Sol_140D0426Q0878.pdf

PDF 430 KB Posted

Attached to
Cobblestone Ramp Repair Federal contract opportunity
Solicitation number
140D0426Q0878
Issued by
Department of the Interior Departmental Offices Interior Business Center

About this file

This is a Request for Quote (RFQ) for construction work to repair historic cobblestone ramps at the Stewart Lee Udall Building (Department of the Interior headquarters) located at 1849 C Street, NW, Washington, DC 20240.

The solicitation is a total small business set-aside under NAICS Code 237310 (Highway, Street, and Bridge Construction) with a $45 million business size standard. The work involves removing, cleaning, resetting, and repointing historic cobblestone paver ramps at four separate locations (Ramps A, B, C, and D), totaling approximately 4,173 square feet. Ramp A covers 845 square feet, Ramp B covers 845 square feet, Ramp C covers 1,379 square feet, and Ramp D covers 1,104 square feet. Contractors must provide separate pricing for each ramp and are required to attend a mandatory site visit on September 1, 2026 at 2:00 PM. Quotes are due September 10, 2026 at 10:00 AM EST and must remain valid for 10 days after submission. The contract will be firm fixed price (FFP) with a 12-month completion deadline. Work includes protecting historic features, documenting existing conditions, preparing surfaces, resetting cobblestones in original patterns using approved mortar bedding, repointing joints, repairing sealant joints, and providing a one-year workmanship warranty. The contractor's masonry supervisor must demonstrate at least five years of experience in historic masonry or cobblestone restoration. Payment will be made through the Invoice Processing Platform (IPP) system, and a Release of Claims is required before final payment. The Contracting Officer is Xanthe Otterstedt (xanthe_otterstedt@ibc.doi.gov; 703-914-3719). General Decision Number DC20260002 Modification 3 (Davis-Bacon wage determination effective May 18, 2026) applies to this contract.

View the file

Other files for this federal contract opportunity

Other files attached to Cobblestone Ramp Repair, newest first.
File Type Posted
DOI_HSR_Update_FINAL_DRAFT_2018_06_25_(high_res)_0002.pdf PDF
Sol_140D0426Q0878_Amd_0002.pdf PDF
140D0426Q0878_Cobblestone_Ramp_Repair_Responses_Final_0002.pdf PDF
Sol_140D0426Q0878_Amd_0001.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

NEGOTIATED (RFP) REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF

SEALED BID (IFB) INVITATION FOR BID

9. FOR

INFORMATION CALL

PAGES

140D0426Q0878

Interior Business Center, AQD Division 2 /Branch 3 381 Elden St Suite 2000A Herndon VA 20170

D23

Kelly Ozah 0000000000

08/26/2026

09/10/2026

0 365

The Contractor shall provide all labor, materials, equipment, and supervision necessary to remove, clean, reset, and repoint the historic cobblestone ramp surfaces at Ramps A, B, C, and D at the Udall

Main Building in accordance with the Performance Work Statement (PWS).

1 51

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Continued...

AMENDMENT

NUMBER

DATE.

Interior Business Center, AQD Division 2 /Branch 3 381 Elden St Suite 2000A Herndon VA 20170

D23

Xanthe Otterstedt

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

Period of Performance: 09/23/2026 to

09/22/2027

00001 1 EARamp A

Product/Service Code: Z2LB

Product/Service Description: REPAIR OR

ALTERATION

OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS

Period of Performance: 09/23/2026 to

03/23/2027

00002 1 EARamp B

Product/Service Code: Z2LB

Product/Service Description: REPAIR OR

ALTERATION

OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS

Period of Performance: 09/23/2026 to

03/23/2027

00003 1 EARamp C

Product/Service Code: Z2LB

Product/Service Description: REPAIR OR

ALTERATION

OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS

Period of Performance: 09/23/2026 to

03/23/2027

00004 1 EARamp D

Product/Service Code: Z2LB

Product/Service Description: REPAIR OR

ALTERATION

OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS

Period of Performance: 09/23/2026 to

03/23/2027

Solicitation No.

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 3 of 26

REF: Solicitation 140D0426Q0878

(i) This is a Request for Quote (RFQ) for construction work located at the Stewart Lee Udall Building, HQ for the Department of the Interior, 1849 C Street, NW, Washington DC 20240.

(ii) This requirement is a total small business set-aside under North American Industry Classification System (NAICS) Code 237310 – Highway, Street, and Bridge Construction with a business size standard of $45 million. Federal Supply Code (FSC) Z2LB – Repair or Alteration of Highways, Roads, Streets, Bridges, and Railways. This solicitation is issued under Revolutionary FAR Overhaul (RFO) Part 12, Acquisition of Commercial Products and Commercial Services.

(iii) This is a combined synopsis/solicitation. This announcement constitutes the only solicitation;

quotes are being requested and a separate written solicitation will not be issued. The Government will award a firm fixed price contract from this solicitation to the responsible vendor whose quote, conforming to the solicitation, will be most advantageous to the Government, price and other factors considered. The Government intends to evaluate all timely quotes received from eligible vendors on a lowest price technically acceptable (LPTA) basis. The Government intends to evaluate quotations and award a contract without discussions with quoters. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary.

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 4 of 26

Section B - Supplies or Services and Prices/Costs

The following is the associated Contract Line Item Number (CLIN):

CLIN Description TYPE Quantity Amount

0001 Ramp A

FFP

(Firm Fixed Price)

1 x job $

0002 Ramp B FFP 1 x job $ 0003 Ramp C FFP 1 x job $ 0004 Ramp D FFP 1 x job $

Total $

Sub description: The contractor shall furnish all required elements, including design, labor, materials, equipment, tools, supervision, and any other items necessary to complete the construction work Stewart Lee Udall Building, HQ for the Department of the Interior, 1849 C Street, NW. The construction alteration work is located in Washington DC 20240. Work shall be in strict compliance with the Statement of Work, all specifications, drawings/diagrams, terms, conditions, clauses, and all other provisions contained herein.

The contract price includes all applicable Federal, State, and local taxes and duties. It is the Contractor's responsibility to include in its price quote any other costs that may be required if the contractor intends to recover such costs under the contract. The Government will not modify the contract after award to compensate the contractor for any other specific costs that may not have been included in the award price.

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 5 of 26

Section C – Description / Specifications / Statement of Work

PERFORMANCE WORK STATEMENT (PWS)

Cobblestone Ramp Repairs Stewart Lee Udall Department of the Interior Building

1.0 Background

The Stewart Lee Udall Department of the Interior Building (Main Interior Building), constructed in 1936, is a historic federal facility requiring preservation-sensitive maintenance. The building contains historic cobblestone paver ramps that have become loose, displaced, and deteriorated due to traffic loading and weather exposure.

2.0 Purpose

The Contractor shall provide all labor, materials, equipment, and supervision necessary to remove, clean, reset, and repoint the historic cobblestone ramp surfaces at Ramps A, B, C, and D.

3.0 Scope of Work

The Contractor shall remove, clean, reset, and repoint the historic cobblestone paving throughout Ramps A, B, C, and/or D, totaling approximately 4,173 square feet. The government may order services for any or all the ramps based on the availability of funding.

CLIN 0001: Ramp A: 845 square feet

CLIN 0002: Ramp B: 845 square feet

CLIN 0003: Ramp C: 1,379 square feet

CLIN 0004: Ramp D: 1,104 square feet

Quantities are approximate. Offerors shall verify all dimensions, quantities, access limitations, and existing conditions during the mandatory site visit before submitting a proposal. The Contractor shall provide separate pricing for each ramp.

Work shall include, but not limited to, the following:

• Protect adjacent historic features and document existing ramp conditions and cobblestone patterns with photographs and dimensioned sketches prior to beginning work.

• The contractor will remove pavers to expose the concrete topping slab, using methods which will not cause damage to the slab which is to remain in existing condition.

• Cobble stones shall be removed, cleaned, stored and reinstalled in same design pattern as originally installed. Take before and after photographs for historic documentation.

• The contractor will clean and prepare the surface of the topping slab to ensure proper adhesion of the approved mortar-bedding system. Reset cobblestones in the original historic pattern using approved mortar bedding.

• Repoint joints with an approved mortar compatible with the existing historic materials in color, texture, composition, strength, and joint profile.

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 6 of 26

• Repair sealant joints between curbs, walls, and pavers using an approved compatible sealant.

• Cure mortar in accordance with the manufacturer's recommendations.

• Remove all construction debris and leave the work area clean upon completion.

4.0 Historic Preservation Requirements

All work shall comply with:

• Secretary of the Interior’s Standards for the Treatment of Historic Properties.

• National Historic Preservation Act of 1966, as amended, and its implementing regulations (36

CFR 800)

• Historic Structure Report (HSR) for the Department of the Interior -Udall Building DC0020ZZ

• ADM 1022.3: GSA Procedures for Historic Properties

• Applicable historic masonry preservation practices.

The Contractor shall protect adjacent historic features. Mortar shall be compatible with existing historic materials and shall not be harder than the existing masonry. Type S or Type M mortar shall not be used unless approved by the Contracting Officer.

The Contractor shall submit product data, safety data sheets, manufacturer’s instructions, proposed mix designs, color and texture samples, and physical samples for all bedding mortar, pointing mortar, sealants, cleaners, and related materials.

The Contractor shall construct a field mock-up at a location designated by the COR. The mock-up shall demonstrate cobblestone cleaning, bedding, resetting, alignment, joint preparation, repointing, tooling, color, texture, sealant installation, and final cleaning. The government shall have 5 business days to review the mockup and provide comments. The contractor shall provide additional mockups as needed to achieve final approval at no additional cost to the government.

No production work shall begin until the proposed materials, mix designs, samples, installation procedures, and field mock-up have been reviewed and approved in writing by DOI and GSA. The approved mock-up shall establish the quality standard for the completed work and shall remain undisturbed until final acceptance.

5.0 Quality Requirements

Completed work shall match existing historic conditions, including:

• Cobblestone pattern.

• Joint profile.

• Color and finish.

• Overall appearance.

6.0 Project Constraints

• Only one ramp may be closed at a time.

• All four ramps receive vehicular traffic. Bedding mortar, pointing mortar, cobblestone installation methods, and curing procedures shall be designed and suitable for the anticipated vehicular traffic and loading conditions.

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 7 of 26

• Each ramp must be returned to service before another ramp closure begins.

• The Contractor shall provide and maintain barriers, warning signs, traffic-control measures, and temporary protections necessary to prevent vehicles and pedestrians from entering closed work areas.

• The Contractor shall maintain safe pedestrian access and protect building operations.

7.0 Deliverables

The Contractor shall provide:

• Work schedule.

• Safety plan.

• Existing condition documentation.

• Mortar samples and product data.

• Weekly Progress reports

• Final inspection report.

• Warranty documentation.

8.0 Acceptance Criteria

The work will be accepted when:

• Cobblestones are securely reset and stable.

• Historic patterns are restored.

• Mortar joints are properly filled and tooled.

• Sealant joints are complete.

• No damage exists to adjacent historic materials.

• Work areas are clean and all deficiencies are corrected.

9.0 Warranty

The Contractor shall provide a minimum one-year workmanship warranty covering installation defects, loose pavers, failed joints, and other deficiencies resulting from the Contractor’s work.

General Notes:

1. The Prime Contractor must attend an onsite walk-through of space to ensure they understand the scope of work and existing conditions

2. The Contractor’s masonry supervisor demonstrates at least five years of successful experience specifically involving historic masonry or historic cobblestone restoration

3. All materials and practices used must be in accordance with manufacturer recommendations and governing regulations.

4. All outages or other impacts to building use must be submitted to the COR at least 10 business days in advance and must be approved by the COR in writing by email prior to taking place.

5. The Prime Contractor must always have their own employee(s) onsite in a supervisory position that one of their subcontractors is working should that be the case.

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 8 of 26

6. Contractor Qualifications: Firm, company and/or principal specializing in this scope of work with not less than 5 years of documented successful experience.

7. Contractor personnel will conduct themselves in a manner that reflects favorably upon the Contractor, the Office of Facilities and Administrative Services, and the Department of the Interior. The Contractor and its personnel will comply with the guidelines and requirements established by Departmental physical-security officials.

8. All practices must be in accordance with all relevant safety standards including but not limited to OSHA requirements, and the GSA P100 standard (including all standards and codes incorporated by reference).

9. The contractor will be responsible for providing all required PPE and safety equipment.

10. Contractor represents, by acceptance of a contract, that it has thoroughly researched all applicable codes and regulations regarding this scope of work.

11. All waste products will become the property of the contractor for removal and must be disposed of in accordance with all local, state, and federal rules and regulations including (where applicable) the US Department of Transportation Federal Motor Carrier Safety Regulations

(FMCSR).

12. The contractor is expected to secure pricing for all associated labor and components at time of contract acceptance. Any price increases from the date of contract are the Contractor’s responsibility.

13. The Ramp D loading dock can be used only for loading and unloading supplies and materials and only after coordination with the COR. The loading dock capacity is restricted to a 24-foot box truck.

Section D - Packaging and Marking

All required submittals shall be delivered to the Primary Contracting Officer’s Representative (COR) listed in Section G herein. All required submittals shall contain the following markings, if applicable:

1. Name and address of the contractor

2. Contract number

3. Description of item submitted

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 9 of 26

Section E - Inspection and Acceptance

CLIN 0001

INSPECT AT: Destination

INSPECT BY: Government

ACCEPT AT: Destination

ACCEPT BY: Government

CLIN 0002

INSPECT AT: Destination

INSPECT BY: Government

ACCEPT AT: Destination

ACCEPT BY: Government

CLIN 0003

INSPECT AT: Destination

INSPECT BY: Government

ACCEPT AT: Destination

ACCEPT BY: Government

CLIN 0004

INSPECT AT: Destination

INSPECT BY: Government

ACCEPT AT: Destination

ACCEPT BY: Government

CLAUSES INCORPORATED BY REFERENCE

52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements (Apr 1984)

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 10 of 26

52.236-12 Cleaning Up (Apr 1984) 52.236-13 Accident Prevention (Nov 1991) 52.246-12 Inspection of Construction (AUG 1996) 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (AUG 1996)

CLAUSES INCORPORATED BY FULL TEXT

Pursuant to FAR 52.246-12, Inspection of Construction (AUG 1996), all work described in Section C of this solicitation, and its attachments, to be delivered under this contract are subject to final inspection and acceptance by an authorized representative of the government. The authorized representative of the government is the Primary COR listed in Section G of this contract.

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 11 of 26

Section F - Deliveries or Performance

Place of Delivery: The construction repair will be completed at the location specified in the Statement of Work located in Washington DC 20240.

Customer Point of Contact(s) for construction:

Primary COR: TBD

Delivery Date: All construction work, including cleanup, shall be completed twelve months after contract award.

CLAUSES INCORPORATED BY REFERENCE

52.211-13 Time Extensions (SEPT 2000) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.242-14 Suspension of Work (APR 1984)

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract immediately after contract award, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than twelve months days after contract award.

(End of Clause)

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 12 of 26

Section G - Contract Administration Data

Contract Administration Data. The Contracting Officer is responsible for the administration of this contract and, alone, is authorized to take actions on behalf of the Government that result in changes in the terms of the contract.

Contracting Officer: Xanthe Otterstedt Email: xanthe_otterstedt@ibc.doi.gov Phone: 703-914-3719

Other Relevant Points of Contract:

Primary COR: TBD

CLAUSES INCORPORATED BY FULL TEXT

DIAR 1432.903 RESPONSIBILITIES

The CO may modify the timing of payment specified in paragraph (a)(1)(i) and (ii) of the clause FAR 52.232-26, Prompt Payment for Fixed-Price Architect-Engineer Contracts, and/or paragraph (a)(1)(i) and

(ii) of the clause at FAR 52.232-27, Prompt Payment for Construction Contracts, as appropriate, to provide for a period shorter than 30 days (but not less than 7 days) for making contract financing payments based on geographical site location, workload, contractor ability to submit a proper request for payment, or other factors. When considering a modification to these FAR standard(s), the CO should alert the finance and program officials involved in the payment process to ensure that such shorter contract payment terms to be specified in the solicitation and resulting contract will be met. A CO determination justifying a shorter payment period must be documented in writing and incorporated into the solicitation/contract file.

Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP) (FEB 2021)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

Invoices must include, as a minimum, the following information:

1. Contractor Name, Address, Contact Information

2. Invoice Date and Invoice Number

3. Contract Number

4. CLIN/Item number of deliverable

5. Description of Deliverable, Work, or Services Performed mailto:xanthe_otterstedt@ibc.doi.gov https://www.ipp.gov/

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 13 of 26

6. Quantity and Firm Fixed Price of Deliverable

7. Date Deliverable was Provided to the Government for Inspection and Accepted

8. Period of Performance/Milestones Dates Applicable

The contractor is responsible for ensuring invoices submitted are accurate and complete.

Additional supporting documentation MAY BE REQUESTED at the discretion of the COR or CO.

The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 – 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone

(866) 973-3131.

A Release of Claims is required IAW 1452.204-70 Release of Claims, after completion of work and prior to final payment.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause) mailto:IPPCustomerSupport@fiscal.treasury.gov

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 14 of 26

Section H – Special Contract Requirements

Compliance with OSHA-Govt owned Facilities/Equipment

"Compliance with Occupational Safety and Health Act -- Government-Owned

Performance of work hereunder shall comply with the provisions of the Occupational Health and Safety Act of 1970, as amended (OSHA). If, at any time during the performance of this contract, the Government- furnished facilities and/or equipment do not conform to OSHA standards, the contractor must so notify the Contracting Officer, in writing, including a recommendation of the corrective action needed.

Accident Reporting

Accident Reporting - If an accident occurs on Government-controlled facilities, a report must be provided to the Contracting Officer's Representative and the Contracting Officer within 48 hours. An accident is defined as an event which causes injury, illness, or loss or damage to Government-owned or private property. The contractor will cooperate with any ensuing Government accident investigation.

List of subcontractors (Construction)

For purposes of monitoring compliance with the insurance and payroll reporting requirements of this contract, the contractor shall furnish a listing of all subcontractors to the Contracting Officer within 5 business days after contract award.

DOI CLAUSE – NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE

ASSESSMENT REPORTING SYSTEM (DEC 2015)

1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The

Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the CPARS for Government use in evaluating past performance as part of a source selection action.

3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO).

Information in the report must be protected as source selection sensitive information not releasable to the public.

4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

a. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.

https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.cpars.gov/ https://www.cpars.csd.disa.mil/ https://www.cpars.gov/

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 15 of 26

b. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

c. All information provided should be reviewed for accuracy prior to submission.

d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in CPARS-RC marked as “Pending” with or without comments and whether or not it has been closed.

f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

6. The following guidelines apply concerning your use of the past performance evaluation:

a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.

8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

(End of Notice)

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 16 of 26

Section I - Contract Clauses

The contractor must comply with the following FAR, DIAR, and local clauses that apply to this acquisition. This solicitation document and incorporated clauses are those in effect through FAC 2026-01, Effective 03/13/2026.

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisiton.gov/

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management (NOV 2024) 52.204-9 Personal Identity Verification of Contractor Personnel (JAN 2011) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.212-4 Terms and Conditions—Commercial Products and Commercial Services (May 2026) 52.215-8 Order of Precedence--Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-14 Limitations on Subcontracting (OCT 2022) 52.219-28 Postaward Small Business Program Rerepresentation (JAN 2025) 52.222-6 Construction Wage Rate Requirements (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination-Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-90 Addressing DEI Discrimination by Federal Contractors (DEVIATION DATE) 52.225-9 Buy American-Construction Materials (OCT 2022) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (MAY 2024) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.228-15 Performance and Payment Bonds-Construction (JUN 2020) 52.229-3 Federal, State and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-16 Progress Payments (NOV 2021) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) https://www.acquisiton.gov/

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 17 of 26

52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.243-5 Changes and Changed Conditions (APR 1984) 52.246-21 Warranty of Construction (MAR 1994) – Alternate I (APR 1984) 52.249-10 Default (Fixed-Price Construction) (APR 1984)

DIAR CLAUSES INCORPORATED BY REFRENCE

1452.201-70 Authorities and Delegations (SEP 2011) 1452.203-70 Restrictions and Endorsements (JUL 1996) 1452.204-70 Release of Claims (JUL 1996)

CLAUSES INCORPORATED BY FULL TEXT

52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 18 of 26

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if– (A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material.

The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together.

Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 19 of 26 combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

"None"

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that- (i)The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1)The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2)For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3)The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2)For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3)The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 20 of 26

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison Construction Material Description

Unit of Measure Quantity Price (dollars)*

Item1:

Foreign construction material Domestic construction material Item2:

Foreign construction material Domestic construction material

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]

(End of Clause)

52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 21 of 26

(b) The use in this solicitation or contract of any clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of Clause)

DIAR CLAUSES INCORPORATED BY FULL TEXT

DAVIS BACON ACT (DBA) WAGE DETERMINATION (WD)

Construction Wage Determination

(i) Reference FAR 52.222-6 Construction Wage Determination General Decision Number

DC20260002 Modification 3, Dated May 18, 2026 applies to this solicitation and/or purchase order and/or contract.

(ii) Wage Determination may be downloaded from the following websites: SAM.gov Wage Determinations Construction (DBA) https://sam.gov/search/?index=dbra&page=1&pageSize=25&sort=-modifiedDate&sfm%5BsimpleSearch%5D%5BkeywordRadio%5D=ALL&sfm%5BsimpleSearch%5D%5BkeywordEditorTextarea%5D=&sfm%5Bstatus%5D%5Bis_active%5D=true https://sam.gov/search/?index=dbra&page=1&pageSize=25&sort=-modifiedDate&sfm%5BsimpleSearch%5D%5BkeywordRadio%5D=ALL&sfm%5BsimpleSearch%5D%5BkeywordEditorTextarea%5D=&sfm%5Bstatus%5D%5Bis_active%5D=true

Document Title Stewart Lee Udall Building Cobblestone Ramp Repair Page 22 of 26

Section J - List of Documents, Exhibits, and Other Attachments

Section K - Representations, Certifications, and Other Statements of Bidders

PROVISIONS INCORPORATED BY REFERENCE

52.236-28 Preparation of Proposals-Construction (OCT 1997)

Section L - Instructions, Conditions, and Notices to Bidders

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov/

(End of Provision)

PROVISIONS INCORPORATED BY REFERENCE

52.201-1 Acquisition 360: Voluntary Survey (SEP 2023) 52.204-7 System for Award Management (NOV 2024) 52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work (MAY 2014) 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999)

DIAR PROVISIONS INCORPORATED BY REFRENCE

1452.215-71 Use and Disclosure of Proposal Information – Department of the Interior (APR 1984)

PROVISIONS INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed Price (FFP) contract resulting from this solicitation.

(End of Provision)

52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS

(MAY 2014)

https://www.acquisition.gov/

Document Title Stewart Lee Udall Building Cobblestone Ramp…