B09_Amendment_Questions_and_Answers_20250527_0001.pdf
PDF 221 KB Posted
- Attached to
- VA HARRISON LAKE NFH POND ELEC. UPGRADE Federal contract opportunity
- Solicitation number
- 140FC225Q0029
About this file
This document is a Questions and Answers record from a site visit for Solicitation 140FC225Q0029, related to an electrical panel upgrade at Harrison Lake National Fish Hatchery. The Q&A session covered key technical details including post installation, electrical work, and project specifications. Notably, the Fish and Wildlife Service (FWS) will purchase and set 19 posts, new panels require grounding, and no branch circuit re-wiring is planned. The main electrical supply is located near the generator.
The site visit clarified operational parameters, with work hours set for Monday-Friday, 7am-4:00pm, with potential limited weekend work allowed. The disconnect locations are to be installed safely, positioned just below ground to avoid interference with mowers or heavy equipment. This document provides critical clarification for potential contractors about the scope and specific requirements of the electrical panel upgrade project at the hatchery.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FC225Q0029_Amd_0001.pdf | ||
| Sol_140FC225Q0029.pdf | ||
| A04_SOW_DB_Wage_Rate_Clauses_20250515.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation 140FC225Q0029
Harrison Lake NFH, Electrical Panel Upgrade May
27, 2025
The following questions were asked and answered during the Site Visit:
1. Are all 19 post going to be set- ANSWER- Yes FWS will purchase posts and set them for all 19 panels
2. Will there be any branch circuit re-wiring, extending wires to the new locations? ANSWER- no
3. Where is the main supply? ANSWER- over by the generator
4. Do new panels need grounding? ANSWER- Yes
5. Do new existing panels need grounding? ANSWER- no
6. What requirements do you want for the 2 disconnect locations? ANSWER we want disconnect to be safe and just below the ground so we wont hit them with mowers or heavy equipment
7. What are the hours of operation? ANSWER M-F 7am-4:00pm. Limited weekend work may be allowed