B08_STATEMENT_OF_WORK_TREE_TRIMING__REMOVAL_rev_0001.pdf
PDF 71 KB Posted
- Attached to
- Tree Trimming and Removal, Tuba City
- Solicitation number
- 140A2324Q0019
About this file
This statement of work outlines tree trimming and removal services required at the Tuba City Boarding School in Arizona. The contractor will trim 20 cottonwood trees by removing overhanging branches, and remove one cottonwood tree identified as tree number 20 on the attached map. The contractor must perform the work in accordance with industry standards, dispose of all debris properly, and complete the project within 120 days of notice to proceed between 7:30am and 4:30pm Monday through Friday. The contractor is responsible for safety precautions and cleanup. This supports solicitation number 140A2324Q0019 issued by the Department of the Interior Bureau of Indian Affairs Bureau of Indian Education for tree trimming and removal services at the Tuba City Boarding School location.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140A2324Q0019_Amd_0001.pdf | ||
| Amend_01-Q_and_A_0001.pdf | ||
| Sol_140A2324Q0019.pdf | ||
| B08_Wage_Determination_2015-5465.pdf | ||
| B08_STATEMENT_OF_WORK_TREE_TRIMING__REMOVAL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK: TREE TRIMING AND TREE REMOVAL AT BIE – TUBA CITY BOARDING SCHOOL.
I. PURPOSE
BIE – TUBA CITY BOARDING SCHOOL HAS A REQUIREMENT TO TRIM 20 COTTONWOOD TREES
AND REMOVAL OF ONE (1) OLD COTTONWOOR TREE IN ACCORDANCE WITH THE ATTACHED
STATEMENT OF WORK (SOW).
II. CONTRACTORS TASKS AND RESPONSBILITIES:
CONTRACTORS SHALL PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, SUPERVISION AND OTHER
NECESSARY INCIDENTIALS TO COMPLETE THE WORK AS REQUIRED.
A. TWENTY COTTONWOOD TRIMS: TRIM OVERHANGING BRANCHES. TWENTY TREES TO BE
TRIMMED ARE LOCATED AROUND THE GROUNDS OF THE JUNIOR HIGH SCHOOL, BIG GYM –
NORTH CAMPUS.
B. REMOVE/DEMOLISH ONE (1) COTTONWOOD TREE IDENTIFIED AS TREE NUMBER TWENTY
(20) ON THE ATTACHED MAP/DRAWING.
C. ESTIMATED HEIGHTS OF THE TREES ARE 40 FT. TO 60 FT. HIGH. APPROXIMATE WIDTH: 30 FT.
WIDE TO 45 FT. WIDE.
D. PERFORMANCE OF WORK SHALL BE IN ACCORDANCE WITH INDUSTRY STANDARS.
E. CONTRACTOR SHALL REMOVE CUT BRANCHES, LIMBS, DEBRES, TREE TRUNK (TREE #20)
ETC., AND PILE THE DEBRI ACROSS THE STREET FROM THE NORTH CAMPUS. DEBRI TO BE
PILED ON THE CORNER OF WEST CEDAR AND MAPLE STREET. ONCE TREE BRANCHES ARE
REMOVED, ALL WOOD CHIPS, BRUSHES, LIMBS, AND LOGS, SHALL BE DISPOSED AT THE
DESIGNATED SITE TO ENSURE 100% RECYCLING IS MET FOR WOODY MATERIAL.
F. UNDER NO CIRCUMSTANCES SHALL THE CONTRACTOR PERFORM WORK NEAR HIGH
VOLTAGE TRANSMISSION OR DISTRIBUTION LINES. LIMBS SHALL BE FELLED DIRECTLY AWAY
FROM POWER OR COMMUNICATIONS LINES, STRUCTURES, VEHICULAR OR PEDESTRIAN
RIGHTS-OF-WAY, OR HORTICULTURAL PLANTINGS.
III. PERIOD OF PERFORMANCE/SCHEDULE:
A. PERIOD OF PERFORMANCE SHALL BE 120 DAYS FROM NOTICE TO PROCEED.
B. WORK SCHEDULE: MONDAY-FRIDAY, 7:30 AM- 4:30 PM. AFTER HOURS AND WEEKEND
WORK SHALL BE ARRANGED WITH THE COR.
C. IF THERE IS INCLEMENT WEATHER OR EXTENUATING CIRCUMSTANCES DURING THE WORK
PERIOD, THE GOVERNMENT MAY EXTEND THE TIME PERIOD IN WHICH THE WORK WILL BE
COMPLETED. ALL EXTENSIONS SHALL BE IN WRITING AND SIGNED BY THE CONTRACT
SPECIALIST.
IV. LOCATION: BIE – TUBA CITY BOARDING SCHOOL, 306 MAIN STREET, TUBA CITY, ARIZONA 86045, COCONINO COUNTY, NAVAJO RESERVATION.
V. GENERAL REQUIREMENTS:
A. THE CONTRACTOR SHALL NOT PERFORM WORK OF ANY KIND IF THERE IS A REASONABLE
POSSIBILITY OF LIMBS OR DEBRIS DAMAGING VEHICLES, PROPERTY OR IF THE WORKER’S
SAFETY IS PUT AT RISK. THE CONTRACTOR SHALL BE HELD LIABLE FOR ALL DAMAGES TO
VEHICLES, PROPERTY, AND PEDESTRIANS CAUSED BY FALL DEBRIS DURING THE EXECUTION
OF THE WORK. THE CONTRACTOR SHALL MAINTAIN INSURANE LIABILITY COVERAGE AS
REQUIRED.
B. NO ALCOHOL, DRUGS OR TOBACCO PRODUCTS ARE ALLOWED ON THE TCBS CAMPUS.
C. CONTRACTOR SHALL BE RESPONSIBLE FOR THE SAFETY OF THE SITE LOCATION WHICH MAY
INCLUDE INSTALLATION, FENCING, BARRICADES AS WELL AS SIGNAGE TO WARN EMPLOYEES
AND THE PUBLIC OF THE ON-GOING PROJECT WORK.
D. CONTRACTOR SHALL BE RESPONSIBLE FOR CLEANUP AFTER EACH DAY. THE CONTRACTOR
BEARS ALL RESPONSIBILITY FOR AND ALL ASSOCIATED OR RELATED COST WITH THE
REMOVAL AND DISPOSAL OF ALL DEBRIS.
VI. DELIVERY REQUIREMENTS:
A. CONTRACTOR SHALL COMPLETE THE PROJECT IN AN EFFICIENT, CODE-COMPLIANT MANNER
THAT FULLY MEETS THE PROJECT’S PERFORMANCE, COST, AND TIME-LINE OBJECTIVES.
B. ADMINISTRATIVE SERVICES, DURING CONSTRUCTION INCLUDING COORDINATION OF
PRODUCT SUBMITTALS, REVIEWS, AND APPROVALS, AND COORDINATING AND
DOCUMENTING WEEKLY PROJECT STATUS MEETINGS.
C. PURCHASE AND MANAGE THE DELIVERY AND STAGING OF CONSTRUCTION MATERIALS.
D. PROVIDE ON-GOING CONSTRUCTION STATUS AND COMPLETION UPDATES IN
COORDINATION WITH THE COR.
E. COORDINATE WITH THE COR FOR PROJECT INSPECTORS FOR SCHEDLING OUTAGES THAT
IMPACT THE CAMPUS PERSONNE.