UNITED STATES

DEPARTMENT OF THE INTERIOR

FISH AND WILDLIFE SERVICE

REGION 6 ENGINEERING

Lakewood, Colorado

NEW VEHICLE STORAGE BUILDING

AUDUBON NATIONAL WILDLIFE REFUGE

McLean County, North Dakota

19-012 06/06/2019

THIS PAGE WAS ALMOST LEFT BLANK

SPECIFICATION INDEX 000001 - 1

DESCRIPTION/SPECIFICATIONS

NEW VEHICLE STORAGE BUILDING

AT

AUDUBON NATIONAL WILDLIFE REFUGE

(19-012)

SPECIFICATION INDEX

DIVISION 1 - GENERAL REQUIREMENTS

SECTION 000001 SPECIFICATION INDEX

011000 SUMMARY OF WORK

012900 PAYMENT PROCEDURES

013100 PROJECT MANAGEMENT AND COORDINATION

013200 CONSTRUCTION PROGRESS DOCUMENTATION

013233 PHOTOGRAPHIC DOCUMENTATION

013300 SUBMITTAL PROCEDURES

013310 SUBMITTAL FORM TEMPLATE

014000 QUALITY REQUIREMENTS

015000 TEMPORARY FACILITIES AND CONTROLS

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 CLOSEOUT PROCEDURES

017823 OPERATION AND MAINTENANCE DATA

DIVISION 3 - CONCRETE

SECTION 033000 CAST-IN-PLACE CONCRETE

DIVISION 5 - METALS

SECTION 055000 METAL FABRICATIONS

DIVISION 6 – WOOD, PLASTICS AND COMPOSITES

SECTION 061000 ROUGH CARPENTRY

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

SECTION 071113 BITUMINOUS DAMPPROOFING

071600 UNDERSLAB VAPOR RETARDERS

079200 JOINT SEALANTS

SPECIFICATION INDEX 000001 - 2

DIVISION 8 – OPENINGS

SECTION 081113 HOLLOW METAL DOORS AND FRAMES

083613 SECTIONAL DOORS

085113 ALUMINUM WINDOWS

087100 DOOR HARDWARE

088000 GLASS AND GLAZING

DIVISION 9 - FINISHES

SECTION 099100 PAINTING

DIVISION 10 - SPECIALTIES

SECTION 105200 FIRE EXTINGUISHERS AND CABINETS

DIVISION 13 - SPECIAL CONSTRUCTION

SECTION 133423 PRE-ENGINEERED METAL BUILDING

DIVISION 26 - ELECTRICAL

SECTION 260500 ELECTRICAL SERVICE

260533 RACEWAYS

262416 PANELBOARDS

262726 WIRING DEVICES

262816 ENCLOSED SWITCHES

265100 LIGHTING

DIVISION 31 - EARTHWORK

SECTION 313215 EXCAVATION, FILL, AND COMPACTION

END OF SECTION 00001

SUMMARY OF WORK 011100-1

SECTION 011100 - SUMMARY OF WORK

PART 1 GENERAL

1.01 DESCRIPTION OF WORK

A. The work consists of designing, furnishing and erecting a 30-foot wide by 142 foot long pre-engineered metal Vehicle Storage building. The work also includes, but is not limited to, site work, earthwork, site electrical, exterior electrical, interior electrical, exterior steel reinforced concrete flatwork, concrete foundations and steel reinforced concrete floor slabs, pre-engineered structural steel frame, metal roofing, metal siding, insulated overhead garage doors, overhead garage door openers, insulated personnel doors, and windows.

B. Contractor shall hire a geotechnical engineering firm to perform a Geotechnical Investigation of the project site and produce a Geotechnical Investigation Report.

That report shall then be used to confirm design assumptions, structural engineering for the structural slab/foundation design assumptions and confirmation to align with the requirements of the selected pre-engineered metal building provider. The Geotechnical Investigation shall be one of the initial duties to be performed by the Contractor and submitted to the Government.

1.02 LOCATION

A. The site of the work is at the Audubon National Wildlife Refuge, in Coleharbor, North Dakota, in McLean County.

B. Contractors are urged to visit the site and become familiar with existing conditions. Failure of the Contractor to ascertain the nature, location, and conditions, which affect the work, will not relieve them from the responsibility for successfully performing the work without additional expense to the Government.

C. Arrangements to inspect the site may be made by contacting the Project Leader, Mr. Todd Frerichs at, (701) 442-5474 ext. 112.

1.03 JOB CONDITIONS

A. The adjacent buildings will be occupied during construction. Maintain access to these buildings and electrical power during construction as much as possible. A portion of this project includes routing new power to the new Vehicle Storage building. Electrical work shall be coordinated with the Project Leader to minimize the impact of power outages.

SUMMARY OF WORK 011100-2

1.04 SURVEY DATA

A. The Contractor shall be responsible for all construction surveys and staking required for performance of all work to the dimensions and grades shown on the drawings.

1.05 PERMITS AND FEES

A. The Contractor shall be responsible for obtaining all necessary local, state, and federal permits and licenses, and payment of related fees, per the Contract Clauses.

1.06 APPLICABLE CODES, STANDARDS AND SPECIFICATIONS

A. All work shall comply with codes and standards applicable to each type of work as listed in individual Sections of these specifications.

1. Materials, applications, and tests specified by reference to published standards of a society, association, code, or other published standards are included in the specifications as if written in their entirety.

2. If there is a conflict between the different design documents, the Contractor is to document that conflict and alert the Government as soon as possible so that a determination of intent can be established. Unless determined differently upon discussion, conflict assumptions are as follows.

3. Where a conflict occurs between referenced documents and the Project Specifications, the Project Specifications govern.

4. Where a conflict occurs between referenced documents, the document containing the most stringent requirements governs.

5. Where referenced documents are not specified by date, the applicable version of the document shall be the version current as of the date established for receipt of bids.

6. Conform to all regulations and statutes of the State of North Dakota and to all Federal regulations, which apply.

1.07 ABBREVIATIONS

A. Abbreviations used throughout the specifications and the organization or document represented:

SUMMARY OF WORK 011100-3

AASHTO American Association of State Highways & Transportation Officials

444 North Capitol Street, N.W., Suite 225 Washington, DC 20001

ACI American Concrete Institute Box 19150 Redford Station Detroit, MI 48219

AISC American Institute of Steel Construction 400 N. Michigan Avenue Chicago, IL 60611

ANSI American National Standards Institute 1430 Broadway New York, NY 10018

ASTM American Society for Testing and Materials 1916 Race Street Philadelphia, PA 19103

AWS American Welding Society, Inc.

550 N.W. LeJeune Road P.O. Box 351040 Miami, FL 33135

CRSI Concrete Reinforcing Steel Institute 933 N. Plum Grove Road Schaumburg, IL 60195

FS Federal Specifications GSA Business Service Center 7th & D Streets S.W.

Washington, DC 20407

OSHA Occupational Safety and Health Administration (U.S. Department of Labor) Government Printing Office Washington, DC 20402

PCA Portland Cement Association

SUMMARY OF WORK 011100-4

5240 Old Orchard Road Skokie, IL 60606

UL Underwriters Laboratories 333 Pfingston Road Northbrook, IL 60062

WWPA Western Wood Products Association (Grading Rules) 1500 Yeon Building Portland, OR 97204

B. Additional abbreviations will be defined as they appear in the specification.

1.08 MANUFACTURER'S SPECIFICATIONS

A. Where manufacturer's products and processes are included in the specifications by reference, they shall be included in these specifications as if written in their entirety.

B. Products and processes included in the specifications shall conform to the manufacturer's latest published specifications.

C. At the request of the Contracting Officer, the Contractor shall provide a sworn affidavit from the manufacturer certifying that material, products, and processes delivered and used on the project meet the specified requirements. This affidavit shall not relieve the Contractor from his responsibility for full compliance with the requirements of the specifications.

1.09 SUBSTITUTIONS

A. The contractor shall provide all equipment, materials, and services as specified or noted on the drawings, unless an approved substitution is obtained.

B. All proposals for substitutions must be submitted in writing to the Contracting

Officer for approval. Products and materials proposed for substitution shall meet or exceed the salient characteristics of the specified items. Substitution proposals shall include all data necessary for thorough comparison with specified item and reason for the proposed substitution. The Contracting Officer’s determination as to whether substitution will be permitted and as to what substitute materials may be used, shall be final and conclusive.

C. For proposed substitutions, the Contractor shall:

SUMMARY OF WORK 011100-5

1. Provide all additional drawings and data for approval as considered necessary by the Contracting Officer.

2. Indicate if the proposed substitution will result in a credit to the Government. If the substitution results in additional costs, pay for the additional labor and materials required because of the substitution.

3. Substitutions shall not be submitted as a regular submittal. Substitutions shall be presented separately and prior to the regular submittal process.

1.10 MEANS AND METHODS

A. Means and methods of construction shall be such as the Contractor may choose;

subject, however, to the Contracting Officer's right to reject means and methods proposed which:

1. Constitute a hazard to the work, persons, or property.

2. Will not produce finished work in accordance with terms of the contract.

3. Are contrary to specified means or methods included in the contract.

B. The right to reject means and methods of the Contractor or subcontractor shall not be construed or interpreted as acceptance of control of means and methods by the Contracting Officer.

C. The Contracting Officer's approval of means and methods or failure to exercise right to reject means and methods shall not relieve the Contractor of the obligation to complete the work required by the contract.

C. Total responsibility for control of all means and methods lies with the Contractor for all work.

1.11 COORDINATION

A. Provide minimum (48) hour advance notice to the Government of electrical outages. For outages in excess of one hour, make arrangements with Government for temporary or alternate means of service.

B. Coordinate work so that station operations will not be restricted and utilities will not be disrupted beyond the end of each workday.

C. Coordinate all work of the project to facilitate orderly progress and proper

SUMMARY OF WORK 011100-6

sequence of work at all times.

D. In the event that other contracts are in progress concurrently with this contract, the

Contractor shall coordinate his work so as not to disrupt progress of other work, and shall cooperate to facilitate orderly progress of all work.

1.12 ENVIRONMENTAL PROTECTION

A. Pollution Control

1. The Contractor shall abate and control all environmental pollution arising from construction activities by complying with all applicable Federal, State, and local laws and regulations concerning environmental pollution control and abatement, as well as the specified requirements in this contract.

a. Compliance with this requirement by subcontractors will be the responsibility of the Contractor.

B. Prevention of Water Pollution

1. The Contractor is responsible for implementing the terms and requirements of the North Dakota storm water discharge permit, as issued by the State under the Department of Health, Environmental Health, by the Environmental Protection Agency (EPA). The Contractor shall apply for and execute all permits as required by the State of North Dakota regarding storm water discharge from the construction site. The Contractor shall submit to the Contracting Officer all permit applications and all approvals from the State of North Dakota. Allow the Government 14 calendar days for review of the application package prior to submission.

2. During construction the Contractor shall comply with all applicable Federal, State, and local laws and regulations concerning the control and abatement of water pollution.

3. The Contractor's construction activities shall be performed by methods that will prevent entrance or accidental spillage of solid matter, contaminants, debris, and other objectionable pollutants and wastes into streams, flowing or dry water-courses, lakes, ponds, and underground water sources. The Contractor shall dispose of all pollutants such as petroleum products, rubbish, cement, concrete, etc., and objectionable material at a jurisdictionally accepted waste management facility.

SUMMARY OF WORK 011100-7

C. Abatement of Air Pollution

1. The Contractor shall comply with applicable Federal, State, and local laws and regulations concerning the prevention and control of air pollution.

2. Construction activities shall be performed in such a manner that air pollution is held to a minimum.

3. Burning of materials, trees and brush, combustible construction materials, and rubbish will not be permitted. Construction debris shall be hauled off the Refuge to an approved landfill area.

D. Fossils and Cultural Materials

1. Should the Contractor discover any fossils or cultural materials during construction operations, such objects shall become the property of the Government. The Contractor shall cease construction operations in the area of the "find," and immediately notify the Facility Director and the Contracting Officer of such discovery. Construction operations may proceed in other areas not affected by this clause. Care shall be exercised by the Contractor so as not to damage or collect fossils or cultural materials uncovered during excavation operations.

2. Failure to comply with this requirement may be considered a violation of the Archeological Resources Protection Act of 1979 as amended.

Destruction of historic and prehistoric sites and/or unauthorized collection of cultural materials can result in criminal and/or civil penalties. Penalties can include fines, prison sentences, and/or confiscation of equipment.

3. If the Contractor obtains borrow materials from a nongovernment source to perform work required under this project, and an existing borrow site is expanded or a new site is opened in order to obtain such materials, the Contractor shall assure that such borrow area disturbance complies with Section 106 of the National Historic Preservation Act.

E. Environmental Litigation

1. Time lost due to work stoppage because of failure of the Contractor to comply with these requirements shall not be the subject of a claim for extension of time or for costs or damages.

END OF SECTION 011100

PAYMENT PROCEDURES 012900 - 1

SECTION 012900 – PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.

1.2 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.

1. Submit the schedule of values to Contracting Officer at earliest possible date but no later than seven days before the date scheduled for submittal of initial Applications for Payment.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Contracting Officer.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Government and Contractor.

C. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. Schedule of values.

2. Contractor's construction schedule (preliminary if not final).

3. Submittal schedule (preliminary if not final).

D. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Written guarantees, warranties, and certificates.

3. Record (As-Built) Drawings

4. All test reports.

END OF SECTION 012900

PROJECT MANAGEMENT AND COORDINATION 013100 - 1

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Coordination drawings.

2. Requests for Information (RFIs).

3. Project meetings.

1.2 DEFINITIONS

A. RFI: Request from Government, Owner, Construction Manager, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.3 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

1.4 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.

Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Provide a construction schedule noting demolition activities, construction activities, deliveries, payments, etc., as needed to convey coordination information to the Contacting Officer, Contacting Officer’s Representative (COR), Government Inspector as well as local staff.

PROJECT MANAGEMENT AND COORDINATION 013100 - 2

2. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

3. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

4. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities as well as any activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the Schedule Of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Pre-installation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

1.5 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Architect indicating

PROJECT MANAGEMENT AND COORDINATION 013100 - 3

proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and electrical Work. Show locations of visible ceiling-mounted devices.

2. Indicate subframing for support of electrical equipment, and related work. Locate components to accommodate layout of light fixtures indicated on Drawings.

3. Structural Penetrations: Indicate penetrations and openings required.

4. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

5. Review: The Government will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility.

1.6 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. The Government will return RFIs as submitted to the Government by other entities controlled by Contractor with no response. RFI’s must come directly from the Contractor.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. RFI number, numbered sequentially.

6. RFI subject.

7. Specification Section number and title and related paragraphs, as appropriate.

8. Drawing number and detail references, as appropriate.

9. Field dimensions and conditions, as appropriate.

PROJECT MANAGEMENT AND COORDINATION 013100 - 4

10. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

11. Contractor's signature.

12. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. RFI Forms: AIA Document G716, or Software-generated form with substantially the same content as indicated above, acceptable to the Government.

D. The Governments Action: The Government will review each RFI, determine action required, and respond. Allow seven working days for the Government’s response for each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day.

1. The following RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for coordination information already indicated in the Contract

Documents.

d. Requests for adjustments in the Contract Time or the Contract Sum.

e. Requests for interpretation of Architect's actions on submittals.

f. Incomplete RFIs or inaccurately prepared RFIs.

g. Request For Information submitted by a sub-contractor to the Contractor.

2. The Government’s action may include a request for additional information, in which case the time for response will date from time of receipt of additional information.

3. The Government’s action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal.

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Contacting Officer and COR in writing within 10 days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly with not less than the following information:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Contacting Officer and COR.

4. RFI number including RFIs that were dropped and not submitted.

5. RFI description.

6. Date the RFI was submitted.

7. Date the Contacting Officer’s response was received.

PROJECT MANAGEMENT AND COORDINATION 013100 - 5

F. On receipt of the Government’s action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify the Government within seven days if Contractor disagrees with response.

1. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate.

2. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.

1.7 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify the U.S. FWS Project Leader, the Contracting officer and the COR of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including the Contracting Officer and the COR, Construction Manager, and Architect, within three days of the meeting.

B. Preconstruction Conference: The Contracting Officer will schedule a preconstruction conference before starting construction, at a time convenient to the Contracting Officer, COR, Facility Director, On-Site Government Inspector and Contractor.

1. Attendees: Authorized representatives of the Contracting Officer, Government Project Manager, U.S. FWS Project Leader, Owner's Commissioning Authority, Construction Manager, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule.

b. Phasing.

c. Critical work sequencing and long-lead items.

d. Designation of key personnel and their duties.

e. Procedures for processing field decisions and Change Orders.

f. Procedures for RFIs.

g. Procedures for testing and inspecting.

h. Procedures for processing Applications for Payment.

PROJECT MANAGEMENT AND COORDINATION 013100 - 6

i. Distribution of the Contract Documents.

j. Submittal procedures.

k. Preparation of record documents.

l. Use of the premises and existing building.

m. Work restrictions.

n. Working hours.

o. Owner's occupancy requirements.

p. Responsibility for temporary facilities and controls.

q. Procedures for moisture and mold control.

r. Procedures for disruptions and shutdowns.

s. Construction waste management and recycling.

t. Parking availability.

u. Office, work, and storage areas.

v. Equipment deliveries and priorities.

w. First aid.

x. Security.

y. Progress cleaning.

3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise the Government of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility problems.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written instructions.

n. Warranty requirements.

o. Compatibility of materials.

PROJECT MANAGEMENT AND COORDINATION 013100 - 7

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of authorities having jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Progress Meetings: Conduct progress meetings at regular intervals as directed by the Contracting officer and/or the COR.

1. Attendees: In addition to representatives of the Government, Construction Manager, and Architect (as applicable), each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting.

Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

PROJECT MANAGEMENT AND COORDINATION 013100 - 8

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site utilization.

8) Temporary facilities and controls.

9) Progress cleaning.

10) Quality and work standards.

11) Status of correction of deficient items.

12) Field observations.

13) Status of RFIs.

14) Status of proposal requests.

15) Pending changes.

16) Status of Change Orders.

17) Pending claims and disputes.

18) Documentation of information for payment requests.

3. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013100

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 1

SECTION 013200 – CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's construction schedule.

2. Construction schedule updating reports.

3. Daily construction reports.

4. Site condition reports.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

1.3 INFORMATIONAL SUBMITTALS

A. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.

1. Submit a working electronic copy of schedule, using software indicated, and labeled to comply with requirements for submittals. Include type of schedule (initial or updated) and date on label.

B. Construction Schedule Updating Reports: Submit with Applications for Payment.

1.4 COORDINATION

A. Coordinate Contractor's construction schedule with the schedule of values, submittal schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from entities involved.

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 2

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Time Frame: Extend schedule from date established from the Notice to Proceed to the date of completion.

B. Activities: Treat each story or separate area as a separate numbered activity for each main element of the Work. Comply with the following:

1. Activity Duration

2. Procurement Activities

3. Submittal Review Time

4. Punch List and Final Completion: Include not more than 15 days for completion of punch list items and final completion.

C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

1. Phasing: Arrange list of activities on schedule by phase.

2. Work under More Than One Contract: Include a separate activity for each contract.

3. Work by Owner: Include a separate activity for each portion of the Work performed by Owner.

4. Work Restrictions: Show the effect of the following items on the schedule:

a. Coordination with existing construction.

b. Limitations of continued occupancies.

c. Uninterruptible services.

d. Partial occupancy before Substantial Completion.

e. Use of premises restrictions.

f. Provisions for future construction.

g. Seasonal variations.

h. Environmental control.

5. Work Stages: Indicate important stages of construction for each major portion of the work.

6. Other constraints not listed.

D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and final completion and the following interim milestones.

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 3

1. Insert milestones not indicated elsewhere.

END OF SECTION 013200

PHOTOGRAPHIC DOCUMENTATION 013233 - 1

SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for the following:

1. Preconstruction photographs.

2. Periodic construction photographs.

B. Related Requirements:

1. Section 017700 "Closeout Procedures" for submitting photographic documentation as Project Record Documents at Project closeout.

1.2 INFORMATIONAL SUBMITTALS

A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include same information as corresponding photographic documentation.

B. Digital Photographs: Submit unaltered, original, full-size image files within 5 days of taking photographs.

1. Digital Camera: Minimum sensor resolution of 8 megapixels.

2. Digital photographs to be submitted in the order in which they were taken with the photograph “name” as given by the device used to take to photo.

3. Identification: Provide the following information with each image description in file metadata tag:

a. Date and time photograph was taken

b. Unique photograph number

1.3 QUALITY ASSURANCE

A. Photographs to be clear, focused, level, have proper exposure settings (not over exposed or under exposed), and clearly show and document the subject matter. Detail photographs (close-ups) to be preceded by a larger overall view of the area being documented.

PHOTOGRAPHIC DOCUMENTATION 013233 - 2

1.4 USAGE RIGHTS

A. Obtain and transfer copyright usage rights from photographer to Owner for unlimited reproduction of photographic documentation.

PART 2 - PRODUCTS

2.1 PHOTOGRAPHIC MEDIA

A. Digital Images: Provide images in JPG format, with minimum size of 8 megapixels.

PART 3 - EXECUTION

3.1 CONSTRUCTION PHOTOGRAPHS

A. Photographer: Engage a qualified photographer to take construction photographs.

Photographer need not be a professional photographer, but an individual familiar with and able to produce clear, focused photographs of the subject area with good reference points.

B. General: Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.

1. Maintain key plan with each set of construction photographs that identifies each photographic location.

C. Digital Images: Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.

1. Date and Time: Include date and time in file name for each image.

2. Field Office Images: Maintain one set of images accessible in the field office at

Project site, available at all times for reference. Identify images in the same manner as those submitted to the Government.

D. Preconstruction Photographs: Before commencement of excavation, commencement of demolition and starting construction, take photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Government.

1. Flag excavation areas before taking construction photographs.

2. Take minimum of 10 photographs, or as needed, to show existing conditions adjacent to property before starting the Work.

3. Take minimum of 10 photographs, or as needed, of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.

PHOTOGRAPHIC DOCUMENTATION 013233 - 3

E. Periodic Construction Photographs: Take photographs as needed to fully document the construction progress. Select vantage points to show status of construction and progress since last photographs were taken. Try to retake progress photos from the same vantage points when possible so as to show relative construction progress.

F. Final Completion Construction Photographs: Take color photographs after date of Substantial Completion for submission as Project Record Documents. The Government will inform photographer of desired vantage points.

G. Additional Photographs: The Government may request photographs in addition to periodic photographs specified as needed to verify progress or to verify work completion accuracy.

1. Three days' notice will be given, where feasible.

2. In emergency situations, take additional photographs within 24 hours of request.

3. Circumstances that could require additional photographs include, but are not limited to, the following:

a. Special events planned at Project site.

b. Immediate follow-up when on-site events result in construction damage or losses.

c. Photographs to be taken at fabrication locations away from Project site. These photographs are not subject to unit prices or unit-cost allowances.

d. Substantial Completion of a major phase or component of the Work.

e. Extra record photographs at time of final acceptance.

f. Owner's request for special publicity photographs.

END OF SECTION 013233

SUBMITTAL PROCEDURES 013300 - 1

SECTION 013300 – SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Architect's Contracting Officer responsive action.

B. Informational Submittals: Written and graphic information and physical samples that do not require Architect's Contracting Officer responsive action. Submittals may be rejected for not complying with requirements.

1.3 ACTION SUBMITTALS

A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by the Contracting Officer and additional time for handling and reviewing submittals required by those corrections.

1.4 SUBMITTAL ADMINISTRATIVE REQUIREMENTS

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

SUBMITTAL PROCEDURES 013300 - 2

B. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer receipt of submittal.

No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 10 working days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Contracting Officer will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 10 working days for review of each resubmittal.

C. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. Name file with submittal number or other unique identifier, including revision identifier.

a. File name shall use station initials (CMR) and a sequential submittal number followed by the Specification Section number (CMR-005-061000).

Resubmittals shall include an alphabetic suffix after the sequential submittal number (e.g., CMR-005A-061000).

2. Transmittal Form for Electronic Submittals: Use electronic form provided by Contracting Officer.

D. Paper Submittals: Place a permanent label or title block on each submittal item for identification.

1. Number system for paper submittals shall conform to the system as noted in C-1-a.

above.

2. Transmittal for Paper Submittals: Assemble each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form.

a. Transmittal Form for Paper Submittals: Use FWS transmittal form.

E. Options: Identify options requiring selection by the Government.

F. Deviations: Identify deviations from the Contract Documents on submittals.

G. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

SUBMITTAL PROCEDURES 013300 - 3

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from Contracting Officer’s action stamp.

H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

I. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Contracting Officer’s action stamp.

PART 2 - PRODUCTS

2.1 SUBMITTAL PROCEDURES

A. General Electronic Submittal Procedure Requirements:

1. Submit electronic submittals via email as PDF electronic files. PDF files shall use a cover sheet as provided by the Government (refer to attached sample). This standard cover sheet is to be used for each submittal and includes general submittal information, dates, submittal number, brief description of the submitted information, etc., as well as placed for signatures and review and acceptance designations.

2. Contracting Officer’s Representative, through the Contracting Officer, will return annotated file by e-mail and/or standard mail. Annotate and retain one copy of file as an electronic Project record document file.

B. General Paper Submittal Procedure Requirements:

1. Action Submittals: Submit four (4) paper copies of each submittal unless otherwise indicated. Contracting Officer’s Representative through the Contracting Officer will return three (3) copies.

2. Informational Submittals: Submit three (3) paper copies of each submittal unless otherwise indicated. Contracting Officer will not return copies.

3. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

SUBMITTAL PROCEDURES 013300 - 4

a. Provide a digital signature with digital certificate on electronically-submitted certificates and certifications where indicated.

b. Provide a notarized statement on original paper copy certificates and certifications where indicated.

C. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams showing factory-installed wiring.

b. Printed performance curves.

c. Operational range diagrams.

d. Clearances required to other construction, if not indicated on accompanying

Shop Drawings.

5. Submit Product Data before or concurrent with Samples.

6. Submit Product Data in the following format:

a. PDF electronic file.

b. Four (4) paper copies of Product Data unless otherwise indicated. Contracting

Officer’s Representative through the Contracting Officer will return two (2) copies.

D. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data unless submittal based on drawing files is otherwise permitted.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

SUBMITTAL PROCEDURES 013300 - 5

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional engineer if specified.

2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 11 by 17 inches, but no larger than 30 by 42 inches.

3. Submit Shop Drawings in the following format:

a. PDF electronic file.

b. Four (4) opaque copies of each submittal. Contracting Officer’s

Representative through the Contracting Officer will retain two (2) copies;

remainder will be returned.

E. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample.

b. Product name and name of manufacturer.

c. Sample source.

d. Number and title of applicable Specification Section.

3. For projects where electronic submittals are required, provide corresponding electronic submittal of Sample transmittal, digital image file illustrating Sample characteristics, and identification information for record.

4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.

b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

SUBMITTAL PROCEDURES…