This is Amendment 0002 to RFQ #140A0525Q0004 for Remediation Services within the Village of Tuntutuliak, Alaska, issued by the DOI Bureau of Indian Affairs Pacific Contracting Office in Sacramento. The amendment extends the quote due date to January 29, 2025 at 0900 Pacific and includes a Q&A document addressing 13 questions from potential offerors.
Key details from the Q&A include: the scope of work does not include any tank or piping work; soil samples will be analyzed for DRO, PAH, and VOCs (GRO analysis not required); sample locations will be determined during project planning with BIA and DEC involvement; work will occur within BIA/school property boundaries; no surface water samples are needed; and the contractor is responsible for disposal of investigation-derived waste per DEC requirements. The period of performance is February 17, 2025 to June 30, 2026. Interested parties must complete blocks 8 and 15A-C of the amendment and include it with their quotation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08_Solicitation_Rev1_1_15_25_0001.pdf | ||
| Sol_140A0525Q0004_Amd_0001.pdf | ||
| Sol_140A0525Q0004.pdf | ||
| A05_-_PWS.pdf | ||
| IEE_Rep_Form.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140A0525Q0004 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
A13
Sacramento CA 95825
2800 COTTAGE WAY ROOM W2820
Contracting Office
DOI, BIA PACIFIC
A13
Sacramento CA 95825
2800 COTTAGE WAY ROOM W2820
Contracting Office
BIA PACIFIC 00013
01/15/20250002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/15/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of Amendment 0002 is to extend the due date and publicly release all questions that have been asked on the solicitation to date and the answers provided by BIA.
The due date and time for this RFQ is hereby changed to 1/29/25, 0900 PS.
All interested parties submitting a quotation must complete blocks 8 and 15A-C of this
Amendment AND INCLUDE the completed page 1 of this Amendment with their quotation. All questions about this amendment shall be emailed to jodi.zachary@bia.gov.
All terms and conditions of the solicitation remain unchanged.
Period of Performance: 02/17/2025 to 06/30/2026
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Jodi Zachary
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
RFQ# 140A0525Q0004, Amendment #2 Remediation Services within the Village of Tuntutuliak
Questions & Answers
1. Are any components of the tanks /piping currently in use? If no, has the product been removed from the tank/piping?
The SOW for Tuntutuliak does not include any tank or piping work
2. Are as-builts available to identify underground utility’s and/or fuel piping?
The SOW for Tuntutuliak does not include any tank or piping work
3. Can BIA provide any information regarding soil type, depth to groundwater and depth to permafrost?
BIA has no specific information for Tuntutuliak regarding soil, groundwater or permafrost
4. Task 2 indicates samples should be analyzed for DRO, PAH, and VOCs. ADEC Field Sampling Guidance 2024 Appendix F states GRO (and DRO, PAH, & VOCs) analysis is required when #1 or #2 Diesel is the contaminant of concern. Please confirm if GRO analysis is required for the project.
DEC has not required GRO analysis in the past. GRO analysis is not a requirement in this
RFQ.
5. Are DRO, VOCs, and PAHs the only analytes in this project?
These are the primary contaminants of concern for this project.
6. Have the locations for the sediment/soil samples been selected? Or is this part of the scope of work?
No, this will be discussed and agreed upon during project planning.
7. Have any soil sample sites been selected?
No, this will be discussed and agreed upon during project planning.
8. Will a Quality Assurance Project Plan (QAPP) be required?
Standard QA/QC practices; as required by Alaska DEC, the analytical laboratory and scientific professionalism, are expected. These should be established prior to fieldwork and sampling
RFQ# 140A0525Q0004, Amendment #2 Remediation Services within the Village of Tuntutuliak
Questions & Answers
9. “Plan fieldwork with BIA” – does this mean BIA staff will be present during fieldwork? Or does it mean that the BIA wants to be involved in the fieldwork planning?
BIA and DEC will be involved in planning the fieldwork.
10. Will access to neighboring properties be required, or will all field activities occur within the BIA/school property boundaries?
Access to neighboring properties should not be necessary.
11. Are wetlands maps available for the project area?
BIA does not have wetland maps of the property.
12. Will there be any surface water samples collected?
No
13. Is the contractor responsible the disposal, including shipping, of investigation derived waste including soils from borings and purge water from monitoring wells?
Yes, as required by DEC.