B09_AMEND_P0001_Q-A_0001.pdf

PDF 64 KB Posted

Attached to
AK-YUKON FLATS NWR-ASPHALT HOT STRIPING
Solicitation number
140FC125Q0018
Issued by

About this file

This is a Questions and Answers document (Amendment P0001) for solicitation 140FC125Q0018 regarding hangar asphalt hot striping work at Alaska-Yukon Flats National Wildlife Refuge (NWR). The document addresses six contractor inquiries about this Request for Quote (RFQ) for a new project that is currently open for bidding.

Key project details clarified include that this is a brand-new project with no incumbent contractor, involving crack fill and asphalt repair work with completion required by August 31, 2025 (subject to change based on award timing). The government directed potential contractors to review the Statement of Work thoroughly for specific scope details rather than confirming whether sealcoating is included. For submission requirements, bidders are instructed to consult page 66, section L.1.2 of the solicitation document for detailed bid submission instructions and compliance requirements.

View the file

Other files

File Type Posted
Sol_140FC125Q0018_Amd_0002.pdf PDF
Sol_140FC125Q0018_Amd_0001.pdf PDF
Sol_140FC125Q0018.pdf PDF
A04-SOW_YUKON_UPDATED.pdf PDF
B08_Sol-YUKON.pdf PDF
B03_WAGE_DETERMINATION-1-03-2025.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B09 AMENDMENT P0001 QUESTIONS AND ANSWERS FOR AK-YUKON FLATS NWR-

HANGAR ASPHALT HOT STRIPING-140FC125Q0018

1. Is there any incumbent/recompete or is this a brand-new project?

Answer: This is a new project.

2. This is still open for bid?

Answer: Yes

3. This is just crack fill and asphalt repair, no sealcoat?

Answer: Kindly ensure that you review the Statement of Work (SOW) thoroughly, as all relevant information is detailed within that document.

4. There are di erent completion timeframes listed; first is Aug 31,2025 and the second is 60 days from NTP?

Answer: The correct completion date will be Aug 31, 2025 (May change depending on awarded.

5. What type of solicitation is this; RFQ, IFB, or RFP?

Answer: This is an RFQ.

6. Can the bids be submitted via email or do all bids need to be sealed and delivered hard copies?

Answer: Please review the solicitation document, specifically page 66, section L.1.2, which provides detailed instructions regarding the submission requirements for bids and quotes.

Kindly refer back to this section to ensure compliance.

File details come from the government source that posted it. Updated .