Q_and_A_Dumpster_Service_140FF027Q0057_0002.pdf

PDF 170 KB Posted

Attached to
IN PATOKA RIVER NWR DUMPSTER SERVICE
Solicitation number
140FF027Q0057
Issued by
Not on record

About this file

This is a Consolidated Vendor Questions document for Solicitation 140FF027Q0057, a dumpster service solicitation for Patoka River National Wildlife Refuge. The document addresses vendor inquiries regarding pricing structure, payment terms, operational requirements, and contract administration for a demolition debris removal and metal recycling project.

Offerors must submit two separate unit prices: (1) delivery and haul fee per container, and (2) disposal fee per ton. Payment is based on actual hauls performed and tonnage, which may vary from the estimated 24 hauls. A common per-haul/delivery rate applies to both waste-disposal and metal-recycling hauls, with initial container placement included in the per-haul rate. Invoicing occurs upon job completion with submission of disposal tickets showing weight from the landfill. Additional hauls beyond the 24-estimated require prior authorization from the Contracting Officer at the same price per container. For containers exceeding 10 tons, per-ton overage pricing applies rather than a fixed haul price. Container detention, rental, standby, or demurrage charges are allowable for government-caused delays but not weather-related delays; such charges must be clearly outlined in the offer.

The project involves demolition debris (concrete, brick, masonry, wood, dirt, metal) at two locations sequentially, with an estimated 12 working days in December. Debris may be delivered to either Velpen C and D Fill Site (Velpen, IN) or Republic Services (Mount Vernon, IN). Asbestos remediation has been completed by a government contractor. Contractors must maintain multiple containers on-site simultaneously (potentially two debris and one recycling container) with same-day swap capability to prevent work disruption, even during weekends. Working hours are 7:00 a.m. to 5:00 p.m. Central Time. Metal recycling proceeds are remitted directly to Friends of Patoka River NWR, LLC via cash or check based on recycling center receipts and are treated as administrative pass-through, not as contract price offsets. Scale tickets from disposal and recycling facilities must be provided to the refuge office. Site contact is Willie Pepmiller. The quotation deadline is November 17, 2026, at 5:00 p.m. Eastern Time.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140FF027Q0057 Dumpster Service Page 1 of 4 Patoka River National Wildlife Refuge

Solicitation 140FF027Q0057 | Consolidated Questions

Consolidated Vendor Questions

Solicitation 140FF027Q0057 | Patoka River NWR Dumpster Service

Purpose: This document consolidates the distinct questions received from prospective vendors. Substantially similar questions have been combined. Vendor names and repeated follow-up wording are omitted.

* We need the contractors to provide 2 prices (this will clear up a bunch of the questions and allow us to compare them all against each other):

1) Delivery and haul fee per container

2) Disposal fee per ton

1. Pricing, CLIN Structure, and Payment

1. Should offerors submit one firm-fixed total price for the complete project, or a unit price per completed haul based on the estimated 24 hauls? Unit Price see * above.

2. Should waste-disposal hauls and metal-recycling hauls use one common per-haul rate, or may separate rates be quoted? Common per haul/delivery rate no matter debris or recycling.

3. Should the initial delivery or placement of the containers be included in the per-haul rate or priced separately? Per haul rate.

4. What quantity, unit of measure, and evaluated total should offerors enter for CLIN 00010? See * above

5. Will payment be based on the actual number of authorized and accepted hauls performed? Yes.

6. If the actual number of hauls is fewer or greater than 24, will the awarded total remain unchanged or be adjusted by contract modification? Payment based on total hauls and tonnage. Could be less than 24 or more.

7. Will hauls beyond the estimated 24 require prior authorization from the Contracting Officer, and how will those additional hauls be priced and funded? Needs prior authorization, same price per container.

8. May the contractor submit partial or weekly invoices for completed hauls, or is invoicing expected only after the project is complete? Upon completion of the job and providing a copy to the office.

9. Are any closeout documents required beyond those identified in the solicitation? Provide disposal ticket of weight from delivery at landfill.

2. Weight, Disposal, and Debris

10. If a container exceeds 10 tons, should offerors include a per-ton overage rate, will the Government create a separate line item, or should the overage risk be included in the quoted haul price? See *, based on per ton

140FF027Q0057 Dumpster Service Page 2 of 4

Solicitation 140FF027Q0057 | Consolidated Questions

11. What types of debris should contractors anticipate, including concrete, brick, masonry, wood, dirt, metal, hazardous material, or other restricted material? Expect concrete, brick, masonry, wood, dirt, metal

12. Has a disposal facility already been approved to receive debris processed by the ARJES Impaktor? There are 2 disposal sites in the area that are approved to take such materials. Velpen C and D Fill Site (Velpen, IN), and Republic Services (Mount Vernon, IN)

13. Have the structures been inspected and remediated for asbestos or other regulated materials, and will documentation be available if required by the receiving landfill? Yes government contractor removed all asbestos already

3. Containers, Haul Mix, and Turnaround

14. Is the estimated quantity of 24 deliveries or hauls the total for both project locations and both waste streams? Yes, estimated total for both sites combined.

15. Is there an estimated split between demolition-debris hauls and metal-recycling hauls, or a recommended assumption for consistent pricing? Same price

16. How many containers are required at one time: one waste and one recycling container serving the active site, or separate pairs at both sites simultaneously? Need as many containers to keep demolition project moving. i.e. may need 2 debris containers and 1 recycling container there at one time, demolition work will continue over weekend and containers need to be in place to ensure work can continue without disruption whether or not hauling company works on weekend.

17. Would the Government accept two 15-yard containers in place of each required 30-yard container, with the 10-ton limit applied across the pair? No

18. What turnaround time is required after the contractor is notified that a container is full, such as same-day service or a 24-hour swap? Same day to ensure work can continue without disruption

4. Recycling Proceeds and Documentation

19. What materials must be separated for recycling? Metal, demo crew will coordinate and take care of separation

20. How should scrap-metal proceeds be remitted to Friends of Patoka River NWR, LLC, including whether the recycler or subcontractor may pay the organization directly? Cash or check provided to Friends based on receipt tickets from recycling center based on the total value of recycled materials. Provide receipt.

21. What scale tickets, receipts, or other supporting records must be provided, and how should they be included with IPP invoices? Scale tickets from disposal site and recycling center provided to office.

22. Will recycling proceeds be treated as a separate administrative pass-through rather than an offset or credit against the contract price? Pass through, not an offset as proceeds will be given to Friends.

140FF027Q0057 Dumpster Service Page 3 of 4

Solicitation 140FF027Q0057 | Consolidated Questions

5. Schedule, Sequencing, and Delays

23. Will demolition occur at both locations simultaneously, or will one site be completed before work moves to the other? One site at a time demo

24. The December 7-18 period contains 10 weekdays while the SOW references 12 working days. Should contractors anticipate weekend work, an extended performance period, or a different schedule? See #16

25. What working hours should contractors plan for? 7:00A – 5:00P Central Time

26. If the period of performance is extended because of weather or Government equipment or staffing availability, will container detention, rental, standby, or demurrage charges be allowable? Charges will be allowed for government delay not weather-related delays. Potential charges must be clearly outlined in offer.

6. Site Access and Operations

27. Where should containers be placed at each site, and are the placement areas and turnarounds adequate for loaded roll-off trucks and multiple containers? Will be coordinated by demo crew based on their needs. Yes ample areas are available for multiple containers.

28. Will the Government provide all-weather drivable access to the container drop points, including firm gravel or paved areas suitable for December conditions? All sites have gravel or paved roads with easy access. Demo crew will need to move dumpsters while on site and will need instructions on how to do so per container company specification.

29. Are there county-road, bridge-weight, seasonal-access, gate, access-hour, or entry-code restrictions that drivers must follow? Demo crew will make sure all County restrictions are conformed with.

30. Who is the on-site point of contact for container placement and swap requests? Willie Pepmiller

7. Site Visit, Subcontractors, and Proposal Requirements

31. Is the site visit optional, and may a local subcontractor attend on the prime contractor’s behalf? Yes

32. What subcontractor information must be included with the quotation? Is the subcontractor’s legal name, address, SAM UEI, and CAGE Code sufficient, or are technical capability and past-performance documents also required? Subcontractor’s legal business name

33. Can a proposed subcontractor’s relevant experience and technical capabilities be considered in the evaluation of the quotation? Yes.

8. Solicitation Documents and Deadline

34. Please confirm that the attached SOW is the correct version for Solicitation 140FF027Q0057, despite the different solicitation number shown in the SOW header. Yes. There is an extra 2 in the header (140FF0227Q0057). This is unintentional.

140FF027Q0057 Dumpster Service Page 4 of 4

Solicitation 140FF027Q0057 | Consolidated Questions

35. Please confirm that the quotation deadline is November 17, 2026, at 5:00 p.m. Eastern Time. Yes, correct.

1. Pricing, CLIN Structure, and Payment
2. Weight, Disposal, and Debris
3. Containers, Haul Mix, and Turnaround
4. Recycling Proceeds and Documentation
5. Schedule, Sequencing, and Delays
6. Site Access and Operations
7. Site Visit, Subcontractors, and Proposal Requirements
8. Solicitation Documents and Deadline