B12 Q and A 12.8.2020_0002.pdf
PDF 45 KB Posted
- Attached to
- HI-JAMES CAMPBELL NWR URGENT PUMP REPAIR
- Solicitation number
- 140F0121Q0009
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140F0121Q0009_Amd_0002.pdf | ||
| Sol_140F0121Q0009_Amd_0001.pdf | ||
| DOL Wage Determination.pdf | ||
| A04 SOW_JCNWR_PUMP_TRASH_RACKS.pdf | ||
| Sol_140F0121Q0009.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140F0121Q0009 James Campbell National Wildlife Refuge
Questions and Answers (Q&A’s)
12/08/2020
The SOW reads that the contractor shall test run the 40hp pump for proper operation.
1) Can you confirm if a procedure for proper pump operation will be provided and/or what is the contractor to confirm?
Answer: No proper pump operation will be provided. The contractor is to confirm that when the pump is turned on to its operating position no debris from the sump is sucked up into the pump.
2) Can you confirm that the pump can be started and stopped at the building on site?
Answer: Yes, the pump can be started and stopped at the building site.