Attachment_4_Questions_and_Answers_0001.pdf

PDF 282 KB Posted

Attached to
SC- SANDHILLS NWR-GATE INSTALL
Solicitation number
140F0122R0118
Issued by

View the file

Other files

File Type Posted
Sol_140F0122R0118_Amd_0001.pdf PDF
Sol_140F0122R0118.pdf PDF
Attachment_1_Bid_Schedule.pdf PDF
Attachment_2_Statement_of_Work.pdf PDF
Attachment_3_WDOL_Davis_Bacon_Wages.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers - 140F0122R0118

1. SOW is silent concerning the AC electrical power required for the gate operator.

A. Power is available for the gate operator; power source is within 5 feet.

2. On the SF 1442 in the solicitation, it states that we are required to provide a payment/performance bond. However, this project is anticipated to be under $25,000 and usually projects over $35,000 requires a payment and performance bond and not under $35,000. Therefore, I wanted to get confirmation that the we are to provide/furnish the payment and performance bond.

A. Bond not required for projects under $35,000.