B09_Amendment_Questions_and_Answers_20250527_0001.pdf

PDF 221 KB Posted

Attached to
VA HARRISON LAKE NFH POND ELEC. UPGRADE Federal contract opportunity
Solicitation number
140FC225Q0029
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This document is a Questions and Answers record from a site visit for Solicitation 140FC225Q0029, related to an electrical panel upgrade at Harrison Lake National Fish Hatchery. The Q&A session covered key technical details including post installation, electrical work, and project specifications. Notably, the Fish and Wildlife Service (FWS) will purchase and set 19 posts, new panels require grounding, and no branch circuit re-wiring is planned. The main electrical supply is located near the generator.

The site visit clarified operational parameters, with work hours set for Monday-Friday, 7am-4:00pm, with potential limited weekend work allowed. The disconnect locations are to be installed safely, positioned just below ground to avoid interference with mowers or heavy equipment. This document provides critical clarification for potential contractors about the scope and specific requirements of the electrical panel upgrade project at the hatchery.

View the file

Other files for this federal contract opportunity

Other files attached to VA HARRISON LAKE NFH POND ELEC. UPGRADE, newest first.
File Type Posted
Sol_140FC225Q0029_Amd_0001.pdf PDF
Sol_140FC225Q0029.pdf PDF
A04_SOW_DB_Wage_Rate_Clauses_20250515.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 140FC225Q0029

Harrison Lake NFH, Electrical Panel Upgrade May

27, 2025

The following questions were asked and answered during the Site Visit:

1. Are all 19 post going to be set- ANSWER- Yes FWS will purchase posts and set them for all 19 panels

2. Will there be any branch circuit re-wiring, extending wires to the new locations? ANSWER- no

3. Where is the main supply? ANSWER- over by the generator

4. Do new panels need grounding? ANSWER- Yes

5. Do new existing panels need grounding? ANSWER- no

6. What requirements do you want for the 2 disconnect locations? ANSWER we want disconnect to be safe and just below the ground so we wont hit them with mowers or heavy equipment

7. What are the hours of operation? ANSWER M-F 7am-4:00pm. Limited weekend work may be allowed