Sources Sought Synopsis Summary

This is a Sources Sought Synopsis issued by the U.S. Fish and Wildlife Service (USFWS) for informational and market research purposes only. The synopsis is not a Request for Proposal, quotation, or bid, and no solicitation is currently available. The estimated posting date for the resulting solicitation is on or about November 6, 2026, and interested firms must monitor SAM.gov for future issuance. Responses to this synopsis must be submitted electronically to Contracting Officer Cindy Salazar (cindy_salazar@ios.doi.gov) no later than 5:00 PM Pacific Standard Time on November 6, 2026. The requirement is classified under NAICS Code 238290 with a Small Business Size Standard of $22.0 Million and Product and Service Code Z2AZ. The resulting contract will be awarded on a Firm-Fixed-Price (FFP) basis. The synopsis encourages responses from Small Business, 8(a) firms, HUBZone, Women-Owned Small Business (WOSB), Economically Disadvantaged Women-Owned Small Business (EDWOSB), and Service-Disabled Veteran Owned Small Business (SDVOSB) firms, which are highly encouraged to respond.

The project scope, titled "Re-Key Project," involves replacing interior and exterior door hardware at Sheldon National Wildlife Refuge in Denio, Nevada (44280 Virgin Valley Road, Denio, NV 89404) to convert the facility to a Best Lock interchangeable core system compatible with existing systems at other refuge facilities. The contractor must furnish all labor, supervision, materials, equipment, transportation, tools, permits, and incidentals necessary to remove, replace, and modify existing hardware on designated doors while ensuring full operability, security, and compatibility with the Government's Best Lock system. Work includes four exterior doors (Outside Utility Door, Staff Entrance, Visitor Entrance, and Conference Room Exterior Entrance) and eight interior doors (Dividing Door, Manager's Office, Assistant Manager's Office, Interior Utility Room, Conference Room, Bathroom, Storage Closet, and IT Closet). The period of performance is 120 days from Notice to Proceed, with normal duty hours Monday through Friday, 7:00 AM to 4:30 PM. Contractors must have demonstrated experience installing commercial-grade door hardware and interchangeable core locking systems in commercial or government facilities and must comply with International Building Code (IBC), ADA Accessibility Guidelines (ADAAG), ANSI/BHMA standards, manufacturer installation requirements, OSHA safety regulations, and applicable federal, state, and local building codes. Potential contractors submitting capabilities responses should provide information on no more than three similar projects completed within the past five years, including contract details, pricing, complexity, and relevance to door hardware installation, and must include company name and address, points of contact, CAGE Code and Unique Entity Identifier (UEI) Number (must be registered in SAM.gov), interest in working as prime contractor or subcontractor, business size classification, and any socioeconomic program certifications.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 1

This is a SOURCES SOUGHT SYNOPSIS and is for informational / market research purposes only.

THIS IS NOT A REQUEST FOR PROPOSAL, QUOTATION OR BID, NOR A SYNOPSIS OF A

PROPOSED CONTRACT ACTION UNDER FAR SUBPART 5.2.

No reimbursement will be made for any costs associated with providing information in response to this synopsis or on any follow-up information.

NO SOLICITATION IS CURRENTLY AVAILABLE.

The purpose for this synopsis is to conduct market research to help identify capable, potential sources and to establish if this requirement can be set-aside for small business or other socioeconomic programs to include: Small Business, 8(a) firms, Historically Underutilized Business Zones (HUBZone), Women- Owned Small Business (WOSB), Economically Disadvantaged Women-Owned Small Business (EDWOSB) and Service-Disabled Veteran Owned Small Business (SDVOSB). Those programs are highly encouraged to respond.

The synopsis and solicitation, if issued, will be made available on https://www.SAM.gov. It is the potential offerors responsibility to monitor https://www.SAM.gov/opportunities for issuance of any future solicitation that may result from this Sources Sought Synopsis. The estimated posting date of the solicitation will be on or about 11/06/2026.

NAICS Code: 238290 Small Business Size Standard: $22.0 Million Product and Service Code (PSC): Z2AZ

The resulting solicitation and contract will be Firm-Fixed-Price (FFP).

GENERAL INFORMATION:

The U.S. Fish and Wildlife Service (USFWS) Contracting Office Background requirements for location Sheldon National Wildlife Refuge, Denio, Nevada. See Statement of Work (SOW) at end of this synopsis for the Re-Key project.

Re-Key Project:

For a qualified contractor to furnish all labor, supervision, materials, equipment, transportation, tools, permits (if required), and incidentals necessary to remove, replace, and/or modify existing door hardware on designated interior and exterior doors to convert the facility to a Best Lock interchangeable core system compatible with the existing Best Lock Interchangeable Core System currently in place at all other refuge facilities).

The contractor shall replace existing hardware as necessary to ensure all designated doors are fully operational, secure, and compatible with the Government's Best Lock interchangeable core system.

Where existing doors or frames require modification to accept new hardware, the contractor shall perform all necessary adaptations without compromising door operation, fire ratings (where applicable), or building security.

The contractor shall verify all existing conditions, door types, handing, frame configurations, and hardware requirements prior to ordering materials. Measurements and field verification are the contractor's responsibility.

https://www.sam.gov/ https://www.sam.gov/opportunities

The Contractor shall coordinate the acquisition of the Best Lock cores and keys with the government as the specific cores are secure and require authorization to purchase.

Contractor Qualifications: The contractor shall have demonstrated experience installing commercial-grade door hardware and interchangeable core locking systems in commercial or government facilities.

All work shall comply with:

1.B.1 Applicable International Building Code (IBC) 1.B.2 ADA Accessibility Guidelines (ADAAG) 1.B.3 ANSI/BHMA standards for commercial door hardware 1.B.4 Manufacturer installation requirements 1.B.5 OSHA safety regulations

Applicable Federal, State, and local building codes and any other standards not listed but required.

THE WORK CONSISTS OF:

Re-Key:

The contractor shall verify all existing conditions, door types, handing, frame configurations, and hardware requirements prior to ordering materials. Measurements and field verification are the contractor's responsibility.

The Contractor shall coordinate the acquisition of the Best Lock cores and keys with the government as

Read through the Statement of Work’s for the complete requirements and work.

The period of performance for the project is 60 days from Notice to proceed.

CAPABILITIES:

Contractors shall demonstrate the following:

1. Experience: At a minimum, firms shall provide the following information for similar work as listed on the Statement of Work

2. GENERAL INFORMATION and THE WORK CONSISTS OF: C ont r a c t o r s shall provide no more than three (3) projects and complete within the past five (5) years. Projects do not have to be Government contracts to be considered.

Documentation shall include the following:

- Contract Number

- Contract Title

- Contract Location

- Contract Type (FFP, Cost Reimbursement, or Other (Please Specify))

- Construction Type (D-B-B, Design-Build (D-B), or Other (Please Specify))

- Worked as the Prime Contractor, Subcontractor, Designer-of-Record, Joint Venture, or Other (Please

Explain)

- List of Major Subcontractors (i.e. Subcontracts Greater than $150,000) (List Subcontractors Disciplines)

- Contract Award Completion Date

- Contract Actual Completion Date

- Brief Explanation of Difference in Contract Award and Actual Completion Date

- Contract Award Price

- Contract Final Price (Inclusive of Modifications)

- Brief Explanation of Difference in Contract Award and Final Price

- Complexity of Project (High, Medium or Low)

- Briefly describe the contract and how it is relevant to installation of garage door installations as listed under GENERAL INFORMATION and THE WORK CONSISTS

OF.

INSTRUCTIONS TO RESPOND TO SOURCES SOUGHT SYNOPSIS:

Contractor’s responses to this synopsis shall be limited to 5 (3 contracts) pages and, at a minimum, shall include the following information:

1. Name and address

2. Points of contact name, phone number and email address

3. CAGE Code and Unique Entity Identifier (i.e. UEI) Number (MUST BE registered in SAM.gov)

4. Interest in working as a prime contractor, subcontractor and/or joint venture

5. Capabilities: Firms shall demonstrate their ability to meet the requirements in the section titled

CAPABILITIES.

6. Business size based on the listed NAICS Code, as well as any socioeconomic categories (Small Business, 8(a), HUBZone, WOSB, EDWOSB and SDVOSB)

7. Firms Joint Venture information (if applicable)

Responses will be shared within the Governments project team but otherwise will be held in strict confidence.

Interested firms shall respond to this synopsis no later than 5:00 PM Pacific Standard Time (PST) on November 6, 2026. All responses shall be submitted electronically to the Contracting Officer, Cindy Salazar, cindy_salazar@ios.doi.gov.

mailto:cindy_salazar@ios.doi.gov

STATEMENT OF WORK

Replace Interior and Exterior Door Hardware with Best Lock System

Sheldon National Wildlife Refuge July 16, 2026

1) General:

The U.S. Fish and Wildlife Service (USFWS) requires a qualified contractor to furnish all labor, supervision, materials, equipment, transportation, tools, permits (if required), and incidentals necessary to remove, replace, and/or modify existing door hardware on designated interior and exterior doors to convert the facility to a Best Lock interchangeable core system compatible with the existing Best Lock Interchangeable Core System currently in place at all other refuge facilities.

The contractor shall replace existing hardware as necessary to ensure all designated doors are fully operational, secure, and compatible with the Government's Best Lock interchangeable core system.

Where existing doors or frames require modification to accept new hardware, the contractor shall perform all necessary adaptations without compromising door operation, fire ratings (where applicable), or building security.

The contractor shall verify all existing conditions, door types, handing, frame configurations, and hardware requirements prior to ordering materials. Measurements and field verification are the contractor's responsibility.

The Contractor shall coordinate the acquisition of the Best Lock cores and keys with the government as

A. Contractor Qualifications: The contractor shall have demonstrated experience installing commercial-grade door hardware and interchangeable core locking systems in commercial or government facilities.

B. Standards: All work shall comply with:

1.D.1 Applicable International Building Code (IBC) 1.D.2 ADA Accessibility Guidelines (ADAAG) 1.D.3 ANSI/BHMA standards for commercial door hardware 1.D.4 Manufacturer installation requirements 1.D.5 OSHA safety regulations 1.D.6 Applicable Federal, State, and local building codes

C. Photographs of the doors are included. A pre-bid meeting will be held on TBD. For questions or additional information, see Refuge Contact Information.

D. Site Visit Contractors are encouraged to perform a site visit prior to submitting a proposal to verify existing conditions and quantities.

2) Place and Period of Performance A. Place of Performance: Sheldon National Wildlife Refuge, 44280 Virgin Valley Road, Denio, NV

89404.

B. Period of Performance: Notice to Proceed + 120 days

C. Normal Duty Hours Monday thru Friday 7:00am-4:30pm

D. Non-duty hours include weeknights, weekends, and Government holidays (New Year’s Day, Memorial Day, President's Day, Juneteenth, Fourth of July, Thanksgiving, Columbus Day, Christmas).

3) Scope

The contractor shall remove existing door hardware and install new hardware compatible with the Government's Best Lock interchangeable core system on the following doors.

A. Exterior Doors

The contractor shall replace or modify all existing locking hardware necessary to accommodate Best Lock interchangeable cores.

Doors include:

1. Outside Utility Door

2. Staff Entrance

3. Visitor Entrance

4. Conference Room Exterior Entrance

Work shall include:

• Removal of existing locksets, cylinders, strikes, closers (if replacement is required), panic hardware, and associated hardware.

• Installation of new commercial-grade hardware compatible with Best Lock interchangeable cores.

• Adjustment of doors and frames as necessary for proper alignment.

• Replacement of worn or damaged strikes, latch plates, hinges, or associated hardware where required to ensure proper operation.

• Installation of weather-resistant hardware suitable for exterior use.

• Proper adjustment to ensure doors latch, lock, and close correctly.

B. Interior Doors

The contractor shall replace existing hardware and adapt all designated interior doors to accept Best Lock interchangeable cores.

Doors include:

1. Dividing Door

2. Manager's Office

3. Assistant Manager's Office

4. Interior Utility Room

5. Conference Room

6. Bathroom

7. Storage Closet

8. IT Closet

Work shall include:

• Removal of existing locksets and cylinders.

• Installation of Best Lock compatible locksets and hardware.

• Replacement of latch assemblies and strikes as required.

• Modification of doors or frames as necessary to accommodate new hardware.

• Adjustment to ensure smooth operation and proper security.

General Requirements The contractor shall:

• Verify handing and swing of every door.

• Coordinate all lock functions with the Government prior to ordering hardware.

• Match existing hardware finishes unless otherwise approved.

• Protect adjacent walls, floors, and finishes from damage.

• Maintain building security throughout construction.

• Remove and dispose of all existing hardware off-site unless otherwise directed.

• Immediately report unforeseen conditions affecting installation.

• Coordinate work to minimize disruption to Government operations.

4) Deliverables and/or Delivery Schedule A. Prior to Construction

• Provide submittals for all hardware. Product data sheets for all proposed hardware.

• Hardware schedule identifying each door and associated hardware.

• Installation schedule.

• Project schedule.

• Any required manufacturer's certifications.

B. During Construction

• Daily cleanup of work areas.

• Protection of Government property.

• Coordination with COR regarding building access.

C. Project Closeout Provide:

• Manufacturer warranties.

• Hardware maintenance instructions.

• Final hardware schedule.

• Confirmation that all doors operate correctly.

• All applicable keys, cores, and documentation associated with the Best Lock system.

• Removal of all debris from the site.

• Invoices shall be submitted in accordance with Government contracting requirements. An email with a copy of each invoice will be submitted for approval to Caitlin Simms (caitlin_simms@fws.gov;

541-947-3315) with a cc to the Contracting Officer prior to payments. Approved invoices will then be submitted through IPP.gov

5) Government-Furnished Equipment and Government-Furnished Information

A. The Government shall furnish:

• Best Lock interchangeable cores.

• Keying schedule.

• Building access.

• Existing building drawings, if available.

All remaining materials, locksets, latch assemblies, cylinders, hinges (if required), strikes, fasteners, and miscellaneous installation materials shall be furnished by the contractor.

6) Evaluation and Acceptance A. Government representatives may inspect the work at any time.

mailto:(caitlin_simms@fws.gov

B. Final acceptance shall require:

i) All designated doors converted to the Best Lock interchangeable core system.

ii) Proper operation of all locks, latches, closers, and hardware.

iii) Doors opening and closing smoothly without binding.

iv) Hardware installed in accordance with manufacturer specifications.

v) Completion of punch list items.

vi) Delivery of all closeout documentation.

vii) Final Government inspection and acceptance. Inspection: the services/work performed under this contract are subject to observation and review by the USFWS and other authorities having jurisdiction.

C. Acceptance: Acceptance of the work is contingent on compliance with the requirements set forth in the statement of work awarded with, referenced by, and/or developed within the scope of the contract for this project. Final acceptance requires completion of all work, correction of deficiencies, delivery of closeout documents, and verification that the roof is weather-tight and installed per manufacturer requirements. Final acceptance requires successful inspections, code compliance, operational testing, correction of deficiencies, submission of warranties and closeout documents, and Government acceptance.

7) Quality Control/Quality Assurance:

A. The contractor shall maintain a quality control program throughout the project.

B. Work shall be:

i) Professionally installed.

ii) Secure and tamper resistant.

iii) Properly aligned and adjusted.

iv) Fully operational upon completion.

v) Free of cosmetic damage or installation defects.

vi) Installed in accordance with industry best practices and manufacturer recommendations.

vii) Any damaged finishes resulting from installation shall be repaired or replaced by the contractor at no additional cost to the Government.

viii) For commercial supplies and services reference clauses for inspection and acceptance. Where appropriate, QC will be maintained according to industry standards and made available to the agency with the contractor’s proposal.

C. Work and products shall be code-compliant, stout, secure, weather-tight, rodent-resistant, plumb-square-true, free of any readily noticeable defects when viewed by a casual observer and shall smoothly transition to meet-and-match existing adjacent features. To the extent feasible, new work shall appear seamless with existing structures and features.

8) Technical Coordinator:

A. Primary: Carissa Callison, Refuge Manager, USFWS, Sheldon NWR, PO Box 84, Denio, NV 89404; 541- 238-4536; carissa_callison@fws.gov

B. Secondary: Shannon Ludwig, Project Leader, USFWS, Sheldon-Hart Mt. NWRC, PO Box 111, Lakeview, OR 97630; 541-219-2707; shannon_ludwig@fws.gov mailto:carissa_callison@fws.gov mailto:shannon_ludwig@fws.gov

NO SOLICITATION IS CURRENTLY AVAILABLE.
GENERAL INFORMATION:
THE WORK CONSISTS OF:
CAPABILITIES:
INSTRUCTIONS TO RESPOND TO SOURCES SOUGHT SYNOPSIS:
STATEMENT OF WORK

File details come from the government source that posted it. Updated .