Sol_140FC325R0011_Amd_0001.pdf
PDF 121 KB Posted
- Attached to
- WA-LWS NFH-SEPTIC LINE REPAIR QUARTERS
- Solicitation number
- 140FC325R0011
About this file
This is a Standard Form 30 (SF-30) Amendment of Solicitation/Modification of Contract for a septic line repair project at the LWS Hatchery housing. The amendment (0001) is for Septic Line Repair for Quarters 6 and 7, issued by the Fish and Wildlife Service Construction A/E Team 3 located in Falls Church, VA. The period of performance is from 07/23/2025 to 08/31/2025, with a site visit conducted on 07/10/2025 at the LWS Hatchery housing.
The amendment includes a site visit sign-in sheet with contact information for two potential contractors: Paul Van Laar from Beam Exc. and representatives from River City (Chas Eakmen Caldwell and Jeremy Bennett). The contract references FAR clause 52.236-27 regarding site visits and provides contact information for the Contracting Officer, Shannon Barnhill, with an email address of shannon_barnhill@fws.gov. The document indicates that contractors must acknowledge receipt of this amendment prior to the specified date and time.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FC325R0011_Amd_0002.pdf | ||
| Sol_140FC325R0011.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140FC325R0011
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
FC3
Falls Church VA 22041 5275 Leesburg Pike FWS, Construction A/E Team 3 FWS Constr A/E 3
06/18/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/18/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Septic Line Repair for Quarters 6 and 7 in accordance with the attached Statement of Work.
Refer to 52.236-27 - SITE VISIT for site visit information.
This amendment is to provide the site visit sign in sheet.
Period of Performance: 07/23/2025 to 08/31/2025
Points of Contact:
Contractor:
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Shannon Barnhill
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140FC325R0011/0001
Contracting Officer Representative (COR):
Contracting Officer:
Shannon Barnhill shannon_barnhill@fws.gov
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Septic Work Sight Visit
07/10/2025
LWS Hatchery housing
1. Paul Van Laar Beam Exc.
541-490-3585 Paul.Beamexcavating@gmail.com
2. Chas Eakmen Caldwell River city 571-303-3313 Chas.eakmen-caldwell@rivercityusa.com
Jeremy Beanett River City 360-601-8153 Jeremy.bennett@rivercityusa.com mailto:Paul.Beamexcavating@gmail.com mailto:Chas.eakmen-caldwell@rivercityusa.com mailto:Jeremy.bennett@rivercityusa.com
File details come from the government source that posted it. Updated .