140A2322R0030__WES_Roofing_-_Question_Log_0002.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
BIE/NMNS/FM/INSTALL NEW TPO ROOFING EXS
Solicitation number
140A2322R0030
Issued by

About this file

This document contains a question log and related federal contract opportunity for roofing repairs at Wingate Elementary School. The question log addresses contractor questions on project details such as the use of a cover board, wind uplift requirements, reuse of coping caps and collector heads, separation of taxes in the price schedule, acceptable membrane material, replacement of walkways, and reattachment of ground wires. The related federal contract opportunity is solicitation number 140A2322R0030 for installation of a new TPO roofing system at BIE/NMNS/FM. The small business set-aside opportunity closes on May 13, 2022. Interested contractors should schedule a site visit with the contracting officer's representative and submit a two-volume response including price and technical proposals to the contracting officer by May 4 for any additional questions. The Department of the Interior Bureau of Indian Affairs Bureau of Indian Education is the contracting agency.

View the file

Other files

File Type Posted
Sol_140A2322R0030_Amd_0003.pdf PDF
Sol_140A2322R0030_Amd_0002.pdf PDF
IMG_0018_0001.JPG JPG image
IMG_0015_0001.JPG JPG image
Sol_140A2322R0030_Amd_0001.pdf PDF
IMG_0016_0001.JPG JPG image
IMG_0009_0001.JPG JPG image
Attachment_3_-_SF-24_Bid_Bond_Form.pdf PDF
Attachment_5_-_SF-25A_Payment_Bond_Form.pdf PDF
Attachment_1_-_Wage_Rates.pdf PDF
Sol_140A2322R0030.pdf PDF
Attachment_2_-_Question_Log.xlsx XLSX spreadsheet
Attachment_4_-_SF-25_Performance_Bond_Form.pdf PDF
Attachment_6_-_SF-1413_Statement_and_Acknowledgement_Form_(Subcontracting).pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Question Log for WES Roofing Repairs
Contractor's QuestionGovernment Response
1Are we installing a cover board with recover?This is an overlay only. No demo of existing.
2Is there a peak wind uplift required if so whats the peak?Contract to determine per Structural/Construction design codes for location.
3Is coping cap being reused?Yes.
4Is collector heads being added to over flow scuppers?Yes.
5On price Schedule are we including Navajo nation taxes and NM state taxes togetger?Keep the Tax lines separated they are both at difference percentages.
6Is Carlisle syntec 60 mil TPO accetable for membrane?White 60 mil TPO membrane is noted in Statement of Work.
7Will the walk ways be replaced?Yes, replace the walkpads with new. Adhere to TPO membrane.
8What will be used to reattach the ground wires back to the roof?use a TPO strips not the metal braces that need to be screwed into the TPO
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30

File details come from the government source that posted it. Updated .