B09_Amendment_02_Q_A_0002.docx
DOCX document 15 KB Posted
- Attached to
- MUD GAS SEPARATOR Federal contract opportunity
- Solicitation number
- 140E0122Q0023
About this file
This document contains questions and answers related to solicitation number 140E0122Q0023 from the Department of the Interior Bureau of Safety and Environmental Enforcement for a mud gas separator. The solicitation seeks proposals to design and evaluate mud gas separators for a range of well conditions including high temperatures and pressures exceeding 300 degrees Fahrenheit and 15,000 psi. Respondents are asked to consider factors such as hydrogen sulfide and carbon dioxide corrosion and their effect on degradation of vessels and piping over time. The technical volume of proposals is limited to 30 pages excluding resumes and past performance information. An employee non-disclosure agreement is required to be submitted upon award but not with the initial quotation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140E0122Q0023_Amd_0002.pdf | ||
| Sol_140E0122Q0023_Amd_0001.pdf | ||
| Sol_140E0122Q0023.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ: 140E0122Q0023 Page 2 of 2 Amendment 0002
Questions and Answers on RFQ 140E0122Q0023
Question 1. Is there any budget ceiling for this application?
Answer: Although there is Government’s Independent Cost Estimate (IGCE), there is no budget ceiling for this solicitation. The IGCE cannot be released to the prospective offerors.
Question 2. To design/evaluate MGS for different well conditions, we will develop/evaluate MGS performance on HTHP conditions. Do you have any suggested testing temperatures and pressures? We assume exceeding 300 F and 15000 psi.
Answer: BSEE would like to evaluate well conditions for abroad range of typical GOM wells including HTHP wells with consideration to water depths. It would say there are some reservoirs with parameters that may exceed 15k and 300 F.
Question 3. With respect to the MGS degradation, do you think evaluating the H2S and CO2 effect on MGS is a good direction?
Answer: H2S and CO2 with respect to how they impact degradation such as corrosion and erosion over time of the vessel and piping over time would be something BSEE would like to consider. Anything determined to affect operating parameters and the integrity of the MGS over time should be considered.
Question 4. Application mentions 30 pages limit for technical volume, does that exclude cover page and references?
Answer: Cover page and references are included in the page limitations. Only resumes and past performance are excluded from the page limitations.
Question 5. I am assuming attachment 2 is not required to be submitted by quotation-please confirm.
Answer: Attachment 2. Contractor Employee Non-Disclosure Agreement shall be signed and submitted once awarded.