SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040435667

FWS, DIVISION OF CONTRACTING AND GE

LAKE PLAZA NORTH

134 UNION BOULEVARD

LAKEWOOD CO 80228-1807

F06

FWS, DIVISION OF CONTRACTING

LAKE PLAZA NORTH

134 UNION BOULEVARD

LAKEWOOD, CO 80228-1807

Ryan Cope 303-236-4349

19-012 x 06/12/2019

140F0619R0020

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

CONSTRUCT METAL VEHICLE STORAGE BUILDING AT AUDUBON NATIONAL WILDLIFE REFUGE, ND

NAICS 236220 - COMMERICAL AND INSTITUTIONAL BUILDING CONSTRUCTION

SET-ASIDE: TOTAL SMALL BUSINESS

PROJECT MAGNITUDE: BETWEEN $500,000 AND $1,000,000

TECHNICAL/SPECIFICATIONS:

1. SPECIFICATIONS, DATED 6/6/2019, 170 PAGES

2. DRAWINGS, DATED 6/7/2019, 10 PAGES

3. PROJECT SUBMITTAL LIST, 3 PAGES

4. WAGE DETERMINATION - ND190023, DATED 2/15/2019, 5 PAGES

WORK UNDER THIS CONTRACT:

The contractor shall provide all labor, materials, and equipment necessary to construct a metal vehicle storage building at the Audubon National Wildlife Refuge in accordance with the attached specifications and drawings.

Continued ...

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 120 calendar days and complete it within ________________ ________________ calendar days after receiving

FAR 52.211-10

07/24/2019

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

FWS, DIVISION OF CONTRACTING AND GE

LAKE PLAZA NORTH

134 UNION BOULEVARD

LAKEWOOD CO 80228-1807

F06

Ryan Cope

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 68

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140F0619R0020

LOCATION AND INSPECTION OF THE SITE:

The jobsite is located on the Audubon National

Wildlife Refuge. The address is 3275 11th Street

NW Coleharbor, ND 58531. Prospective bidders are encouraged to visit the site and become familiar with existing site conditions. Prospective bidders must contact the Project Leader (Todd

Frerichs) at todd_frerichs@fws.gov, office number

(701) 442-5474 ext. 112, or cell number (701)

460-0576 to arrange for a site visit. Site visits shall be scheduled at least 48 hours in advance.

Failure of the contractor to ascertain the nature, location, and conditions which affect the work will not relieve the contractor from the responsibility for successfully performing the work without additional expense to the

Government. All questions regarding the subject requirement shall be submitted by 3:00 PM MT on

July 10, 2019 via email to the Contracting

Officer at ryan_cope@fws.gov. Please include the solicitation number, company name, address, telephone number, email, and contact name on any correspondence.

PROSPECTIVE OFFERORS MUST BE REGISTERED WITH THE

SYSTEM OF AWARD MANAGEMENT AT:

http://www.sam.gov/portal/public/SAM

Legacy Doc #: FWS

Delivery: 120 Days After Notice to Proceed

Delivery Location Code: 0008350129

FWS AUDUBON NWR

3275 11TH STREET NW

COLEHARBOR ND 58531-9419 US

Period of Performance: 09/02/2019 to 12/31/2019

00010 CONSTRUCT METAL VEHICLE STORAGE BUILDING AT

AUDUBON NATIONAL WILDLIFE REFUGE, ND

The contractor shall provide all labor, materials, and equipment necessary to construct a metal vehicle storage building at the Audubon

National Wildlife Refuge in accordance with the attached specifications and drawings.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Document No.

140F0619R0020

Document Title

CONSTRUCT METAL VEHICLE STORAGE BUILDING AT THE

AUDUBON NATIONAL WILDLIFE REFUGE, ND

4 | P a g e

TABLE OF CONTENTS

B – Bid Schedule

C - Description/Specifications

E - Inspection and Acceptance

F - Deliveries or Performance

G - Contract Administration Data

I - Contract Clauses

J - List of Documents, Exhibits and Other Attachments

K - Representations, Certifications, and Other Statements of Bidders

L - Instructions,Conditions, and Notices to Bidders

M - Evaluation Factors For Award……………………………………………...…….65

Document Title

5 | P a g e

B – Bid Schedule

Bid Schedule Vehicle Storage Building

Audubon NWR (19-012)

ITEM

NO. DESCRIPTION QTY UNIT AMOUNT

1. Geotechnical Inves. & Report 1 Lump Sum $_____________

2. Mobilization/Demob 1 Lump Sum $_____________

3. Site Prep & Excavation 1 Lump Sum $_____________

4. Exterior Electrical Supply 1 Lump Sum $_____________

5. Foundations & Footings 1 Lump Sum $_____________

6. Interior Slab on Grade 1 Lump Sum $_____________

7. Exterior Concrete Apron 1 Lump Sum $_____________

8. Sidewalks & Stoops 1 Lump Sum $_____________

9. Bollards 1 Lump Sum $_____________

10. Metal Building 1 Lump Sum $_____________

11. Overhead Garage Doors 1 Lump Sum $_____________

12. Openers Ovhd Garage Doors 1 Lump Sum $_____________

13. Interior Elec/Lighting 1 Lump Sum $_____________

14. Exterior Elec./Lighting 1 Lump Sum $_____________

15. Windows 1 Lump Sum $_____________

16. Personnel Metal Doors/Frames 1 Lump Sum $_____________

17. Personnel Metal Doors Hardware 1 Lump Sum $_____________

18. Finish Grading & Site Work 1 Lump Sum $_____________

19. Construction Equipment Rental 1 Lump Sum $_____________

Subtotal: $____________

21. Contractor’s Overhead _____% $____________

23. Contractor’s Insurance _____% $____________

25. Profit _____% $____________

26. Bonding _____% $____________

27. North Dakota Gross Receipts Tax _____% $____________

Subtotal: $____________

Total: $______________

Document Title

6 | P a g e

C - Description/Specifications

The Specifications and Drawings are attached (See Section J)

E - Inspection and Acceptance

52.236-27 Site Visit (Construction). (FEB 1995) - Alternate I. (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Name: Todd Frerichs

Telephone: (701) 442-5474 ext. 112 or (701) 460-0576

Email: todd_frerichs@fws.gov

(End of provision)

52.246-12 -- Inspection of Construction. (AUG 1996)

(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not --

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

Document Title

7 | P a g e

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price.

The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may --

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately.

Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

Document Title

8 | P a g e

(End of Clause)

52.246-21 -- Warranty of Construction. (MAR 1994)

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor’s expense any damage to Government-owned or controlled real or personal property, when that damage is the result of --

(1) The Contractor’s failure to conform to contract requirements; or

(2) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor’s warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall --

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.

Document Title

9 | P a g e

(h) In the event the Contractor’s warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor’s, manufacturer’s, or supplier’s warranty.

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.

(j) This warranty shall not limit the Government’s rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.

(End of Clause)

F - Deliveries or Performance

52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the Notice To Proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days after the date the contractor receives the Notice To Proceed.

The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.211-12 Liquidated Damages – Construction. (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $190.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.211-13 -- Time Extensions. (SEP 2000)

Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered.

The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.

Document Title

10 | P a g e

(End of clause)

G - Contract Administration Data

Contracting Officer (CO) responsible for this contract:

Ryan Cope U.S. Fish and Wildlife Service Acquisitions & Property Operations 134 Union Blvd.

Lakewood, CO 80228 Telephone #: 303-236-4349 E-mail: ryan_cope@fws.gov

Engineering Project Manager is:

Wilbert Ortega U.S. Fish and Wildlife Service Division of Engineering 134 Union Blvd.

Lakewood, CO 80228 Telephone #: 303-236-5410 E-mail: wilber_ortega@fws.gov

Project Leader & On-site Inspector:

Todd Frerichs U.S. Fish and Wildlife Service Audubon National Wildlife Refuge 3275 11th Street NW Coleharbor, ND 58531 Telephone #: 701-442-5474 x 112 E-mail: todd_frerichs@fws.gov

Only a duly authorized Contracting Officer may change or modify the terms of this contract. All such actions must be formalized by a proper contractual document executed by the Contracting Officer.

All correspondence and submittals pertaining to the contract MUST be addressed to the Contracting Officer

Prohibition on Text Messaging and Using Electronic Equipment Supplied by the Government while Driving. (OCT 2009)

Executive Order 13513 , Federal Leadership On Reducing Text Messaging While Driving , was signed by President Barack Obama on October 1, 2009 (Ref:

http://edocket.access.gpo.gov/2009/pdf/E9-24203.pdf). This Executive Order introduces mailto:todd_frerichs@fws.gov

Document Title

11 | P a g e a Federal Government-wide prohibition on the use of text messaging while driving on official business or while using Government-supplied equipment. Additional guidance enforcing the ban will be issued at a later date. In the meantime, please adopt and enforce policies that immediately bans text messaging while driving company-owned or rented vehicles, government owned or leased vehicles, or while driving privately owned vehicles while on official government business or when performing any work for or on behalf of the government.

(End of DOI clause)

Electronic Invoicing and Payment Requirements - Invoice Processing Platform

(IPP). (APR 2013)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

A copy of the invoice must be submitted to the Contracting Officer (CO) and the Contracting Officer’s Representative (COR) for approval prior to submission into IPP.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of local clause)

1452.204-70 Release of Claims—Department of the Interior. (JUL 1996)

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this

Document Title

12 | P a g e contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

1452.215-70 Examination of Records by the Department of the Interior. (APR 1984)

For purposes of the Examination of Records by the Comptroller General clause of this contract (FAR 52.215–2(d)), the Secretary of the Interior, the Inspector General, and their duly authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States.

1452.215-71 Use and Disclosure of Proposal Information-Department of the Interior. (APR 1984)

(a) Definitions. For the purposes of this provision and the Freedom of Information Act (5 U.S.C. 552), the following terms shall have the meaning set forth below: (1) “Trade Secret” means an unpatented, secret, commercially valuable plan, appliance, formula, or process, which is used for making, preparing, compounding, treating or processing articles or materials which are trade commodities. (2) “Confidential commercial or financial information” means any business information (other than trade secrets) which is exempt from the mandatory disclosure requirement of the Freedom of Information Act, 5 U.S.C. 552. Exemptions from mandatory disclosure which may be applicable to business information contained in proposals include exemption (4), which covers “commercial and financial information obtained from a person and privileged or confidential,” and exemption (9), which covers “geological and geophysical information, including maps, concerning wells.”

(b) If the offeror, or its subcontractor(s), believes that the proposal contains trade secrets or confidential commercial or financial information exempt from disclosure under the Freedom of Information Act, (5 U.S.C. 552), the cover page of each copy of the proposal shall be marked with the following legend:

“The information specifically identified on pages ______ of this proposal constitutes trade secrets or confidential commercial and financial information which the offeror believes to be exempt from disclosure under the Freedom of Information Act. The offeror requests that this information not be disclosed to the public, except as may be required by law. The offeror also requests that this information not be used in whole or part by the government for any purpose other than to evaluate the proposal, except that if a contract is awarded to the offeror as a result of or in connection with the submission of the proposal, the Government shall have the right to use the information to the extent provided in the contract.”

(c) The offeror shall also specifically identify trade secret information and confidential commercial and financial information on the pages of the proposal on which it appears and shall mark each such page with the following legend:

“This page contains trade secrets or confidential commercial and financial information which the offeror believes to be exempt from disclosure under the Freedom of

Document Title

13 | P a g e

Information Act and which is subject to the legend contained on the cover page of this proposal.”

(d) Information in a proposal identified by an offeror as trade secret information or confidential commercial and financial information shall be used by the Government only for the purpose of evaluating the proposal, except that (i) if a contract is awarded to the offeror as a result of or in connection with submission of the proposal, the Government shall have the right to use the information as provided in the contract, and (ii) if the same information is obtained from another source without restriction it may be used without restriction.

(e) If a request under the Freedom of Information Act seeks access to information in a proposal identified as trade secret information or confidential commercial and financial information, full consideration will be given to the offeror's view that the information constitutes trade secrets or confidential commercial or financial information. The offeror will also be promptly notified of the request and given an opportunity to provide additional evidence and argument in support of its position, unless administratively unfeasible to do so. If it is determined that information claimed by the offeror to be trade secret information or confidential commercial or financial information is not exempt from disclosure under the Freedom of Information Act, the offeror will be notified of this determination prior to disclosure of the information.

(f) The Government assumes no liability for the disclosure or use of information contained in a proposal if not marked in accordance with paragraphs (b) and (c) of this provision. If a request under the Freedom of Information Act is made for information in a proposal not marked in accordance with paragraphs (b) and (c) of this provision, the offeror concerned shall be promptly notified of the request and given an opportunity to provide its position to the Government. However, failure of an offeror to mark information contained in a proposal as trade secret information or confidential commercial or financial information will be treated by the Government as evidence that the information is not exempt from disclosure under the Freedom of Information Act, absent a showing that the failure to mark was due to unusual or extenuating circumstances, such as a showing that the offeror had intended to mark, but that markings were omitted from the offeror's proposal due to clerical error.

I - Contract Clauses

52.202-1 Definitions. (NOV 2013)

52.203-3 Gratuities. (APR 1984)

52.203-5 Covenant Against Contingent Fees. (MAY 2014)

52.203-6 Restrictions on Subcontractor Sales to the Government. (SEP 2006)

52.203-7 Anti-Kickback Procedures. (MAY 2014)

Document Title

14 | P a g e

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT 2010)

52.203-16 Preventing Personal Conflicts of Interest. (DEC 2011)

52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights. (APR 2014)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper.

(MAY 2011)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards.

(OCT 2018)

52.204-13 System for Award Management Maintenance. (OCT 2018)

52.204-14 Service Contract Reporting Requirements. (OCT 2016)

52.204-16 Commercial and Government Entity Code Reporting. (JUL 2016)

52.204-18 Commercial and Government Entity Code Maintenance. (JUL 2016)

52.204-22 Alternative Line Item Proposal. (JAN 2017)

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015)

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters. (OCT 2018)

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015)

52.211-6 Brand Name or Equal. (AUG 1999)

52.211-18 Variation in Estimated Quantity. (APR 1984)

52.215-1 Instructions to Offerors—Competitive Acquisition. (JAN 2017)

52.215-2 Audit and Records—Negotiation. (OCT 2010)

52.215-10 Price Reduction for Defective Certified Cost or Pricing Data. (AUG 2011)

52.215-12 Subcontractor Certified Cost or Pricing Data. (OCT 2010)

52.215-15 Pension Adjustments and Asset Reversions. (OCT 2010) https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1138393

Document Title

15 | P a g e

52.215-17 Waiver of Facilities Capital Cost of Money. (OCT 1997)

52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions. (JUL 2005)

52.215-19 Notification of Ownership Changes. (OCT 1997)

52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data—Modifications. (OCT 2010)

52.219-8 Utilization of Small Business Concerns. (OCT 2018)

52.219-14 Limitations on Subcontracting. (JAN 2017)

52.222-3 Convict Labor. (JUN 2003)

52.222-4 Contract Work Hours and Safety Standards - Overtime Compensation.

(MAY 2018)

52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work.

(MAY 2014)

52.222-6 Construction Wage Rate Requirements. (AUG 2018)

52.222-7 Withholding of Funds. (MAY 2014)

52.222-8 Payrolls and Basic Records. (MAY 2014)

52.222-9 Apprentices and Trainees. (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)

52.222-11 Subcontracts (Labor Standards). (MAY 2014)

52.222-12 Contract Termination – Debarment. (MAY 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)

52.222-14 Disputes Concerning Labor Standards. (FEB 1988)

52.222-15 Certification of Eligibility. (MAY 2014)

52.222-21 Prohibition of Segregated Facilities. (APR 2015)

52.222-22 Previous Contracts and Compliance Reports. (FEB 1999)

52.222-26 Equal Opportunity. (SEP 2016)

52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)

Document Title

16 | P a g e

52.222-35 Equal Opportunity for Veterans. (OCT 2015)

52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014)

52.222-40 Notification of Employee Rights Under the National Labor Relations Act.

(DEC 2010)

52.222-50 Combating Trafficking in Persons. (MAR 2015)

52.222-54 Employment Eligibility Verification. (OCT 2015)

52.222-55 Minimum Wages under Executive Order 13658. (DEC 2015)

52.222-62 Paid Sick Leave Under Executive Order 13706. (JAN 2017)

52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. (SEP 2013)

52.223-3 Hazardous Material Identification and Material Safety Data. (JAN 1997)

52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)

52.223-6 Drug-Free Workplace. (MAY 2001)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving

.(AUG 2011)

52.224-1 Privacy Act Notification. (APR 1984)

52.224-2 Privacy Act. (APR 1984)

52.224-3 Privacy Training. (JAN 2017)

52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)

52.227-1 Authorization and Consent. (DEC 2007)

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement.

(DEC 2007)

52.227-4 Patent Indemnity - Construction Contracts. (DEC 2007)

52.227-17 Rights in Data – Special Works. (DEC 2007)

52.228-2 Additional Bond Security. (OCT 1997)

52.228-5 Insurance - Work on a Government Installation. (JAN 1997)

52.228-11 Pledges of Assets. (AUG 2018)

52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)

Document Title

17 | P a g e

52.229-3 Federal, State, and Local Taxes. (FEB 2013)

52.232-17 Interest. (MAY 2014)

52.232-18 Availability of Funds. (APR 1984)

52.232-23 Assignment of Claims. (MAY 2014)

52.232-27 Prompt Payment for Construction Contracts. (JAN 2017)

52.232-39 Unenforceability of Unauthorized Obligations. (JUN 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013)

52.233-1 Disputes. (MAY 2014) – Alternate I. (DEC 1991)

52.233-3 Protest after Award. (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)

52.242-13 Bankruptcy. (JUL 1995)

52.242-14 Suspension of Work. (APR 1984)

52.243-4 Changes. (JUN 2007)

52.244-6 Subcontracts for Commercial Items. (OCT 2018)

52.248-3 Value Engineering – Construction. (OCT 2015)

52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)

- Alternate I. (SEP 1996)

52.249-10 Default (Fixed-Price Construction). (APR 1984)

52.252-5 Authorized Deviations in Provisions. (APR 1984)

52.253-1 Computer Generated Forms. (JAN 1991)

52.216-1 Type of Contract. (APR 1984)

The Government contemplates award of a Firm Fixed-Price contract resulting from this solicitation.

(End of provision)

52.219-28 Post-Award Small Business Program Re-representation. (JUL 2013)

(a) Definitions. As used in this clause-

Document Title

18 | P a g e

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is "not dominant in its field of operation" when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall re-represent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts-

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall re-represent its size status in accordance with the size standard in effect at the time of this re-representation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

Document Title

19 | P a g e

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following re-representation and submit it to the contracting office, along with the contract number and the date on which the re-representation was completed:

The Contractor represents that it ___ is, ___ is not a small business concern under NAICS Code [insert NAICS Code] assigned to contract number [insert contract number].

(Contractor to sign and date and insert authorized signer's name and title).

(End of clause)

52.219-6 -- Notice of Total Small Business Set-Aside. (NOV 2011)

(a) Definition. “Small business concern,” as used in this clause, means a concern, including its affiliates that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the size standards in this solicitation.

(b) Applicability. This clause applies only to--

(1) Contracts that have been totally set aside or reserved for small business concerns; and

(2) Orders set aside for small business concerns under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F).*

(c) General.

(1) Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.

(2) Any award resulting from this solicitation will be made to a small business concern.

Document Title

20 | P a g e

(d) Agreement. A small business concern submitting an offer in its own name shall furnish, in performing the contract, only end items manufactured or produced by small business concerns in the United States or its outlying areas. If this procurement is processed under simplified acquisition procedures and the total amount of this contract does not exceed $25,000, a small business concern may furnish the product of any domestic firm. This paragraph does not apply to construction or service contracts.

(End of Clause)

52.225-9 Buy American - Construction Materials. (MAY 2014)

(a) Definitions. As used in this clause-

Commercially available off-the-shelf (COTS) item- (1) Means any item of supply (including construction material) that is-

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means-

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph

(1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Document Title

21 | P a g e

Domestic construction material means-

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if-

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which non-availability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

Foreign construction material means a construction material other than a domestic construction material.

United States means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

Document Title

22 | P a g e

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of Payments Program.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description

Unit of Measure Quantity Price

(Dollars)*

Item 1:

Document Title

23 | P a g e

Foreign construction material ________ ________ ________

Domestic construction material ________ ________ ________

Item 2:

Foreign construction material ________ ________ ________

Domestic construction material ________ ________ ________

* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).

List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.

Include other applicable supporting information.

(End of clause)

52.225-10 Notice of Buy American Requirement - Construction Materials. (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American- Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

Document Title

24 | P a g e

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers. (1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception…