B09_Amd2_Q_A_HVAC_WV_0002.docx

DOCX document 20 KB Posted

Attached to
HVAC Replacement - WV Federal contract opportunity
Solicitation number
140FC226R0011
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This is a Question and Answer (Q&A) document for an HVAC replacement solicitation issued by the Department of the Interior Fish and Wildlife Service (Solicitation Number: 140FC226R0011). The document addresses three sets of contractor inquiries regarding the scope, specifications, and execution of the project.

The solicitation requires replacement of HVAC equipment with mini-split/multi-split systems featuring wall-mounted indoor heads, powered by 208-volt, 3-phase incoming electrical service. The existing outdoor units are Trane XR models (4TWR4036D1000AB) operating at 208/240 volts on 410A refrigerant, though indoor unit models and serial numbers are not available. The contractor is responsible for determining final line set lengths based on field conditions and approved shop drawings. The period of performance will be confirmed prior to award, with the solicitation indicating dates from July 13, 2026 through January 29, 2027 (approximately 200 days). The building will remain occupied by a small staff during construction, with several rooms containing aquatic systems housing endangered and non-endangered species requiring safety coordination. The facility is less than 20 years old and contains no asbestos or lead. The project is tax-exempt and does not require third-party inspections, permitting, partitioning, dust containment, or negative air machines; however, a manufacturer's representative must review and verify the installed system against approved shop drawings. One individual may serve as Superintendent, Safety and Site Health Officer (SSHO), and Quality Control (QC) Manager. Equipment delivery is permitted directly to the site, with the contractor responsible for receiving, unloading, and signing for all materials.

View the file

Other files for this federal contract opportunity

Other files attached to HVAC Replacement - WV, newest first.
File Type Posted
Sol_140FC226R0011_Amd_0002.pdf PDF
Sol_140FC226R0011_Amd_0001.pdf PDF
SOW_HVAC_Replacement_with_drawings.pdf PDF
Past_Performance_Survey.pdf PDF
Sol_140FC226R0011.pdf PDF
Wages.pdf PDF
B08_Bid_Sheet.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A HVAC WV

Set1)

1. What type/style of indoor units does the Government require: cassette, wall-mounted, ducted, or another type?

2. The SOW states that the replacement system shall be a VRF heat pump system; however, the listed part number appears to be for a mini-split/multi-split type unit. Can the Government please clarify whether a true VRF system is required, or whether the listed mini-split/multi-split units are acceptable?

3. What is the available site electrical voltage and phase for the HVAC equipment?

4. Are the required line set lengths available, or should the contractor determine final line set lengths based on field conditions and approved shop drawings?

5. Can the Government provide the model and serial numbers of the existing outdoor and indoor HVAC units scheduled for removal?

Answers

1. Wall mounted indoor heads

2. Mini split/ muti split system only

3. Incoming power is 208 Volt 3 Phase

4. It is the contractors responsibility for the line set lengths

5. The outdoor units are Trane XR --model-4TWR4036D1000AB Serial # 161232TUBF Model - 4TWR4036D1000AB Serial # 16345LMNBF Both 208/240 Volt 410A Freon Indoor units I do not have model and serial #'s

Set2)

1 The SOW states the work is to be completed within 180 days of award, while the solicitation identifies a Period of Performance of 07/13/2026 through 01/29/2027 which is 200 days. Additionally, SF-1442 Block 11 indicates 0 calendar days. Please confirm the required Period of Performance for this project.

2 Will direct delivery of materials and equipment to the work site be permitted? Additionally, may contractor vehicles be parked at or immediately adjacent to the work site during working hours to support construction activities?

Answers

1 Confirmation of start and end dates will be agreed upon prior to award. For bidding purposes, the scope of work indicates accurate period of performance.

2 The contractor can park their vehicles in the gravel parking lot beside the building. The equipment can be directly delivered to the job site but the contractor needs to be here when it is delivered and it is their responsibility to unload the equipment and sign for it.

Set3)

1. Can one person "triple hat" as Superintendent, SSHO and QC Manager?

2. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

3. Please provide the site visit attendee sign in sheet.

4. (If building is occupied) Are there any phasing requirements? How many people will be in the building? Are there any temporary heating/cooling requirements?

5. Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation.

6. Is this project tax exempt?

7. When do you anticipate on site work starting?

8. Are third party inspections required?

9. Is permitting required?

10. Are partitioning, dust containment, and/or negative air machines required for this project?

Answers

1. Yes

2. Period of performance will be agreed upon, considering all relevant current factors, prior to award.

3. No information will be provided

4. Yes, it will be occupied by a couple of staff members at any given time and expensive aquatic systems are in several rooms with endangered and non-endangered species.

5. No lead or asbestos present, this building is less than 20 years old

6. Yes

7. Based on period of performance and material/equipment lead times as asked in question #2

8. No. "A manufacturer’s representative shall review the installed system and verify the work has been completed per the approved shop drawings." is required in the Objectives section. Contractor is also required to perform their own inspections.

9. No

10. No, but contractor will work with staff to ensure safety measures are used for equipment and aquatic species.