Sol_140FC325R0003_Amd_0002.pdf
PDF 89 KB Posted
- Attached to
- NV Upper Carson Slough Backcountry Trail System
- Solicitation number
- 140FC325R0003
About this file
This is Amendment 0002 to solicitation 140FC325R0003, containing questions and answers for the Ash Meadows National Wildlife Refuge Upper Carson Slough Backcountry Trail System project. The amendment clarifies two key points: 1) Only the Prime Contractor's past performance will be evaluated, not subcontractors', and 2) Directs offerors to Section J of the solicitation for accessing plans and specifications attachments.
The project has an estimated magnitude between $1,000,000 and $5,000,000 and is being administered by the FWS Construction A/E Team 3 in Falls Church, VA. The amendment notes that the questions deadline has closed and the requirement is subject to availability of funds. The Contracting Officer is Shannon Barnhill, with both the Contractor and Contracting Officer Representative (COR) positions listed as TBD.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FC325R0003_Amd_0006.pdf | ||
| Sol_140FC325R0003_Amd_0005.pdf | ||
| Sol_140FC325R0003_Amd_0004.pdf | ||
| Sol_140FC325R0003_Amd_0003.pdf | ||
| Sol_140FC325R0003_Amd_0001.pdf | ||
| Sol_140FC325R0003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140FC325R0003
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
FC3
Falls Church VA 22041 5275 Leesburg Pike FWS, Construction A/E Team 3 FWS Constr A/E 3
01/08/20250002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/02/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Ash Meadows National Wildlife Refuge Upper Carson Slough Backcountry Trail System in accordance with the attached Statement of Work.
**The questions deadline has now closed**
This requirement is subject to availability of funds.
Project Magnitude: Between $1,000,000 and $5,000,000.
Amendment 0002 - Questions and Answers
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Shannon Barnhill
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140FC325R0003/0002
Question 1: In reference to the Phase I, Volume
3: Factor II, Past Performance requirements, please confirm if key subcontractors past similar projects can be presented with the proposal, in lieu of the general contractors.
Answer: Only the Prime Contractor's past performance will be evaluated.
Question 2: Are the plans and specs to be released as it is listed on Sam.gov as a solicitation?
Answer: Please refer to Section J of the solicitation for the link to all attachments.
Points of Contact:
Contractor:
TBD
Contracting Officer Representative (COR):
TBD
Contracting Officer:
Shannon Barnhill shannon_barnhill@fws.gov
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110