Sol_140FC325R0005_Amd_0001.pdf
PDF 200 KB Posted
- Attached to
- HI-Hakalau NWR PV System replacement Federal contract opportunity
- Solicitation number
- 140FC325R0005
About this file
This is an amendment (Amendment 0001) to solicitation 140FC325R0005 for a Photovoltaic System Replacement project at the Hakalau Forest National Wildlife Refuge in Hawaii, issued by the Fish and Wildlife Service Construction A/E Team 3 in Falls Church, VA. The amendment contains a Q&A section addressing technical questions about the current solar power system and project requirements.
The Q&A clarifies that while the current solar system is sufficient, the project aims to: 1) replace failing lead-acid batteries with advanced lithium chemistry batteries and upgrade inverters accordingly, 2) add redundancy for improved system resilience, and 3) accommodate future station growth and increased electrical loads. Most technical questions about system specifications, current equipment details, and usage patterns were deferred to the second phase (design request) of the solicitation. The amendment confirms that new large loads are expected to be added in the next year. The effective date is listed as January 6, 2025.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FC325R0005_Amd_0003.pdf | ||
| Sol_140FC325R0005_Amd_0002.pdf | ||
| Sol_140FC325R0005.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140FC325R0005
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
FC3
Falls Church VA 22041 5275 Leesburg Pike FWS, Construction A/E Team 3 FWS Constr A/E 3
01/06/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/06/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Photovoltaic System Replacement HI Hakalau Forest National Wildlife Refuge in accordance with the attached statement of work.
Points of Contact:
Contractor:
TBD
Contracting Officer Representative (COR):
TBD
Contracting Officer:
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Shannon Barnhill
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140FC325R0005/0001
Shannon Barnhill shannon_barnhill@fws.gov
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Amendment 0001 – Questions and Answers **The questions deadline has now closed**
Question 1: Was the current solar, inverter, storage, combination sufficient for the station’s needs?
Answer: Yes. However, the intent of this project is to: 1) replace current lead-acid batteries that are failing with more advanced lithium chemistry batteries and correspondingly upgrade the inverters to more technologically advanced models that create a maximally compatible system, 2) create an additional redundancy to have a system more resilient to possible failures, and 3) to have a system that can easily accommodate future station growth and corresponding load on the electrical system.
Question 2: What azimuth, pitch, and construction is the mounting roof?
Answer: This question should be deferred to the second phase (design request) of the solicitation.
Question 3: Please provide the make and model numbers of the current batteries, Outback Inverters / Charge Controllers, solar modules, and generator, for design reference.
Question 4: Can you provide a recent average daily kWhr’s consumed at the site? (daily usage for the past 365 days would be ideal)
Question 5: What is the single largest load on site and what size CB controls it?
Question 6: Are there any expected new large loads to be added in the next year?
Answer: Yes.
Question 7: Has the specified 50kWhr of storage been calculated to account for the minimum required days of autonomy where solar is not available? If not, how many days of autonomy (i.e. without solar) are required from the batteries?
File details come from the government source that posted it. Updated .