This document contains Questions and Responses related to Solicitation 140FS124Q0063 to Furnish and Install Solar Inverters at the FWS Stillwater NWR Complex in Nevada.
The key details are:
- The current solar system consists of two 7kW SunnyBoy inverters manufactured by Sanyo, installed approximately 14 years ago.
- Solicitation Amendment 0001 includes electrical plans and solar panel photos for the existing system.
- Site visits are encouraged but not mandatory, and can be arranged by contacting the Deputy Project Leader.
- The solicitation is for the replacement of the solar inverters at the Stillwater NWR Complex.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FS124Q0063_Amd_0002.pdf | ||
| DOL_Wage_Determination_No_2015_Rev_23_Date_of_Last_Revision_12-26-2023_0001.pdf | ||
| Sol_140FS124Q0063_Amd_0001.pdf | ||
| Sol_140FS124Q0063.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS & U.S. FISH & WILDLIFE SERVICE RESPONSES
SOLICITATION 140FS124Q0063
FURNISH & INSTALL SOLAR INVERTERS
FWS STILLWATER NWR COMPLEX NV
QUESTION 1: Can the end user provide the manufacture and model/serial number of the two inverters currently installed?
FWS RESPONSE: The manufacturer information is as follows:
• System Size: 14.4 kW
• Models: (72) Sanyo 200W – 36 panels to each inverter
• Inverter #1: SunnyBoy 7k SN: 2001064249
• Inverter #2: SunnyBoy 7k SN: 2000680189
• Age of System: Estimated 14 years.
QUESTION: Can the end user please provide the as built electrical plans for the solar system?
FWS RESPONSE: See Solicita�on Amendment 0001 Atachment, Electrical Plans & Solar Panel Photo.
QUESTION: In regard to the S�llwater NWR CPLX-Solar replacement effort, will you be having a site walk?
FWS RESPONSE: Site visits are not mandatory but encouraged to gain a beter understanding of the project. To arrange a visit, please contact:
Deputy Project Leader, Bethany Chagnon (Bethany_chagnon@fws.gov/775-217-7498), Monday through Friday, (9:00am to 3:00pm PDT, by appointment only.
mailto:Bethany_chagnon@fws.gov/775-217-7498
4/22/24, 2:30 PM Mail - Lockhart, Roger - Outlook https://outlook.office365.com/mail/inbox/id/AAQkADI3ZmZlYTJjLWY0MGYtNGQ3MS1iMmQ5LWZiMzk4YjIzMjQ4NQAQAO3hU8DkaaNOrisS0tGm7B… 1/1
4/22/24, 2:30 PM Mail - Lockhart, Roger - Outlook https://outlook.office365.com/mail/inbox/id/AAQkADI3ZmZlYTJjLWY0MGYtNGQ3MS1iMmQ5LWZiMzk4YjIzMjQ4NQAQAO3hU8DkaaNOrisS0tGm7B… 1/1
4/22/24, 2:29 PM Mail - Lockhart, Roger - Outlook https://outlook.office365.com/mail/inbox/id/AAQkADI3ZmZlYTJjLWY0MGYtNGQ3MS1iMmQ5LWZiMzk4YjIzMjQ4NQAQAO3hU8DkaaNOrisS0tGm7B… 1/1
File details come from the government source that posted it. Updated .