B09_-_140D0423Q0812__QA_-_A00002_0002.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Hazardous Tree & Debris Removal Services Federal contract opportunity
- Solicitation number
- 140D0423Q0812
About this file
This document contains questions and answers regarding Solicitation Number 140D0423Q0812 for hazardous tree and debris removal services issued by the Department of the Interior Departmental Offices Interior Business Center. The solicitation requires contractors to remove hazardous trees and debris on an emergency basis within four hours of notification, as well as perform vegetation management and scheduled tree removal services. The incumbent contractor is Riverbend Landscapes, LLC, which was awarded $403,220 under the previous contract. The solicitation is seeking firm fixed prices for debris removal measured by cubic yard, vegetation management on a time and materials basis, and emergency tree removal also on a time and materials basis. Contractors must have a certified arborist and Maryland tree expert on staff.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_140D0423Q0812A00002_Amended_Solicitation_0002.pdf | ||
| B08_Attachment_A_SOW_Hazardous_Tree_Debris_Removal_(Final)(20230726)_0002.docx | DOCX document | |
| Sol_140D0423Q0812_Amd_0002.pdf | ||
| B08_140D0423Q0812_Amendment_A00001_(Final)(20230710)_0001.pdf | ||
| Sol_140D0423Q0812_Amd_0001.pdf | ||
| B08_Attachment_B_Tree_Details_with_GPS.xlsx | XLSX spreadsheet | |
| B08_Attachment_C_Wage_Determination_2015-4281.pdf | ||
| B08_140D0423Q0812_(Final)(20230706).pdf | ||
| B08_Attachment_A_SOW_Hazardous_Tree_Debris_Removal_(Final)(20230706).docx | DOCX document | |
| Sol_140D0423Q0812.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| No. | Contractor Questions | Government Responses |
| 1 | CLIN 0004 emergency tree removal. Does the contractor have to bid this part my company is out of state and can’t be there in 4 hours? | The requirment for contractors to be able to respond to an emergency within 4 hours is a mandatory requirement, and any contractor that cannot meet this requirement will not be determined technically capable of meeting this requirement. |
| 2 | Would there be a possibility to set this aside for SDVOSB? | The set-aside for this procurement will remain unchanged. |
| 3 | In the SOW it states that: Emergency Tree Removal (Time and Materials) - Contractor shall respond to an emergency within Four (4) hours of COR notifying contractor. Including nights, weekends, and Holidays. All wood, Debris, and root ball (If tree has up rooted) must be removed and hauled off NPS property. Contractor is responsible for their own traffic control. (Emergency will be identified by the COR). Our offices are set up about 6.5 hours from Washington DC and crews could be onsite in an emergency event within 12-24 hours. Would we be qualified to bid on this contract? | The requirment for contractors to be able to respond to an emergency within 4 hours is a mandatory requirement, and any contractor that cannot meet this requirement will not be determined technically capable of meeting this requirement. |
| 4 | Is there any preference in how you would like the proposal to be submitted? | Please submit quotes via email to laura.kattner@ibc.doi.gov and jonathan.chisholm@ibc.doi.gov |
| 5 | Please provide me with the details of the incumbent company, what is the current yearly contract award. | Incumbent Company is Riverbend Landscapes, LLC and yearly contract award is $403,220.00 |
| 6 | If we have additional questions after the site visit on Tuesday, July 25, are we able to submit those and get answers prior to submitting our proposal on the 28th? | Comment: Questions from the site visit are addressed as part of this amendment. |
| 7 | Given that this solicitation is subject to FAR 52.222-54, and the contractor and their partners/subcontractors are to be enrolled in and use e-Verify, is the verification of compliance to be submitted in technical capabilities & approach response? | Compliance should be submitted to the Contracting Officer's Represenative with the Contracting points of contact carbon copied. |
| 8 | It appears that there may be wood and debris that remain unaddressed from last year’s solicitation that was contracted. Could you provide an insight on this scope of work overlap between last year’s solicitation with the current solicitation? | Work under the scope of the previous order has been completed. The contractor will be responsible for the removal of debris under this requirement as instructed by the Government and will be compensated for work completed on per cubic yard of debris removal basis. |
| 9 | Is the remnant debris pile going to be further reduced (under the previous contract), or is the pile as observed now to be completely removed under this contract? | The previous award has no bearing on this requirement. Debris removal will occur inaccordance with the statement of work for this requirment up to the not exceed threshold established under the corresponding contract line item number. |
| 10 | What is the unit of measure to bid 0002 Debris Removal Services? | Cubic Yards. |
| 11 | What is the unit of measure to bid 0003 Vegetation Management? | This is a time and materials line item. Vendors should provide the Government with an hourly rate for any applicable labor categories that will be billed under this requirement. If unique or unusual equipment is required to be deployed in response to an assignment under Contract Line Item Number (CLIN) 00003 any associated quoted costs will be reviewed by the Government for reasonableness before work commences. |
| 12 | What is the unit of measurement to bid 0004 Emergency Tree Removal? What equipment is expected? Verbal conversation yesterday on site alluded to any equipment up to and including crane and log loaders, traffic control TMA trucks, etc. | This is a time and materials line item. Vendors should provide the Government with an hourly rate for any applicable labor categories that will be billed under this requirement. If unique or unusual equipment is required to be deployed in response to an assignment under Contract Line Item Number (CLIN) 0004 any associated quoted costs will be reviewed by the Government for reasonableness before work commences. |
| 13 | How are we to bid a firm fixed price to 1001 Tree Removal Services – Option Period 1, when the trees will be an entirely different scope, location, and quantity? | Option Period 1 will be removed in its entirety. |
| 14 | Note to Contractors: See the Updated SOW | Section III of the SOW adds a requirement for the contractor to have a Society of Arborculture aborist and Maryland tee expert on staff. |