This is a Request for Proposal (RFP) for design-build services to rehabilitate approximately 20,700 linear feet of shoreline and seawall infrastructure at East Potomac Park in Washington, D.C. The Department of the Interior's National Park Service is the requesting agency, with the Interior Business Center's Acquisition Services Directorate managing the solicitation. This is an unrestricted, firm-fixed-price design-build contract under FAR 36.101-2 using a two-phase selection process. The NAICS code is 237990 (Other Heavy and Civil Engineering Construction), the product service code is Y1PZ, and the small business size standard is $45 million. All construction work, including cleanup, must be completed within 51 months of award. The project encompasses shoreline protection along both the Potomac River and Washington Channel, with a Z-panel wall section extending from the inlet to the middle of the southbound 395 bridge and a stamped concrete wall section extending from the middle of the southbound 395 bridge to the 14th Street bridge abutment on the Washington Channel side.

Phase One responses are due by the date specified in SF-1442 Block 13a via email, with up to three qualified contractors selected to proceed to Phase Two with responses due within 30 days of notification. The contract includes three contract line items: design (CD & DD), construction of Z-panel wall, and construction of stamped concrete wall. Key personnel requirements include a project manager, jobsite superintendent, A/E project manager, landscape architect, arborist, and turf manager, with substitution restrictions during the first 120 calendar days. Contractors must demonstrate bonding capacity of at least $322 million and comply with Davis-Bacon wage requirements. A/E design services are capped at 6 percent of estimated construction costs. The Government will evaluate Phase One proposals on General Technical Approach, Technical Qualifications, and Past Performance (price not considered). Phase Two evaluation will use equal-weight non-price factors (Technical Solution, Schedule, Small Business Participation) and price using a best-value tradeoff approach, with non-price factors significantly more important than price. Liquidated damages are assessed at $2,023 per calendar day of delay.

View the file

Other files

File Type Posted
Attachment_B_-_EPP_MAP_1.pdf PDF
Attachment_A_-_NAMA_326209_EPP_POR_093026_draft_1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Document No.

140D0427RP001

Document Title NAMA 326209 East Potomac Seawalls Design Build

P a g e | 1

SECTION A – SOLICITATION / CONTRACT FORM

(1) Issuing Agency:

Department of the Interior (DOI), Interior Business Center (IBC), Acquisition Services Directorate (AQD)

(2) Requesting Agency:

DOI National Park Service (NPS)

(3) Contract Information:

AQD is a Federal Franchise Fund Contracting Office that operates under the authority of the Government Management Reform Act, as amended. AQD provides contracting support to all Federal Agencies and the Department of Defense. AQD Procurement will handle solicitation, award, contract administration, and invoice payments for this requirement.

This Request for Proposal (RFP) is issued in accordance with the Two-Phase Design-Build Selection Procedures in FAR 36.101-2 and FAR 15, as deviated. This solicitation is unrestricted.

NAICS Code: 237990 – Other Heavy and Civil Engineering Construction Product Service Code: Y1PZ – Construction of Other Non-Building Facilities SB Size Standard: $45M

SECTION B – PRICE SCHEDULE

This section is only applicable to offerors in Phase 2.

The anticipated Contract Line-Item Number (CLIN) structure is in the table below. This may change based on actual pricing proposal. Reference section L for the instructions and requirements for the submission of the detailed price proposal.

The total firm-fixed price for this project is: $___

CLIN Description Total Price 0001 Design (CD & DD) 0002 Construction of Z-Panel Wall 0003 Construction Stamped Concrete Wall

Total

SECTION C – SPECIFICATIONS / DRAWINGS

This requirement is for the design and construction to rehabilitee approximately 20,700 linear feet of shoreline and seawall infrastructure at East Potomac Park (EPP or Park). The project area includes the shoreline along both the Potomac River and Washington Channel and encompasses associated improvements required to provide long-term shoreline protection, improve drainage performance, preserve public access and protect Park resources.

DRAFT

Solicitation

Document No.

Document Title NAMA 326209 East Potomac Seawalls Design Build

P a g e | 2

Please see Attachment A – NAMA 326209_ EPP POR_09-30-26_Final for all specifications and drawings.

NOTE: Please ignore any language in the Program of Requirements (POR) that pertains to living shorelines. There will be no living shorelines as part of this project. The extent of the use of the Z-panel wall and the stamped concrete wall are outlined below:

• Z-panel: inlet to middle of South bound 395 bridge

• Stamped Concrete: middle of South bound 395 bridge to 14th st bridge abutment on

Washington Channel Side

• Reference Attachment B – EPP MAP for a map of East Potomac Park that shows which section will be a Z-panel wall and which will be a stamped concrete wall.

Refer to Section J for a list of all attachments.

SECTION D – PACKING AND MARKING

All required submittals shall be delivered to the Primary Contracting Officer’s Representative (COR) listed in Section G herein. All required submittals shall contain the following markings, if applicable:

1. Name and address of the contractor

2. Contract number

3. Description of item submitted

SECTION E – INSPECTION AND ACCEPTANCE

52.246-11 Higher Level Contract Quality Requirement (Dec 2014) 52.246-12 Inspection of Construction (Aug 1996)

SECTION F – DELIVERIES OR PERFORMANCE

Project Location: The construction will be completed at the location specified in the POR in East Potomac Park, Washington, D.C.

Delivery Date: All construction work, including cleanup, shall be completed within 51 months of award.

FAR 52.236-15 Schedules for Construction Contracts (Deviated) (Jan 2026) FAR 52.242-14 Suspension of Work (Apr 1984)

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 3

SECTION G – CONTRACT ADMINISTRATION DATA

In no event shall any understanding, agreement, change, or other matter that deviates from the terms of this RFP between the contractor and a person other than the IBC AQD Contracting Officer (CO) be effective or binding upon the Government. All such actions must be formalized by a proper contractual document executed by the Contracting Officer (CO).

(a) The CO is Ericka Graham, 571-560-2329, ericka_graham@ibc.doi.gov

(b) Contracting Officer’s Representative (COR): Provided upon award

(c) Contractor’s Information: TBD

(d) All contract administration associated will be performed by the CO and COR unless otherwise designated. Changes in the CO or COR will be made by written modification.

(e) The Contractor shall establish processes and assign appropriate resources to effectively administer the requirement. Duties include but are not limited to: responding to Government requests for contractual actions in a timely fashion; having a single point of contact between the Government and Contractor personnel assigned to support requirements; and assigning work effort and maintaining proper/accurate time keeping records of personnel assigned to work on the requirement.

DIAR 1452.201-70 Authorities and Delegations (SEP 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 4 memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the

COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

(End of clause)

DIAR 1452.204-70 Release of Claims - Department of the Interior (JUL 1996)

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

Contractor Performance Assessment Reporting System (December 2015)

1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2) The past performance evaluation process is a totally paperless process using CPARS.

CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in CPARS for Government use in evaluating past performance as part of a source selection action.

https://www.acquisition.gov/far/part-42#FAR_42_1502 https://www.acquisition.gov/far/subpart-42.15

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 5

3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.

4) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

5) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

a) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.

b) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

c) All information provided should be reviewed for accuracy prior to submission.

d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in CPARS marked as “Pending” with or without comments and whether or not it has been closed.

f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

6) The following guidelines apply concerning your use of the past performance evaluation:

a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

6) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The

DRAFT

https://www.cpars.gov/ https://www.cpars.csd.disa.mil/ https://www.cpars.csd.disa.mil/ https://www.cpars.gov/

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 6 meeting will be held in person or via telephone or other means during your 60-day review period.

8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

(End of Local Clause) Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP) (February 2021)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following information (at a minimum) is required in the IPP invoice:

1. Contractor Name, Address, Contact Information

2. Invoice Date and Invoice Number

3. Contract Number

4. CLIN/Item number of deliverable

5. Description of Deliverable, Work, or Services Performed

6. Quantity and Firm Fixed Price of Deliverable

7. Date Deliverable was Provided to the Government for Inspection and Accepted

8. Period of Performance/Milestones Dates Applicable

A Release of Claims is required IAW 1452.204-70 Release of Claims, after completion of work and prior to final payment.

The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 – 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause) https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 7

SECTION H – SPECIAL CONTRACT REQUIREMENTS

(1) KEY PERSONNEL

The Contractor shall assign to this contract the following Key Personnel:

• Project Manager

• Job-site Superintendent

• A/E Project Manager

• Landscape Architect

• Arborist

• Turfrass Manager

*The final award may have additional or alternate Key Personnel as a result of the proposed positions.

During the first 120 calendar days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 30 calendar day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 calendar days prior to making any permanent substitutions.

The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.

(2) SMALL BUSINESS PARTICIPATION

(a) Definitions. As used in this clause—“Subcontract” means any agreement (other than one involving an employer-employee relationship) entered into by a Federal Government prime Contractor calling for supplies or services required for performance of the contract.

(b) The contractor shall ensure participation of the total contract value to the greatest extent practicable is performed by Small Business. This requirement may be met by:

i. Self-performance by small business prime contractors and / or

ii. Subcontracting portions of the work to small businesses

(c) Prior to submittal of their initial invoice the contractor shall submit a small business participation plan that demonstrates compliance with the requirements noted in (b) above. The plan shall include:

(i) A listing of anticipated subcontracts to small businesses including the following information for each subcontract:

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 8

a. Subcontractor name

b. Description of supply or service

c. Subcontract dollar value

(ii) If the prime contractor is a small business then also list the dollar value of the work the prime contractor will self-perform.

(iii)Total dollar value for all small business subcontracts + dollar value of work to be self-performed by small business prime contractors.

(iv) The total prime contract dollar value.

(v) Small business participation expressed as a percentage of the total contract value contracted to small businesses and self-performed by small business prime contractors.

(d) Failure of the contractor to meet the minimum required small business participation shall be reflected in the Government’s evaluation of the contractor’s performance upon contract completion.

(3) FEE LIMITATION

The six percent (6%) fee limitation (fee is limited to six percent (6%) of estimated construction costs) for A/E services applies only to the actual preparation of final designs, drawings, and specifications. Any services which are not integral part of the production of drawings and specifications may be excluded for the fee limitation.

(4) GOVERNMENT-FURNISHED SPECIFICATIONS AND DRAWINGS FOR

CONSTRUCTION

This is to clarify that contract clause, "Specifications and Drawings for Construction," refers to any specifications and drawings or design or design criteria furnished in the Request for Proposal (RFP). The term "specifications" refers to the design criteria or scope of work, in addition to any attached specifications.

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall—

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 9

(1) Large-scale drawings shall govern over small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(End of Special Requirement)

(5) DESIGN BUILD CONTRACT ORDER OF PRECEDENCE

(a) Design-Build Contract Order of Precedence. The contract includes the standard contract clauses and schedules current at the time of contract award. The contract entails the Solicitation in its entirety, including all drawings, cuts, and illustrations, and any amendments, and the successful offeror’s accepted proposal. The contract constitutes and defines the entire agreement between the Contractor and the Government. No documentation shall be omitted which in any way bears upon the terms of that agreement.

In the event of conflict or inconsistency between any portion of this contract, precedence shall be given in the following order:

(1) Betterments: Any portions of the accepted proposal which both conform to and exceed the requirements of the Solicitation.

(2) The requirements of the Solicitation. (See also FAR 52.236-21, Specifications and Drawings for Construction)

(3) All other elements of the accepted proposal.

(4) Any design products including, but not limited to, plans, specifications, engineering studies and analyses, shop drawings, equipment installation drawings, etc. These are "deliverables" under the contract and are not part of the contract itself. Design products must conform to all provisions of the contract, in the order of precedence herein.

(b) Personnel, subcontractors, and outside associates or consultants. In connection with this contract, any in-house personnel, subcontractors, and outside associates or consultants will be limited to individuals or firms that were specifically identified in the Contractor's accepted proposal. The Contractor shall obtain the Contracting Officer's written consent before making any substitution for these designated in-house personnel, subcontractors, associates, or consultants. If the Contractor proposes a substitution, it shall submit the same type of information that was submitted in the accepted proposal to the Contracting Officer for evaluation and approval. The level of qualifications and experience submitted in the accepted proposal or that required by the Solicitation, whichever is greater, is the minimum standard for any substitution.

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 10

(c) Responsibility of the Contractor for Design. The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all designs, drawings, specifications, and other non-construction services furnished by the Contractor under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiency in its designs, drawings, specifications, and other non-construction services and perform any necessary rework or modifications, including any damage to real or personal property, resulting from the design error or omission.

(1) The standard of care for all design services performed under this agreement shall be the care and skill ordinarily used by members of the architectural or engineering professions practicing under similar conditions at the same time and locality.

Notwithstanding the above, in the event that the contract specifies that portions of the Work be performed in accordance with a performance standard, the design services shall be performed so as to achieve such standards.

(2) Neither the Government's review, approval or acceptance of, nor payment for, the services required under this contract, shall be construed to operate as a waiver of any rights under this contract or of any cause of action arising out of the performance of this contract. The Contractor shall be and remain liable to the Government in accordance with applicable law for all damages to the Government caused by the Contractor's negligent performance of any of these services furnished under this contract

(3) The rights and remedies of the Government provided for under this contract are in addition to any other rights and remedies provided by law.

(4) If the Contractor is comprised of more than one legal entity, each entity shall be jointly and severally liable hereunder.

(d) Contractor's Role during the Design Process. The Contractor's construction management key personnel shall be actively involved during the design process to effectively integrate the design and construction requirements of this contract. In addition to the typical required construction activities, the Contractor's involvement includes, but is not limited to actions such as: integrating the design schedule into the Master Schedule to maximize the effectiveness of fast-tracking design and construction (within the limits allowed in the contract), ensuring constructability and economy of the design, integrating the shop drawing and installation drawing process into the design, executing the material and equipment acquisition programs to meet critical schedules, effectively interfacing the design and construction quality control (QC) management programs with the design QC program, and maintaining and providing the design team with accurate, up-to-date redline and as-built documentation for eventual submission as Record Drawings.. The Contractor shall require and manage the active involvement of key trade subcontractors in the above activities.

(e) Deviating from the Accepted Design. The Contractor must obtain the approval of the Designer of Record and the Government's concurrence, in the form of supplemental agreement to the contract, for any Contractor-proposed revision to the professionally stamped-and-sealed and Government-reviewed final design that has been released for

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 11

Construction before proceeding with the revision. The Government reserves the right to disapprove such a revision.

(1) The Government reserves the right to non-concur with any revision to the final design that has been released for construction, including those which may impact furniture, furnishings, equipment selections or operations decisions that were made, based on the reviewed design.

(2) Any Contractor-proposed revision to the design which deviates from the contract requirements (i.e., the Request for Proposal (RFP) and the accepted proposal), will require a bilateral modification (e.g. supplemental agreement) to the contract before any work commences.

(3) Unless the Government initiates a change to the contract requirements, or the Government determines that the Government furnished design criteria are incorrect and must be revised, any Contractor initiated proposed change to the contract requirements, which results in additional cost, shall strictly be at the Contractor's expense.

(4) The Contractor shall track all approved revisions to the reviewed and accepted design and shall incorporate them into the as-built design documentation, in accordance with agreed procedures. The Designer of Record shall document its professional concurrence on the as-builts for any revisions in the stamped and sealed drawings and specifications.

(f) Value Engineering after Award. In reference to Federal Acquisition Regulation (FAR)clause

52.248-3, Value Engineering - Construction, the Government may refuse to entertain a "Value Engineering Change Proposal" (VECP) for those "performance oriented" aspects of the Solicitation documents which were addressed in the Contractor's accepted contract proposal and which were evaluated in competition with other offerors for award of this contract.

(1) The Government may consider a VECP for those "prescriptive" aspects of the Solicitation documents, not addressed in the Contractor's accepted contract proposal or addressed but evaluated only for minimum conformance with the Solicitation requirements.

(2) For purposes of this clause, the term "performance oriented" refers to those aspects of the design criteria or other contract requirements, which allow the offeror or Contractor certain latitude, choice of and flexibility to propose in its accepted proposal a choice of design, technical approach, design solution, construction approach or other approach to fulfill the contract requirements. Such requirements generally tend to be expressed in terms of functions to be performed, performance required or essential physical characteristics, without dictating a specific process or specific design solution for achieving the desired result.

(3) In contrast, for purposes of this clause, the term "prescriptive" refers to those aspects of the design criteria or other Solicitation requirements wherein the Government expressed the design solution or other requirements in terms of specific material, approaches, systems, and/or processes to be used. Prescriptive aspects typically allow the offerors little or no freedom in the choice of design approach, materials, Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 12 fabrication techniques, methods of installation, or any other approach to fulfill the contract requirements.

(g) Government Re-Use of Design. In conjunction with the 52.227-17 RIGHTS IN DATA –

SPECIAL WORKS, (DEC 2007), the Government will not ask for additional originals or copies of the design works after the Contractor provides all required design documentation and record drawing documentation under the instant contract. Further, if the Government uses the design for other projects without additional compensation to the Contractor for re-use, the Government releases the Contractor from liability in the design on the other projects, due to defects in the design that are not the result of fraud, gross mistake as amounts to fraud, gross negligence or intentional misrepresentation.

(6) WARRANTY OF DESIGN (FIRM FIXED PRICE DESIGN-BUILD CONTRACT)

(a) The Contractor warrants that the design shall be performed in accordance with the Contract requirements. Design and design related construction not conforming to the Contract requirements shall be corrected at no additional cost to the Government. The standard of care for design is defined in paragraph (b) of Special Contract Requirement

“RESPONSIBILITY OF THE CONTRACTOR FOR DESIGN.”

(b) The period of this warranty shall commence upon final completion and the Government’s acceptance of the work, or in the case of the Government’s beneficial occupancy of all or part of the work for its convenience, prior to final completion and acceptance, at the time of such occupancy.

(c) This design warranty shall be effective from the above event through the Statue of Limitations and Statute of Repose, as applicable to the state that the project is located in.

(d) The rights and remedies of the Government provided for under this clause are in addition to any other rights and remedies provided in this contract or by law.

(7) RESPONSIBILITY OF THE ARCHITECT-ENGINEER CONTRACTOR

(a) The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all designs, drawings, specifications, and other services furnished by the Contractor under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its designs, drawings, specifications, and other services.

(b) Neither the Government’s review, approval or acceptance of, nor payment for, the services required under this contract shall be construed to operate as a waiver of any rights under this contract or of any cause of action arising out of the performance of this contract, and the Contractor shall be and remain liable to the Government in accordance with applicable law for all damages to the Government caused by the Contractor’s negligent performance of any of the services furnished under this contract.

(c) The rights and remedies of the Government provided for under this contract are in addition to any other rights and remedies provided by law.

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 13

(d) If the Contractor is comprised of more than one legal entity, each such entity shall be jointly and severally liable hereunder.

(8) WORK OVERSIGHT IN ARCHITECT-ENGINEER CONTRACTS

The extent and character of the work to be done by the Contractor shall be subject to the general oversight, supervision, direction, control, and approval of the Contracting Officer.

(End of Special Requirement)

(9) REQUIREMENTS FOR REGISTRATION OF DESIGNERS

Architects or engineers registered to practice in the particular professional field involved in a State, the District of Columbia, or an outlying area of the United States the state where the construction work shall be performed shall prepare or review and approve the design of architectural, structural, mechanical, electrical, civil, or other architectural and engineering features of the work.

SECTION I – CONTRACT CLAUSES

52.252-2 Clauses Incorporated By Reference (Feb 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.acquisition.gov/far/part-52

(End of clause)

CLAUSES INCORPORATED BY REFERENCE

Clause Title Date 52.202-1 Definitions Jun 2020 52.203-3 Gratuities Apr 1984 52.203-5 Covenant Against Contingent Fees May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government Jun 2020 52.203-7 Anti-Kickback Procedures Jun 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or

Improper Activity May 2014

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity May 2014 52.203-12 Limitation on Payments to Influence Certain Federal Transactions Jun 2020 52.203-13 Contractor Code of Business Ethics and Conduct Nov 2021 52.203-14 Display of Hotline Poster(s) Nov 2021 52.203-17 Contractor Employee Whistleblower Rights Nov 2023 52.203-19

Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

Jan 2017

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 14

52.204-9 Personal Identity Verification of Contractor Personnel Jan 2011 52.204-10 Reporting Executive Compensation and First-Tier Subcontract

Awards (Deviation) Mar 2026

52.204-13 System for Award Management Maintenance (Deviation) Mar 2026 52.204-19 Incorporation by Reference of Representations and Certifications Dec 2014 52.209-6 Protecting the Government’s Interest When Subcontracting with

Contractors Debarred, Suspended, or Proposed for Debarment (Deviation)

May 2026

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Deviation)

May 2026

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Deviation)

May 2026

52.210-1 Market Research (Deviation) Jul 2025 52.211-13 Time Extensions Sep 2000 52.215-2 Audit and Records—Negotiation (Deviation) Oct 2026 52.215-10 Price Reduction for Defective Certified Cost or Pricing Data Aug 2011 52.215-12 Subcontractor Certified Cost or Pricing Data Oct 2025 52.215-15 Pension Adjustments and Asset Reversions (Deviation) Oct 2026 52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits

(PRB) Other Than Pensions (Deviation) Oct 2026

52.215-19 Notification of Ownership Changes (Deviation) Oct 2026 52.215-20 Requirements for Certified Cost or Pricing Data and Data Other

Than Certified Cost or Pricing Data (Deviation) Oct 2026

52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data—Modifications (Deviation)

Oct 2026

52.219-8 Utilization of Small Business Concerns (Deviation) Jan 2026 52.219-9 Small Business Subcontracting Plan (Deviation) Feb 2026 52.219-28 Post-Award Small Business Program Rerepresentation

(Deviation) Jan 2026

52.222-3 Convict Labor Jun 2003 52.222-4 Contract Work Hours and Safety Standards —Overtime

Compensation (Deviation) May 2026

52.222-6 Construction Wage Rate Requirements (Deviation) May 2026 52.222-7 Withholding of Funds (Deviation) May 2026 52.222-8 Payrolls and Basic Records (Deviation) May 2026 52.222-9 Apprentices and Trainees (Deviation) May 2026 52.222-10 Compliance with Copeland Act Requirements (Deviation) May 2026 52.222-11 Subcontracts (Labor Standards) (Deviation) May 2026 52.222-12 Contract Termination—Debarment May 2014 52.222-13 Compliance with Construction Wage Rate Requirements and

Related Regulations May 2014

52.222-14 Disputes Concerning Labor Standards (Deviation) May 2026 52.222-15 Certification of Eligibility May 2014 52.222-35 Equal Opportunity for Veterans (Deviation) May 2026

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 15

52.222-36 Equal Opportunity for Workers with Disabilities (Deviation) May 2026 52.222-37 Employment Reports on Veterans (Deviation) May 2026 52.222-40 Notification of Employee Rights Under the National Labor

Relations Act (Deviation) May 2026

52.222-50 Combating Trafficking in Persons (Deviation) May 2026 52.222-54 Employment Eligibility Verification (Deviation) May 2026 52.222-55 Minimum Wages for Contractor Workers Under Executive Order

14026 (Deviation) May 2026

52.222-62 Paid Sick Leave Under Executive Order 13706 (Deviation) May 2026 52.222-90 Addressing DEI Discrimination by Federal Contractors

(Deviation) May 2026

52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (Deviation)

May 2026

52.223-5 Pollution Prevention & Right-To-Know Information May 2024 52.223-23 Sustainable Products and Services (Deviated) May 2026 52.225-11 Buy American—Construction Materials under Trade Agreements

(Deviation) Oct 2026

52.226-7 Drug-Free Workplace May 2024 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While

Driving May 2024

52.227-1 Authorization and Consent Jun 2020 52.227-2 Notice and Assistance Regarding Patent and Copyright

Infringement Jun 2020

52.227-4 Patent Indemnity—Construction Contracts Dec 2007 52.227-17 Rights in Data—Special Works Dec 2007 52.228-2 Additional Bond Security Oct 1997 52.228-5 Insurance – Work on a Government Installation Jan 1997 52.228-11 Individual Surety-Pledges of Assets Feb 2021 52.228-12 Prospective Subcontractor Requests for Bonds Dec 2022 52.228-14 Irrevocable Letter of Credit Nov 2014 52.228-15 Performance and Payment Bonds—Construction Jun 2020 52.229-3 Federal, State, and Local Taxes (Deviation) Oct 2025 52.232-5 Payments under Fixed-Price Construction Contracts May 2014 52.232-16 Progress Payments (Deviation) Oct 2026 52.232-17 Interest May 2014 52.232-23 Assignment of Claims May 2014 52.232-27 Prompt Payment for Construction Contracts Jan 2017 52.232-33 Payment by Electronic Funds Transfer—System for Award

Management Oct 2018

52.232-39 Unenforceability of Unauthorized Obligations Jun 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors Mar 2023

52.233-1 Disputes (Deviation) Oct 2026 52.233-3 Protest after Award (Deviation) Oct 2026

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 16

52.233-4 Applicable Law for Breach of Contract Claim (Deviation) Oct 2026 52.236-2 Differing Site Conditions (Deviation) Jan 2026 52.236-3 Site Investigation and Conditions Affecting the Work (Deviation) Jan 2026 52.236-5 Material and Workmanship (Deviation) Jan 2026 52.236-6 Superintendence by the Contractor (Deviation) Jan 2026 52.236-7 Permits and Responsibilities (Deviation) Jan 2026 52.236-8 Other Contracts (Deviation) Jan 2026 52.236-9 Protection of Government Buildings, Equipment, and Vegetation

(Deviation) Jan 2026

52.236-10 Operations and Storage Areas (Deviation) Jan 2026 52.236-11 Use and Possession Prior to Completion (Deviation) Jan 2026 52.236-12 Cleaning Up (Deviation) Jan 2026 52.236-13 Accident Prevention (Deviation) Jan 2026 52.236-14 Availability and Use of Utility Services (Deviation) Jan 2026 52.236-15 Schedules for Construction Contracts Jan 2026 52.236-17 Layout of Work Jan 2026 52.236-21 Specifications and Drawings for Construction Jan 2026 52.240-91 Security Prohibitions and Exclusions (Deviation) Mar 2026 52.242-5 Payments to Small Business Subcontractors Jan 2017 52.242-13 Bankruptcy Jul 1995 52.243-4 Changes (Deviation) Oct 2025 52.243-5 Changes and Changed Conditions (Deviation) Oct 2025 52.244-5 Competition in Subcontracting Aug 2024 52.244-6 Subcontracts for Commercial Products and Commercial Services

(Deviation) May 2026

52.246-21 Warranty of Construction Mar 1994 52.246-26 Reporting Nonconfirming Items Aug 2024 52.248-3 Value Engineering – Construction Oct 2025 52.249-2 Termination for Convenience of the Government (Fixed-Price)

Alternate I Sep 1996

52.249-10 Default (Fixed-Price Construction) Apr 1984 52.253-1 Computer Generated Forms (Deviation) May 2026

Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,023 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 17

52.252-6 Authorized Deviations in Clauses (Nov 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

(b) The use in this solicitation or contract of any Department of Interior Acquisition Regulation (Sec. 205(c), 63 Stat. 390, 40 U.S.C. 486(c); and 5 U.S.C. 301) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

DIAR Clauses

1452.201-70 Authorities and Delegations (Sep 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 18

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the

COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

1452.203-70 Restrictions on Endorsements (Jul 1996)

The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.

(End of clause)

1452.204-70 Release of Claims (Jul 1996)

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

(End of clause)

1452.215-70 Examination of Records by the Department of the Interior (Apr 1984)

For purposes of the Examination of Records by the Comptroller General clause of this contract (FAR 52.215-1), the Secretary of the Interior, the Inspector General, and their duly authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States.

(End of clause)

1452.228-70 Liability Insurance – Department of the Interior (JUL 1996)

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 19 policy shall be the Contractor and the United States of America. The amount of the insurance shall be not less than as follows:

$100,000 each person $500,000 each occurrence $1,000,000 property damage

Employer's Liability: $100,000

General Liability: $500,000

Automobile liability:

$200,000 Per person $500,000 Per occurrence for bodily injury (other than passenger liability) $20,000 Per occurrence for property damage

Architect-Engineer:

$200,000 each person $500,000 each occurrence $20,000 property damage

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

(End of clause)

SECTION J – ATTACHMENTS

The following attachments are incorporated into this solicitation and the subsequent contract.

Attachment Description Date (if applicable)

A NAMA 326209_ EPP POR 09/30/2026

B EPP Map

C NAMA 326209 EPP DB Q&A

D Past Performance Questionnaire E Subcontracting Plan Template F Davis-Bacon Wage Determination DC20260001, mod 6 08/24/2026

Document Title NAMA 326209 East Potomac Seawalls Design

P a g e | 20

SECTION K – REPRESENTATIONS, CERTIFICATION, AND OTHER STATEMENTS

OF OFFERORS

In accordance with FAR 52.102(c), provisions marked with an asterisk (*) must be completed by the offeror and submitted with the proposal only if it is not completed in SAM. Full text of the provisions can be found at: FAR Overhaul - Part 52 | Acquisition.GOV

Provision Title Date 52.203-2 Certificate of Independent Price Determination* Apr 1985 52.203-11 Certification and Disclosure Regarding Payments to Influence

Certain Federal Transactions Sep 2024

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements— Representation

Jan 2017

52.204-5 Women-Owned Business (Other Than Small Business)* Oct 2014 52.209-2 Prohibition on Contracting with Inverted Domestic

Corporations—Representation (Deviated) May 2026

52.209-5 Certification Regarding Responsibility Matters (Deviated)* May 2026 52.209-7 Information Regarding Responsibility Matters (Deviated) May 2026 52.209-11 Representation by Corporations Regarding Delinquent Tax

Liability or a Felony Conviction under any Federal Law (Deviated)*

May 2026

52.219-1 Small Business Program Representations (Deviated)* Jan 2026 52.240-90 Security Prohibitions and Exclusions Representations and

Certifications (Deviated) Mar 2026

Please complete the following provision certification and submit them with the offer:

FAR 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (Deviation) (May 2026)

(a) This provision does not apply to acquisitions at or below the simplified acquisition threshold or to acquisitions of commercial products and…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .