Questions_For_Solicitation_140FC223A0022_0001.docx

DOCX document 12 KB Posted

Attached to
HVAC Installation at Dwight D. Eisenhower NFH
Solicitation number
140FC223Q0022
Issued by

View the file

Other files

File Type Posted
Sol_140FC223Q0022_Amd_0001.pdf PDF
Wage_Determination_VT20220020.pdf PDF
Sol_140FC223Q0022.pdf PDF
SOW_HVAC.pdf PDF
Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS FOR SOLICITATION 140FC223A0022 – Dwight D. Eisenhower NFH HVAC

1. Page 1 on the solicitation, it states “Complete it within 20 calendar days after receiving NOTICE TO PROCEED”, but on page 3 of the solicitation, it states “Period of Performance: 07/06/2023 to 07/31/2023” can you please clarify what the period of performance is?

A: Period of performance is 20 calendar days after Notice to Proceed (NTP). We issue the NTP after we receive your certificate of insurance and payments bonds (this kind of bond is a requirement if your offer is over $35K), you have 5 days after award to submit any bonds and insurance. The PoP of 7/6-7/31 accounts for the 5-day timeline for bonds and 20 for performance.