Question_and_answers_for_140FC225Q0049_0002.docx

DOCX document 15 KB Posted

Attached to
BOAT DOCK REPLACEMENT Federal contract opportunity
Solicitation number
140FC225Q0049
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This document is a Questions and Answers file for Solicitation 140FC225Q0049, a Boat Dock Replacement project for the Upper Mississippi National Wildlife Refuge. The Q&A addresses two specific technical details about the dock installation: contractors are permitted to use 3 1/2 inch pipe with an auger point for securing the dock to the water bottom, and the ramp will not include floatation at this time. The solicitation is issued by the Department of the Interior Fish and Wildlife Service, indicating this is a federal infrastructure improvement project for a national wildlife refuge boat dock facility.

View the file

Other files for this federal contract opportunity

Other files attached to BOAT DOCK REPLACEMENT, newest first.
File Type Posted
Sol_140FC225Q0049_Amd_0002.pdf PDF
Sol_140FC225Q0049_Amd_0001.pdf PDF
A04_Amended_SOW_Long_Lake_Dock_Replacement_0001.pdf PDF
A04_SOW_Long_Lake_Dock_Replacement.pdf PDF
B03_WD.pdf PDF
A06_Specs.pdf PDF
Sol_140FC225Q0049.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question and answers for 140FC225Q0049, Upper Mississippi NWR Boat Dock

In response to the question about using 3 1/2 inch pipe with auger point instead of 4 inch pipe?

1. Contractors can use 3 ½ inch pipe that augers in for securing the dock to the water bottom.

Question about floatation on the ramp:

1. Ramp will not have floatation at this time.