Questions_and_Answers___Final_0002.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
ROOFING PROJECT AT MARIANO LAKE Federal contract opportunity
Solicitation number
140A2324R0094
Issued by
Department of the Interior Bureau of Indian Affairs Bureau of Indian Education

About this file

This document is a Questions and Answers log for Solicitation #140A2324R0094 for a Roofing Project at Mariano Lake. The solicitation is being issued by the Department of the Interior, Bureau of Indian Affairs, Bureau of Indian Education. The questions cover topics such as revising the scope to address drainage issues, confirming ceiling insulation details, and addressing leakage issues on the library roof. The government has provided responses indicating the contractor can propose recommended solutions in some cases, and that the library roof repairs are required to address leakage. The solicitation also requires R-30 insulation on the dormitory building, despite the existing 1/2" styrofoam which may require additional build-up. Overall, this document provides clarification and responses to contractor questions on various aspects of the roofing project requirements.

View the file

Other files for this federal contract opportunity

Other files attached to ROOFING PROJECT AT MARIANO LAKE, newest first.
File Type Posted
Sol_140A2324R0094_Amd_0002.pdf PDF
Sol_140A2324R0094_Amd_0001.pdf PDF
SF-25A_Payment_Bond_Form.pdf PDF
B08_Questions_and_Answers_Log.xlsx XLSX spreadsheet
A04_STATEMENT_OF_WORK.docx DOCX document
B08_BIA_FEDERAL_HEALTH_AND_SAFETY_CODES.pdf PDF
B08_SF-24_Bid_Bond_Form.pdf PDF
Sol_140A2324R0094.pdf PDF
B08_SF-1413_Statement_and_Acknowledgement_Form_(Subcontracting).pdf PDF
B08_Material_Approval_Submittal_BIE.pdf PDF
B03_WAGE_DETERMINATION__NM20240024__07-26-2024.pdf PDF
SF-25_Performance_Bond_Form.pdf PDF
B08_Progress_Schedule.pdf PDF
B08_Progress_Report.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Questions and Answers Log for Solicitation # 140A2324R0094

NumberQuestionDate Sent to CORAnswerDate Answered
1Building Number 414 Boiler room: Would the government consider revising the scope to demo the deck, add scupper and down spout, and full taper and crickets in order to correct the system for proper drainage? The current scope and magnitude does not allow proper correction.8/14/24The contractor can propose their recommended

solution.

2 Building 413 Dormitory: Can the government confirm that insulation on the ceiling is R-30 Batt Insulation? The ciling is hard lid so it could not be verified without destructive investigation. 8/14/24 The Government cannot confirm the ceiling insulation on bldg 413.

3Building 1399 Gym Roof (mechanical well): The crickets are too small for proper drainage. Would the government agreee to demo of existing PVC leaving existing taper system and installing new cricket system?8/14/24Contractor can propose their recommended solution on Bldg. 1399.
4Building 1400 Library: This standing seam roof leaks at HVAC locations. HVAC maintenance personnel could make a permanent fix to seams at these locations with a recommended product. Would the government consider removing this Building from the scope of work?8/14/24Government wants to leakage areas repaired to

ensure no leakages.

5What are they going to do about the library. There was conversation that it was going to be removed from the SOW. Will that be the case.The Library will remain in SOW
6On the dormitory, R30 is requested, however right now there is only 1/2" styrofoam. A build up will be required if R30 is installed. Is this what you would like?Government requires R30