition from a Total Small Business Set-Aside to unrestricted competition, allowing all responsible business concerns to submit quotations. The pricing structure uses firm-fixed-price (FFP) base CLINs for diagnostic and known repair work on nine government-owned deep wells, with separately priced FFP optional repair CLINs (0010-0018) for foreseeable repairs to be exercised only by written Contracting Officer modification after applicable diagnostics establish necessity. Base CLINs cover nine specific wells (P1, P20, R7, P17B, P17A, P4, P9, P2, and P18) with diagnostic inspection, testing, sand/debris evaluation, electrical diagnostics, motor replacement, and a 100-amp electrical service replacement. Optional CLINs address well redevelopment/flushing, control box replacement, pump motor replacement, and control panel replacement. All quoters must price every base and optional CLIN, though optional CLIN pricing evaluation does not obligate the Government to exercise any option. The site visit is scheduled for September 15, 2026, at 9:00 a.m. Pacific Time; questions are due September 16, 2026, at 12:00 p.m. Pacific Time; and revised quotations are due September 18, 2026, at 12:00 p.m. Pacific Time. Performance period is September 28, 2026, through November 15, 2026, with work occurring Monday through Friday, 8:00 a.m. to 4:30 p.m., excluding Federal holidays. Quotations must be submitted as one consolidated PDF file to oscar_orozco@ios.doi.gov with the solicitation number in the subject line.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FS126Q0171_Amd_0002.pdf | ||
| Sol_140FS126Q0171.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140FS126Q0171 - Amendment 0001
AMENDMENT 0001
Solicitation 140FS126Q0171 Merced NWR - Deep Well Repair and Rehabilitation
Item Amended Information Solicitation Number 140FS126Q0171 Amendment Number 0001 Original Posted Date August 21, 2026 Acquisition Status Unrestricted - all responsible business concerns may submit a quotation Site Visit September 15, 2026, 9:00 a.m. Pacific Time Questions Due September 16, 2026, 12:00 p.m. Pacific Time Revised Quote Due September 18, 2026, 12:00 p.m. Pacific Time Submission Email to oscar_orozco@ios.doi.gov Place of Performance Merced National Wildlife Refuge, 7430 W. Sandy Mush Road, Merced, CA 95341
1. Purpose of Amendment Amendment 0001 revises Solicitation 140FS126Q0171 to place all quoters on a common pricing basis after the Government determined that the extent of certain repairs cannot reasonably be known until diagnostic inspection and testing are completed. The amendment also changes the acquisition from a Total Small Business Set-Aside to unrestricted competition and establishes a scheduled site visit.
The revised structure uses firm-fixed-price (FFP) base CLINs for diagnostic and known repair work and separately priced FFP optional repair CLINs for foreseeable repairs. There is no time-and-materials, labor-hour, cost-reimbursement, or generic repair allowance.
2. Changes Made by Amendment 0001
• Set-Aside: The Total Small Business Set-Aside is removed. The solicitation is unrestricted. All responsible business concerns may submit a quotation.
• Site Visit: September 15, 2026, at 9:00 a.m. Pacific Time at the Merced National Wildlife Refuge. Prospective quoters need not confirm attendance. A sign in sheet will be provided on the day of the site visit.
• Questions: Due September 16, 2026, at 12:00 p.m. Pacific Time.
• Quote Deadline: Extended to September 18, 2026, at 12:00 p.m. Pacific Time.
• Pricing: The original quotation schedule is replaced in its entirety by Attachment 1. Quoters shall price every base and optional repair CLIN.
• SOW: The original Statement of Work is replaced in its entirety by Attachment 2.
• Options: Optional Repair CLINs 0010-0018 are separately priced FFP options. They may be exercised only by written Contracting Officer modification after applicable diagnostics establish the repair is required.
• 100-Amp Requirement: P18 is confirmed as a 100-amp electrical service replacement. Attachment 2 and CLIN
0009 are revised accordingly.
• Wage Determination: The Service Contract Labor Standards wage determination incorporated with the original solicitation remains applicable and is not reissued with this amendment.
• Revised Quotations: All quoters wishing to remain under consideration shall submit a revised quotation based on the solicitation as amended and acknowledge Amendment 0001.
3. Provisions and Clauses Changed by This Amendment Only the following provision and option clause are added by Amendment 0001. All other provisions and clauses in the original solicitation remain unchanged except that the small-business set-aside provision is no longer applicable because the solicitation is unrestricted.
• 52.217-5, Evaluation of Options - incorporated by reference for evaluation of Optional Repair CLINs 0010-0018.
• OPTION FOR SEPARATELY PRICED REPAIR SERVICES - OPTIONAL REPAIR CLINS 0010-0018 (Tailored)
- incorporated in full text below.
52.219-6, Notice of Total Small Business Set-Aside, is deleted from the solicitation as a result of the unrestricted acquisition status.
OPTION FOR SEPARATELY PRICED REPAIR SERVICES - OPTIONAL REPAIR CLINS 0010-0018 (TAILORED)
(a) The Government may exercise one or more Optional Repair CLINs 0010 through 0018, independently and at the firm-fixed prices established at contract award.
(b) An optional repair CLIN may be exercised only when the applicable diagnostic work identifies the repair as necessary, funds are available, the Contracting Officer determines exercise is in the Government's best interest, and the Contracting Officer issues written notice exercising the applicable option.
(c) Exercise of one optional repair CLIN does not require exercise of any other optional repair CLIN.
(d) The Government may exercise Optional Repair CLINs 0010 through 0018 by written contract modification issued by the Contracting Officer no later than October 31, 2026.
(e) The Contractor shall not begin performance of an optional repair CLIN until that CLIN has been exercised in writing by the Contracting Officer. Direction, recommendations, requests, or communications from Government technical personnel do not exercise an option or authorize additional work.
(f) Upon exercise, the applicable optional repair CLIN shall be performed at the firm-fixed price established at contract award. The option price includes all labor, supervision, materials, equipment, transportation, removal, installation, testing, commissioning, documentation, overhead, profit, and other costs necessary to complete the repair described by the applicable CLIN and SOW.
(g) The Government is under no obligation to exercise any optional repair CLIN. Evaluation of optional repair CLINs for award does not obligate the Government to exercise any option.
(h) Repair conditions not within the scope of a base CLIN or Optional Repair CLIN 0010 through 0018 are not authorized by this clause and shall not be performed without separate written contractual authorization from the Contracting Officer.
(End of Clause)
4. Other Terms and Conditions Except as specifically modified by Amendment 0001, all other terms, conditions, provisions, clauses, wage determinations, and requirements of Solicitation 140FS126Q0171 remain unchanged.
5. Amendment Acknowledgment Quoter Legal Business Name Authorized Representative Name/Title Signature Date
Attachment 1 - Revised Quotation Schedule
Quoters shall provide firm-fixed prices for every base and optional CLIN. Optional CLIN pricing will be evaluated for award but does not obligate the Government to exercise any option.
CLIN Description Unit Qty Unit Price Total Price
P1 - Diagnostic/inspection:
video inspection, performance/sand testing, pump removal/reinstallation as necessary for diagnosis, operational testing, and diagnostic report.
Job 1 $________ $________
P20 - Diagnostic/inspection:
flow/drawdown testing, pump/motor/electrical inspection, pump removal/reinstallation as necessary for diagnosis, operational testing, and diagnostic report.
Job 1 $________ $________
R7 - Oil dripper replacement plus electrical/control/startup diagnostics, testing, and diagnostic report.
Job 1 $________ $________
P17B - Downhole inspection, sand/performance testing, pump removal/reinstallation as necessary for diagnosis, operational testing, and diagnostic report.
Job 1 $________ $________
P17A - Diagnostic testing, electrical inspection, casing/screen/pump inspection, applicable flow testing, reinstallation as necessary, and diagnostic report.
Job 1 $________ $________
P4 - Incoming power, control system, wiring/protection, and motor diagnostics/testing, with diagnostic report.
Job 1 $________ $________
P9 - Known motor replacement, electrical connection, testing, commissioning, and documentation in accordance with SOW Section 9.
Job 1 $________ $________
P2 - Flow/system diagnostics, pump/casing/screen inspection, reinstallation as
Job 1 $________ $________
CLIN Description Unit Qty Unit Price Total Price necessary, testing, and diagnostic report.
P18 - Known 100-amp electrical service replacement, testing, commissioning, permits/inspections, and documentation in accordance with SOW Section 11.
Job 1 $________ $________
TOTAL BASE FFP $________
Optional Firm-Fixed-Price Repair CLINs
CLIN Optional Repair Description
Unit Qty Unit Price Total Price
P1 - Well redevelopment and flushing following diagnostic confirmation that redevelopment is appropriate.
Job 1 $________ $________
P20 - Well redevelopment and flushing following diagnostic confirmation that redevelopment is appropriate.
Job 1 $________ $________
P17B - Well redevelopment and flushing following diagnostic confirmation that redevelopment is appropriate.
Job 1 $________ $________
P17A - Well cleaning/redevelopment following diagnostic confirmation that redevelopment is appropriate.
Job 1 $________ $________
P2 - Well cleaning/redevelopment following diagnostic confirmation that redevelopment is appropriate.
Job 1 $________ $________
R7 - Furnish and install replacement control box compatible with existing well/pump system; reconnect, test, and commission.
Job 1 $________ $________
R7 - Furnish and install replacement pump motor compatible with existing system;
reconnect, test, and commission.
Job 1 $________ $________
P4 - Furnish and install replacement control panel/control system compatible with existing well/pump system;
reconnect, test, and commission.
Job 1 $________ $________
P4 - Furnish and install replacement pump motor compatible with existing system;
Job 1 $________ $________
CLIN Optional Repair Description
Unit Qty Unit Price Total Price reconnect, test, and commission.
TOTAL OPTIONAL
FFP REPAIR PRICE $________
TOTAL EVALUATED
PRICE (BASE + ALL
OPTIONS)
Quoter Legal Business Name: ______________________________________________
UEI: ____________________________________
Authorized Representative/Title: __________________________________________
Signature: ____________________________________ Date: __________________
Attachment 2 - Revised Statement of Work
Deepwell Diagnostic, Repair, and Rehabilitation Services Merced National Wildlife Refuge
San Luis National Wildlife Refuge Complex 7430 W. Sandy Mush Road, Merced, CA 95341
1. General
1.1 Background
Merced National Wildlife Refuge encompasses more than 10,200 acres of wetlands, native grasslands, vernal pools, and riparian areas. Water management at the Refuge is supported by a network of deep wells used to pump groundwater for wetland management and habitat operations.
1.2 Purpose
The purpose of this requirement is to diagnose identified deficiencies and perform specified repair, rehabilitation, electrical, and testing services on nine (9) Government-owned deep wells and associated pumping systems. The objective is to restore each system to safe and reliable operation to the extent achievable through the work authorized under the contract.
1.3 Contractor Responsibility
The Contractor shall furnish all labor, supervision, materials, equipment, transportation, tools, testing equipment, temporary facilities, and incidentals necessary to perform the authorized work. Work shall be performed professionally and in accordance with applicable manufacturer requirements and Federal, State, and local laws, codes, permits, and regulations.
1.4 Diagnostic Findings and Repair Authorization
Base CLINs include the diagnostic and known repair work expressly stated in this SOW. Diagnostic findings shall be documented and provided to the CO. Optional Repair CLINs 0010-0018 may be exercised only when diagnostic findings establish the applicable repair is required and the CO provides written authorization. No other repair, replacement, redevelopment, cleaning, flushing, or corrective work may be performed without written CO authorization. Repairs not covered by the base scope or Optional Repair CLINs are not authorized and require a separate contractual determination/action.
2. General Performance Requirements
2.1 Safety and Compliance
1. Comply with applicable Federal, State, and local occupational safety and health requirements.
2. Comply with applicable DOI and USFWS safety requirements made applicable to the Contractor.
3. Comply with the applicable National Electrical Code (NEC) and manufacturer installation requirements for electrical work.
4. Conduct a jobsite safety assessment before onsite work.
5. Secure and protect active work areas.
6. Protect existing utilities, structures, equipment, roads, vegetation, wildlife habitat, and Government property.
7. Immediately notify the Government of unsafe conditions or damage resulting from Contractor operations.
2.2 Mobilization and Site Preparation
8. Mobilize personnel and equipment necessary for the authorized work.
9. Provide excavation, lifting, pumping, well-servicing, electrical, and other equipment required for the authorized work.
10. Coordinate access and work sequencing with the Government.
11. Protect the work area during performance.
12. Maintain work areas in a safe and orderly condition.
The Government may identify the order in which wells should be addressed based on operational needs. Such sequencing does not change scope or price unless authorized by the CO.
3. Deepwell P1 - Sand and Debris Production
3.1 Existing Information
• Well Size: 16 inches
• Pump Size: FLO 13 1/2-inch, 2-inch
• Well Depth: Approximately 95 feet
• Column Size: 10 inches
• Reported Current Production: Approximately 1,081 GPM
3.2 Existing Condition
The well is producing sand and debris. Suspected causes may include cavitation, wear, screen/casing deterioration, or structural failure.
3.3 Required Base Work
13. Perform video inspection of accessible well casing and screen.
14. Conduct well performance and sand-production testing.
15. Remove pump assembly as necessary to complete diagnosis.
16. Inspect pump assembly and accessible components for wear, damage, blockage, or deficiencies.
17. Reinstall existing serviceable pump equipment.
18. Conduct operational testing after reinstallation.
19. Document conditions, test results, and recommended corrective action.
If diagnostics support redevelopment/flushing, the Government may exercise Optional Repair CLIN 0010.
Component replacements not otherwise listed are not authorized without separate CO action.
4. Deepwell P20 - Reduced Water Production
4.1 Existing Information
• Well Size: 16 inches
• Pump Size: FLO 13 1/2-inch, 2-inch (verify existing equipment)
• Well Depth: Approximately 185 feet
• Column Size: 10 inches
• Reported Current Production: Approximately 1,068 GPM
4.2 Existing Condition
The well is reported to be producing less water than its historical or intended production level.
4.3 Required Base Work
20. Conduct flow and drawdown testing.
21. Inspect pump, motor, and accessible electrical components.
22. Evaluate accessible casing and screen for clogging, deterioration, or collapse.
23. Remove and inspect pump equipment when necessary for diagnosis.
24. Reinstall existing serviceable equipment.
25. Perform final operational and production testing.
26. Document findings and recommended corrective action.
If diagnostics support redevelopment/flushing, the Government may exercise Optional Repair CLIN 0011.
5. Deepwell R7 - Oil Dripper and Startup Failure
5.1 Existing Information
• Well Size: 16 inches
• Pump Size: 10 inches
• Well Depth: Approximately 160 feet
• Column Size: 10 inches
• Reported Current Production: Approximately 980 GPM
5.2 Existing Condition
The oil dripper assembly is reported defective and the pump is experiencing startup problems.
5.3 Required Base Work
27. Remove and replace defective oil dripper assembly with compatible replacement under Base CLIN 0003.
28. Diagnose electrical and control system.
29. Inspect control box, wiring, protective devices, and motor condition.
30. Test electrical system and startup sequence.
31. Verify pump operation after base work.
32. Document findings and test results.
If diagnostics establish a failed control box or motor, the Government may exercise Optional Repair CLIN 0015 and/or 0016.
6. Deepwell P17B - Sand and Debris Production
6.1 Existing Information
• Well Size: 16 inches
• Pump Size: 10 inches
• Well Depth: Approximately 420 feet
• Column Size: 10 inches
• Reported Current Production: Approximately 1,020 GPM
6.2 Existing Condition
The well is producing sand and debris. Possible causes include cavitation, wear, or structural deterioration.
6.3 Required Base Work
33. Perform downhole inspection of accessible casing and screen.
34. Conduct sand-infiltration and well-performance testing.
35. Pull and inspect pump equipment as necessary.
36. Document damaged, worn, obstructed, or deteriorated components.
37. Reinstall existing serviceable equipment.
38. Conduct operational and production testing.
39. Provide recommended corrective action.
If diagnostics support redevelopment/flushing, the Government may exercise Optional Repair CLIN 0012.
7. Deepwell P17A - Reduced/No Water Production
7.1 Existing Information
• Well Size: 12 inches
• Pump Size: 10 inches
• Well Depth: Approximately 402.6 feet
• Column Size: 10 inches
• Historical/Reported Production: Approximately 500 GPM
• Current Condition: No reported production
7.2 Existing Condition
The well is currently reported as producing no water and historically produced approximately 500 GPM.
7.3 Required Base Work
40. Perform diagnostic testing of well and pump system.
41. Conduct electrical inspection and applicable flow testing.
42. Inspect accessible casing, screen, pump, and associated components.
43. Reinstall existing serviceable equipment as necessary.
44. Conduct final operational testing.
45. Document resulting production rate, system condition, and recommended corrective action.
If diagnostics support cleaning/redevelopment, the Government may exercise Optional Repair CLIN 0013.
8. Deepwell P4 - Pump Startup Failure
8.1 Existing Information
• Well Size: 14 inches
• Pump Size: Peerless 12-inch
• Well Depth: Approximately 129 feet
• Column Size: 8-inch ID
• Reported Current Production: Approximately 950 GPM
8.2 Existing Condition
The pump is experiencing intermittent or failed startup conditions. Existing electrical power/control equipment is reported aged and potentially in need of replacement.
8.3 Required Base Work
46. Diagnose incoming electrical power and pump control system.
47. Inspect switches, control equipment, wiring, overload protection, and associated electrical components.
48. Inspect and electrically test pump motor.
49. Identify defective electrical or mechanical components.
50. Test system under operating conditions to the extent possible.
51. Document findings, electrical test results, and recommended corrective action.
If diagnostics establish that the control system or motor requires replacement, the Government may exercise Optional Repair CLIN 0017 and/or 0018.
9. Deepwell P9 - Motor Replacement
9.1 Existing Information
• Well Size: 14 inches
• Pump Size: 10 inches
• Well Depth: Approximately 162 feet
• Column Size: 8-inch ID
• Reported Current Production: Approximately 866 GPM
9.2 Existing Condition
The existing motor is reported failed or malfunctioning and requires replacement.
9.3 Required Base Work
52. Verify existing motor nameplate and compatibility requirements.
53. Disconnect and remove failed motor.
54. Furnish and install a new compatible motor for the existing pump, electrical service, mounting arrangement, voltage, phase, horsepower, speed, and operating environment.
55. Inspect accessible associated pump components for visible damage.
56. Complete electrical connections and testing.
57. Start and operate pump under normal load.
58. Verify proper rotation, startup, operation, and absence of abnormal vibration, noise, overheating, or electrical conditions.
59. Document manufacturer, model, serial number, ratings, and warranty.
Additional pump damage beyond the known motor replacement is not authorized without separate CO action.
10. Deepwell P2 - Reduced Water Production and Sand/Debris
10.1 Existing Information
• Well Size: 15 inches
• Pump Size: 10 inches
• Well Depth: Approximately 208 feet
• Column Size: 10 inches
• Reported Current Production: Approximately 760 GPM
10.2 Existing Condition
The well is reported to have reduced production and is producing sand or debris.
10.3 Required Base Work
60. Perform flow and system diagnostic testing.
61. Inspect accessible pump assembly, casing, and well screen.
62. Evaluate water-level changes, clogging, mechanical wear, or deterioration.
63. Reinstall existing serviceable equipment as necessary.
64. Perform final operational and production testing.
65. Document findings and recommended corrective action.
If diagnostics support cleaning/redevelopment, the Government may exercise Optional Repair CLIN 0014.
11. Deepwell P18 - 100-Amp Electrical Service Replacement
11.1 Existing Information
• Well Size: 16 inches
• Pump Size: FM 13 1/2-inch FIT (verify existing equipment)
• Well Depth: Approximately 150 feet
• Column Size: 10-inch and/or 12-inch (verify existing configuration)
• Reported Current Production: Approximately 1,800 GPM
11.2 Existing Condition
The existing electrical service equipment requires replacement to support continued operation of the deepwell pumping system.
11.3 Required Base Work
66. Verify field conditions and furnish/install a complete compatible replacement 100-amp electrical service.
67. Provide outdoor/wet-location NEMA-rated 100-amp service disconnect equipment and 100-amp main breaker.
68. Provide meter socket or meter-main combination when required by existing utility configuration.
69. Provide branch breakers necessary to reconnect existing well equipment and ancillary loads.
70. Provide code-compliant grounding and bonding, conductors, conduit, fittings, supports, and weather-resistant connectors.
71. Label circuits and disconnects.
72. Reconnect existing deepwell pump controls and associated equipment.
73. Verify voltage and phase before energization.
74. Remove replaced service equipment unless otherwise directed.
75. Coordinate de-energization/re-energization and required permits/inspections.
P18 is included in Base CLIN 0009. Additional work beyond this defined replacement is not authorized without separate CO action.
12. Optional Repair Work Requirements Optional Repair CLINs 0010-0018 are firm-fixed-price contingent repairs. Quoted prices shall include all labor, materials, equipment, removal, installation, testing, commissioning, cleanup, and documentation necessary for the specified repair. The Contractor shall verify compatibility and field conditions during the site visit and/or base diagnostic work. Exercise of an optional repair CLIN does not authorize work beyond the stated repair.
13. Testing and Commissioning
76. Operational startup and shutdown, as applicable.
77. Verification of proper motor rotation.
78. Flow/production measurement where applicable.
79. Sand-production observations where sand intrusion is an identified condition.
80. Electrical voltage and current measurements.
81. Continuity and insulation resistance testing where applicable.
82. Verification of grounding and bonding for new electrical work.
83. Observation for abnormal vibration, noise, leakage, overheating, or other apparent deficiencies.
Reported historical or existing GPM values are reference information unless expressly identified as a required performance threshold. The Contractor shall record test results and identify the test method/equipment used.
14. Deliverables
84. Diagnostic and inspection findings for each applicable well.
85. Downhole video inspection files where required.
86. Flow, drawdown, sand-production, electrical, and other applicable test results.
87. Final operational testing documentation.
88. Summary of work performed on each well.
89. Identification of materials and replacement equipment installed.
90. Before-and-after photographs when useful.
91. Manufacturer cut sheets and O&M information for newly installed major equipment.
92. Warranty documentation.
93. Electrical schematics or marked-up wiring diagrams for modified electrical systems.
94. As-built drawings or marked-up site sketches when infrastructure is changed.
95. Recommended follow-up repairs or maintenance.
96. Documentation of disposal or return of removed equipment as directed.
15. Inspection and Acceptance Work is acceptable when authorized work is complete; installed equipment is properly secured, connected, and operational; applicable testing is successfully completed; required deliverables are submitted; work areas are cleaned/restored; and deficiencies attributable to Contractor workmanship or installation are corrected. Government acceptance of diagnostic work does not establish a guarantee that a historical production rate will be restored unless expressly stated as a performance requirement.
16. Place and Period of Performance Place of Performance: Merced National Wildlife Refuge, 7430 W. Sandy Mush Road, Merced, California 95341.
Individual wells are located within the Refuge and will be identified by the Government. Performance may begin after award and required coordination. All work shall be completed no later than November 15, 2026. Normal onsite hours are Monday through Friday, 8:00 a.m. to 4:30 p.m., excluding Federal holidays, unless otherwise approved.
17. Government-Furnished Information and Utilities The Government will make available relevant historical well, pump, electrical, or maintenance documentation in its possession. The Contractor is responsible for temporary facilities and utilities necessary for performance. Existing Government utilities may be used only with prior Government approval when such use does not interfere with Refuge operations.
18. Site Access and Protection
97. Coordinate site access with the Government.
98. Limit operations to authorized work areas.
99. Maintain access for Government personnel where practicable.
100. Protect wildlife, vegetation, roads, structures, utilities, and Refuge resources.
101. Immediately report accidental damage or environmental releases.
102. Restore areas disturbed by Contractor operations to substantially their pre-work condition unless otherwise directed.
19. Removal, Disposal, and Warranty Unless otherwise directed, remove debris, waste, packaging, and replaced components and dispose of them in accordance with applicable requirements. Do not dispose of Government-owned equipment designated for retention. Provide standard commercial/manufacturer warranties for newly furnished equipment and materials, including coverage, duration, commencement date, warrantor, and warranty-service contact information.
20. Government Points of Contact Technical Coordinator: Gabriel Sandoval, Refuge Manager, Merced National Wildlife Refuge, Gabriel_Sandoval@fws.gov
Project Manager: Chris Harper, Project Leader, San Luis National Wildlife Refuge Complex, Chris_Harper@fws.gov
Government technical personnel may coordinate access, observe performance, and provide technical information.
Only the Contracting Officer may modify the contract, authorize additional work, change the contract price, or otherwise bind the Government contractually.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
See continuation page
FWS SAT 1
FWS, SAT Team 1 5275 Leesburg Pike Falls Church VA 22041
FS1
140FS126Q0171
08/21/2026
08/21/2026
1 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140FS126Q0171/0001
Quotation Submission: Quoters shall include
Solicitation No. 140FS126Q0171 in the email
Subject line to help ensure quotations are properly received and identified. Quotations shall be submitted as one consolidated PDF file. Failure to properly identify the solicitation number may result in the quotation being misidentified or not received for consideration.
Period of Performance: 09/28/2026 to
11/15/2026
| 1. Purpose of Amendment |
| 2. Changes Made by Amendment 0001 |
| 3. Provisions and Clauses Changed by This Amendment |
| OPTION FOR SEPARATELY PRICED REPAIR SERVICES - OPTIONAL REPAIR CLINS 0010-0018 (TAILORED) |
| 4. Other Terms and Conditions |
| 5. Amendment Acknowledgment |
| 1. General |
| 1.1 Background |
| 1.2 Purpose |
| 1.3 Contractor Responsibility |
| 1.4 Diagnostic Findings and Repair Authorization |
| 2. General Performance Requirements |
| 2.1 Safety and Compliance |
| 2.2 Mobilization and Site Preparation |
| 3. Deepwell P1 - Sand and Debris Production |
| 3.1 Existing Information |
| 3.2 Existing Condition |
| 3.3 Required Base Work |
| 4. Deepwell P20 - Reduced Water Production |
| 4.1 Existing Information |
| 4.2 Existing Condition |
| 4.3 Required Base Work |
| 5. Deepwell R7 - Oil Dripper and Startup Failure |
| 5.1 Existing Information |
| 5.2 Existing Condition |
| 5.3 Required Base Work |
| 6. Deepwell P17B - Sand and Debris Production |
| 6.1 Existing Information |
| 6.2 Existing Condition |
| 6.3 Required Base Work |
| 7. Deepwell P17A - Reduced/No Water Production |
| 7.1 Existing Information |
| 7.2 Existing Condition |
| 7.3 Required Base Work |
| 8. Deepwell P4 - Pump Startup Failure |
| 8.1 Existing Information |
| 8.2 Existing Condition |
| 8.3 Required Base Work |
| 9. Deepwell P9 - Motor Replacement |
| 9.1 Existing Information |
| 9.2 Existing Condition |
| 9.3 Required Base Work |
| 10. Deepwell P2 - Reduced Water Production and Sand/Debris |
| 10.1 Existing Information |
| 10.2 Existing Condition |
| 10.3 Required Base Work |
| 11. Deepwell P18 - 100-Amp Electrical Service Replacement |
| 11.1 Existing Information |
| 11.2 Existing Condition |
| 11.3 Required Base Work |
| 12. Optional Repair Work Requirements |
| 13. Testing and Commissioning |
| 14. Deliverables |
| 15. Inspection and Acceptance |
| 16. Place and Period of Performance |
| 17. Government-Furnished Information and Utilities |
| 18. Site Access and Protection |
| 19. Removal, Disposal, and Warranty |
| 20. Government Points of Contact |
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .