Question_and_Answers_0001.docx

DOCX document 15 KB Posted

Attached to
NY-LWR GRT LAKES FSHRY RSRCS STORAGE VEN
Solicitation number
140FC226Q0039
Issued by

About this file

This is a Question and Answers document for federal solicitation 140FC226Q0039, addressing clarifications on a ventilation system project for the NY-Lower Great Lakes Fishery Resources Storage facility under the Department of the Interior Fish and Wildlife Service. The document clarifies that the government has not predetermined quantities, sizes, or placement locations for ridge vents, wall exhaust fans, and wall louvers, nor has an engineer been engaged to establish specific airflow requirements or air changes per minute/hour specifications. Contractors are directed to follow the Statement of Work requirements when developing proposals and should demonstrate with reasonable confidence that their proposed solutions will resolve the facility's moisture issues, though this is not a design-build engagement.

View the file

Other files

File Type Posted
Sol_140FC226Q0039_Amd_0001.pdf PDF
A04_Scope_of_Work.pdf PDF
B03_WD.pdf PDF
Sol_140FC226Q0039.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Are the required quantities and sizes for the ridge vents, wall exhaust fans and wall louvers already determined?

Answer: Quantities and sizes are not determined. We are seeking proposals to resolve our moisture issue.

2. Is there an engineer involved in the design of the airflow requirements?

Answer: There is not an engineer involved. Proposals should show with reasonable confidence that they will resolve our issues.

3. Are there specific air changes per minute/hour requirements for the building?

Answer: No

4. Are the placement locations for the wall exhaust fans and louvers already identified?

Answer: No

5. If these items have not been predetermined, should the contractor propose a complete design/build ventilation solution based on the SOW requirements?

Answer: Please follow the SOW, this would not be a design/build.