B12 Q and A 12.8.2020_0002.pdf

PDF 45 KB Posted

Attached to
HI-JAMES CAMPBELL NWR URGENT PUMP REPAIR
Solicitation number
140F0121Q0009
Issued by

View the file

Other files

File Type Posted
Sol_140F0121Q0009_Amd_0002.pdf PDF
Sol_140F0121Q0009_Amd_0001.pdf PDF
DOL Wage Determination.pdf PDF
A04 SOW_JCNWR_PUMP_TRASH_RACKS.pdf PDF
Sol_140F0121Q0009.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140F0121Q0009 James Campbell National Wildlife Refuge

Questions and Answers (Q&A’s)

12/08/2020

The SOW reads that the contractor shall test run the 40hp pump for proper operation.

1) Can you confirm if a procedure for proper pump operation will be provided and/or what is the contractor to confirm?

Answer: No proper pump operation will be provided. The contractor is to confirm that when the pump is turned on to its operating position no debris from the sump is sucked up into the pump.

2) Can you confirm that the pump can be started and stopped at the building on site?

Answer: Yes, the pump can be started and stopped at the building site.