This document is an Amendment of Solicitation/Modification of Contract (Standard Form 30) and associated Questions and Answers for a federal demolition project.

Amendment Details and Solicitation Information:

The amendment, numbered 0002 with an effective date of 05/11/2026, pertains to Solicitation No. 140A1626Q0040 for BIA Rosebud Building No. Twenty Eight (28) Demolition. The issuing office is BIA CENTRAL 00016 located at 12201 Sunrise Valley Drive, Reston, VA 20192. The original solicitation is not extended. A question-and-answer log has been provided, and the quote due date has been extended to 05 June 2026 at 1900 Eastern Time (amended from the original date of 5/25/26, which falls on a federal holiday). Contractors must acknowledge receipt of the amendment by completing the form and returning it or by separate letter/electronic communication prior to the specified deadline.

Submission and Scope Requirements:

The amendment confirms that a technical proposal is not required for submission. Offerors must submit only Representations and Certifications, the Indian Affairs Indian Economic Representation Form, and pricing. The project involves demolition and hazardous waste management of a collapsed building structure containing lead-contaminated debris, asbestos-containing materials, fuel oil tanks, and a boiler buried beneath stone rubble. Contractors have the option to either treat hazardous lead debris using methods like Blastox or simply remove the material without treatment and dispose of it in an EPA-approved landfill. Estimates for debris quantities can be established by reviewing the plans and specifications posted on SAM.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Kurt Egner

See continuation page

BIA CENTRAL 00016

12201 Sunrise Valley Drive Contracting Office Mail Stop-244 Reston VA 20192

A16

140A1626Q0040

05/11/2026

05/11/2026

1 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140A1626Q0040/0002

A question-and-answer log has been provided.

The due date for quote submittal has not changed: 05 June 2026 at 1900 Eastern Time.

Solicitation No. 140A1626Q0040 – BIA Rosebud Building No. Twenty Eight (28) Demolition

Questions and Answers

1. The indicated proposal due date is 5/25/26 which is a federal holiday. Will the government consider changing the proposal due date to 5/29/26 to allow adequate time for the government to respond to questions and contractors to incorporate those responses into their proposals?

Answer: The quote due date has been extended to 05 June 2026.

2. Can you please confirm that a technical proposal is not required for this submission. We see the only requirements in the RFP include Reps and Certs, the Indian Affairs Indian Economic Representation Form, and Pricing. Is this correct?

Answer: A technical proposal is not required. The only items required in the submittal package are Reps and Certs, the Indian Affairs Indian Economic Representation Form, and pricing.

3. Rosebud Site – The specifications call out for the hazardous lead waste debris to be treated with Blastox (or similar) and rendered non-hazardous. If a pilot study and/or actual treatment proves ineffective at rendering the debris non-hazardous, will a contract modification be issued to have the debris disposed of as hazardous waste?

Answer: The contractor has the option of simply removing the material without treatment and disposing of it in an EPA approved landfill.

4. Can the government provide the hazardous material survey that contain the lead TCLP results, ACM testing results and quantities of lead and ACM debris anticipated? With the stone walls pushed into the basement and on top of any hazardous debris, there is no way for the contractor to observe, estimate, or accurately determine the quantities of lead and potential ACM debris remaining within the overall debris pile. The lead TCLP results are also needed for estimating the potential quantities of Blastox and potential effectiveness or treating lead debris.

Answer: Estimates can be established from reviewing the plans and specifications that are attached to the solicitation posted on SAM.gov.

5. With the stone walls pushed into the basement and on top of any hazardous debris, there is no way for the contractor to observe, estimate, or accurately determine the quantities of

Solicitation No. 140A1626Q0040 – BIA Rosebud Building No. Twenty Eight (28) Demolition lead and potential ACM debris remaining within the overall debris pile. Can the government provide estimated quantities of lead and ACM debris anticipated for this job?

Answer: Please, see question and answer to number five (5).

6. Was the wood trim around windows/openings containing lead paint removed from the stone walls before pushing them into the basement or is the wood trim material now disbursed and buried within the stone rubble?

Answer: Please assume that the wood trim material is now buried the remaining rubble.

7. Was the “2 to 3 ft. of lead contaminated plaster debris” removed from the building basement before pushing in the stone walls or does the debris remain under the stone rubble?

Answer: No, please consider that the plaster debris is still in the remaining rubble.

8. Were either the fuel oil tanks (and the contents) or the boiler removed from the building basement before pushing in the stone walls or were the crushed/buried under the stone rubble?

Answer: No, please assume the fuel oil tanks and boiler still remains in the rubble.

9. Can the Contractor choose to dispose of the hazardous lead debris as hazardous waste and forego the effort and time to treat the hazardous lead fire debris?

Answer: Yes, this is an option that the contractor has to simply remove the material without treatment and dispose of it in an EPA approved landfill.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .